Question

The production manager of Rordan Corporation has submitted the following quarterly production forecast for the upcoming fiscal year:

The production manager of Rordan Corporation has submitted the following quarterly production forecast for the upcoming fiscal year: 


1st Quarter2nd Quarter3rd Quarter 4th Quarter
Units to be produced8,0006,5007,0007,500

Each unit requires 0.35 direct labor-hours, and direct laborers are paid $12.00 per hour. 


Required: 

1. Prepare the company's direct labor budget for the upcoming fiscal year. Assume that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced. 

2. Prepare the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is not adjusted each quarter. Instead, assume that the company's direct labor workforce consists of permanent employees who are guaranteed to be paid for at least 2,600 hours of work each quarter. If the number of required direct labor- hours is less than this number, the workers are paid for 2,600 hours anyway. Any hours worked in excess of 2,600 hours in a quarter are paid at the rate of 1.5 times the normal hourly rate for direct labor. 


1 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #4

Solution

Rordan Corporation
Direct labor budget
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Year
Units to be produced 8000 6500 7000 7500 29000
Direct labor time per unit (hours) 0.35 0.35 0.35 0.35 0.35
Total direct labor-hours needed 2800 2275 2450 2625 10150
Direct labor cost per hour $                    12 $                    12 $                    12 $                    12 $                    12
Total direct labor cost $            33,600 $            27,300 $           29,400 $            31,500 $          121,800

.

Rordan Corporation
Direct labor budget
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Year
Units to be produced 8000 6500 7000 7500 29000
Direct labor time per unit (hours) 0.35 0.35 0.35 0.35 0.35
Total direct labor-hours needed 2800 2275 2450 2625 10150
Regular hours 2600 2600 2600 2600 10400
Overtime hours 200 25 225
Wages for regular hours $      31,200.00 $      31,200.00 $     31,200.00 $      31,200.00 $    124,800.00
Overtime wages $        3,600.00 $            450.00 $        4,050.00
Total direct labor cost $      34,800.00 $      31,200.00 $     31,200.00 $      31,650.00 $    128,850.00
Add a comment
Answer #2

Requirement 1

Rordan Corporation
Direct labor budget
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Year
Units to be produced 8000 6500 7000 7500 29000
Direct labor time per unit (hours) 0.35 0.35 0.35 0.35 0.35
Total direct labor-hours needed 2800 2275 2450 2625 10150
Direct labor cost per hour $                    12 $                    12 $                    12 $                    12 $                    12
Total direct labor cost $            33,600 $            27,300 $           29,400 $            31,500 $          121,800

.

Requirement 2

Rordan Corporation
Direct labor budget
1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Year
Units to be produced 8000 6500 7000 7500 29000
Direct labor time per unit (hours) 0.35 0.35 0.35 0.35 0.35
Total direct labor-hours needed 2800 2275 2450 2625 10150
Regular hours 2600 2600 2600 2600 10400
Overtime hours 200 25 225
Wages for regular hours $      31,200.00 $      31,200.00 $     31,200.00 $      31,200.00 $    124,800.00
Overtime wages $        3,600.00 $            450.00 $        4,050.00
Total direct labor cost $      34,800.00 $      31,200.00 $     31,200.00 $      31,650.00 $    128,850.00

Overtime wages rate = 12 x 1.5= $18 per hour

Add a comment
✔ Recommended Answer
Answer #1

Add a comment
Answer #3

Answer

1.   

I ST Quarter IInd Quarter IIIrd Quarter IVth Quarter Total Year
Required Production in Unit (A) 8000 6500 7000 7500 29000
Direct Labour time per Unit ( Hours) (B) 0.35 0.35 0.35 0.35 0.35
Total Direct Labour Hour Needed C =(A*B) 2800 2275 2450 2625 10150
Direct Labour Cost per Hour - D 12 12 12 12 12
Total Direct Labour Cost- E (C*D) 33600 27300 29400 31500 121800

2.

I ST Quarter IInd Quarter IIIrd Quarter IVth Quarter Total Year
Total Direct Labour Hour Needed (A) 2800 2275 2450 2625 10150
Regular Hours Paid - (B) 2600 2600 2600 2600 10400
Over time - (C) 200 0 0 25 225
Wage of Regular Hours (D) (12*B) 31200 31200 31200 31200 124800
Overtime Wages (E) (C*1.5*12) 3600 0 0 450 4050
Total Direct Labour Cost- F (D+E) 34800 31200 31200 31650 128850
Add a comment
Know the answer?
Add Answer to:
The production manager of Rordan Corporation has submitted the following quarterly production forecast for the upcoming fiscal year:
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT