Use the following data to calculate the cost of goods sold: Work in process, beg. $38,000 Work in process, end.......... 31,0
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer- $ 132,000

Solution-

Formula-

Cost of goods sold = Beginning Inventory of Finished Goods + Cost of goods manufactured - Ending Inventory of Finished Goods

= $ 40,000 + $137,000 - $45,000

= $ 177,000 - $ 45,000

= $ 132,000 ( Answer)

Working Note-

1- Product Cost incurred during period = Cost of Material used + Direct Labour + Factory Overheard

= 52,000 + 37,000 + 41,000

= $ 130,000

2- Cost of Goods Manufactured = Product Cost incurred during period + Beginning Balance of WIP - Ending Balance of WIP

= 130,000 + 38,000 - 31,000

= 168,000 - 31,000

= $ 137,000

Add a comment
Know the answer?
Add Answer to:
Use the following data to calculate the cost of goods sold: Work in process, beg. $38,000...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Cost of Materials Used$60,000 Direct Labor costs $55,000 Factory Overhead $32,000 Work in Process, beg. $28,000...

    Cost of Materials Used$60,000 Direct Labor costs $55,000 Factory Overhead $32,000 Work in Process, beg. $28,000 Work in Process, end. $18,000 Finished Goods,beg. $28,000 Finished Goods, end. $18,000 What is Cost of Goods Sold?

  • Sleep Tight, Inc. manufactures comforters. The estimated inventories on January 1 for finished goods, work in...

    Sleep Tight, Inc. manufactures comforters. The estimated inventories on January 1 for finished goods, work in process, and materials were $38,000, $31,000 and $25,000 respectively. The desired inventories on December 31 for finished goods, work in process, and materials were $45,000, $37,000 and $22,000 respectively. Direct materials purchases were $560,000. Direct labor was $224,000 for the year. Factory overhead was $149,000. Prepare a cost of goods sold budget for Sleep Tight, Inc. Sleep Tight, Inc. Cost of Goods Sold Budget...

  • Cost of Goods Sold, The total cost of making and finishing a product.Cost of Goods Manufactured...

    Cost of Goods Sold, The total cost of making and finishing a product.Cost of Goods Manufactured Glenville Company has the following information for April: The cost of materials that are an integral part of the finished product.Cost of direct materials used in production $ 49,000 The wages of factory workers who are directly involved in converting materials into a finished product.Direct labor 55,000 All of the costs of producing a product except for direct materials and direct labor.Factory overhead 28,000...

  • eBook Cost of Goods Sold, Cost of Goods Manufactured Timbuk 3 Company has the following information...

    eBook Cost of Goods Sold, Cost of Goods Manufactured Timbuk 3 Company has the following information for March: Cost of direct materials used in production$36,000 Direct labor Factory overhead Work in process inventory, March 1 Work in process inventory, March 31 Finished goods inventory, March 1 Finished goods inventory, March 31 45,000 37,000 27,000 36,250 24,000 17,000 a. For March, determine the cost of goods manufactured. Using the data given, prepare a statement of Cost of Goods Manufactured. Timbuk 3...

  • Sleep Tight, Inc., manufactures comforters. The estimated inventories on January 1 for finished goods, work in process,...

    Sleep Tight, Inc., manufactures comforters. The estimated inventories on January 1 for finished goods, work in process, and materials were $38,000, $33,000, and $26,000, respectively. The desired inventories on December 31 for finished goods, work in process, and materials were $45,000, $38,000, and $20,000, respectively. Direct materials purchases were $575,000, direct labor was $206,000 for the year, and factory overhead was $152,000. Prepare a cost of goods sold budget for Sleep Tight, Inc. Finished goods inventory, January 1 $ ____...

  • Schedule of Cost of Goods Manufactured and Sold The following amounts are available for 2016 for...

    Schedule of Cost of Goods Manufactured and Sold The following amounts are available for 2016 for Bourne Manufacturing Company Administrative salaries (non-factory)$140,000 70,000 82,000 44,000 60,000 34,000 350,000 36,000 24,000 114,000 Administrative rent (non-factory Advertising and promotion expense Depreciation-administrative Depreciation-factory Depreciation-selling Direct labor Factory rent Factory supplies used Finished goods inventory Ulanuary 1) 114000 Finished goods inventory (December 31) 104,000 28,000 38,000 26,000 40,000 Net delivered cost of materials purchased 276,000 52,000 1,690,000 144,000 Work in process inventary (Uanuary )36.000...

  • Cost of Goods Sold, Cost of Goods Manufactured Glenville Company has the following information for April:...

    Cost of Goods Sold, Cost of Goods Manufactured Glenville Company has the following information for April: Cost of direct materials used in production $ 41,000 Direct labor 53,000 Factory overhead 25,000 Work in process inventory, April 1 31,000 Work in process inventory, April 30 29,000 Finished goods inventory, April 1 20,000 Finished goods inventory, April 30 16,000 a. For April, determine the cost of goods manufactured. Using the data given, prepare a statement of Cost of Goods Manufactured. Glenville Company...

  • Cost of Goods Sold, Cost of Goods Manufacture Glenville Company has the following information for April:...

    Cost of Goods Sold, Cost of Goods Manufacture Glenville Company has the following information for April: Cost of direct materials used in production $39,000 Direct labor Factory overhead Work in process inventory, April 1 Work in process inventory, April 30 Finished goods inventory, April 1 Finished goods inventory, April 30 a. For April, determine the cost of goods manufactured. Using the data given, prepare a statement of Cost of Goods Manufactured. 49,000 30,000 24,000 37,000 27,000 21,000 Glenville Company Statement...

  • Exercise JoJo Co. had the following balances and information for October Beg finished goods inventory =...

    Exercise JoJo Co. had the following balances and information for October Beg finished goods inventory = $18 Beg. work in process inventory = $3 Beg, raw materials inventory = $9 End, finished goods inventory = $9 End. Work in process inventory = $6 End. raw materials inventory = $15 Raw material purchases = $OU Factory wages paid = $90 Indirect materials = $b Indirect labor $21 Other overhead costs = $54 Sales = $330 Predetermined overhead rate = 200% direct...

  • Cost of Goods Sold, Cost of Goods Manufactured Glenville Company has the following information for April:...

    Cost of Goods Sold, Cost of Goods Manufactured Glenville Company has the following information for April: Cost of direct materials used in production $39,000 Direct labor Factory overhead Work in process inventory, April 1 Work in process inventory, April 30 Finished goods inventory, April 1 Finished goods inventory, April 30 49,000 30,000 24,000 37,000 27,000 21,000 a. For April, determine the cost of goods manufactured. Using the data given, prepare a statement of Cost of Goods Manufactured. Glenville Company Statement...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT