Question

Problem 6-10 United Research Associates (URA) had received a contract to produce two units of a new cruise missile guidance c
0 0
Add a comment Improve this question Transcribed image text
Answer #1

(a)

90% for 22nd unit 0.6251
80% for 22nd unit 0.3697
Hours in 22nd unit (0.6251*4,000) 2,500.40
Labor cost for 22nd unit (2500.4*20) 50,008
Material cost for 22nd unit (0.3697*40,000) 14,788
Total cost for 22md unit 64,796

(b)

Cumulative improvement factor @ 90% for 22 units 15.86
Hours for 22 units (4,000*15.86) 63,440
Hours for just the 20 units (63,440 - 4,000 - 3,600) 55,840
Average hours for 20 units (55,840/20) 2,792

(c)

Cumulative improvement factor @ 80% for 22 units 11.23
Average Labor cost (2,792*$20)...................................................(1) 55,840
Materials cost for 22 units (11.23*40,000) 449,200
Materials cost for just the 20 units (449,200 - 40,000 - 32,000) 377,200
Average materials cost (377,200 / 20)..........................................(2) 18,860
Average total cost ...............................................................(1) + (2) 74,700
Add a comment
Know the answer?
Add Answer to:
Problem 6-10 United Research Associates (URA) had received a contract to produce two units of a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • United Research Associates (URA) had received a contract to produce two units of a new cruise...

    United Research Associates (URA) had received a contract to produce two units of a new cruise missile guidance control. The first unit took 4,000 hours to complete and cost $30,000 in materials and equipment usage. The second took 2,800 hours and cost $18,000 in materials and equipment usage. Labor cost is charged at $22 per hour. The prime contractor has now approached URA and asked to submit a bid for the cost of producing another 20 guidance controls. Use Exhibit...

  • Operations Management - Learning curve homework

    United Research Associates (URA) has received a contract to produce two units of a new cruise missile guidance control. The first unit took 4,000 hours to complete and cost $30,000 in materials and equipment usage. The second took 2,800 hours and cost $18,000 in materials and equipment usage. Labor cost is charged at $22 per hour. The prime contractor has now approached URA and asked to submit a bid for the cost of producing another 20 guidance controls. Use Exhibit...

  • Lambda Computer Products competed for and won a contract to produce two prototype units of a...

    Lambda Computer Products competed for and won a contract to produce two prototype units of a new type of computer that is based on laser optics rather than on electronic binary bits. The first unit produced by Lambda took 5,000 hours to produce and required $250,000 worth of material, equipment usage, and supplies. The second unit took 3,750 hours and used $212,500 worth of materials, equipment usage, and supplies. Labor is $30 per hour. Use Exhibit 6.5. a. Lambda was...

  • Lambda Computer Products competed for and won a contract to produce two prototype units of a...

    Lambda Computer Products competed for and won a contract to produce two prototype units of a new type of computer that is based on laser optics rather than on electronic binary bits. The company expects "learning" to occur relative to labor and also relative to the pricing of materials, equipment and supplies. The first unit produced by Lambda took 5,000 hours to produce and required $250,000 worth of material, equipment usage, and supplies. The second unit took 3,500 hours and...

  • Lambda Computer Products competed for and won a contract to produce two prototype units of a...

    Lambda Computer Products competed for and won a contract to produce two prototype units of a new type of computer that is based on laser optics rather than on electronic binary bits. The first unit produced by Lambda took 5,000 hours to produce and required $250,000 worth of material, equipment usage, and supplies. The second unit took 3,500 hours and used $200,000 worth of material, equipment usage, and supplies. Labor is $30 per hour. (a) Lambda was asked to present...

  • Johnson Industries received a contract to develop and produce four high-intensity long-distance receiver/transmitters for cellular telephones....

    Johnson Industries received a contract to develop and produce four high-intensity long-distance receiver/transmitters for cellular telephones. The first took 2,600 labor hours and $44,000 worth of purchased and manufactured parts; the second took 2,240 labor hours and $42,240 in parts; the third took 2,060 labor hours and $40,980 in parts; and the fourth took 1,882 labor hours and $39,710 in parts.      Johnson was asked to bid on a follow-on contract for another dozen receiver/transmitter units. (Hint: There are two learning...

  • Activity-Based Costing Zeus Industries manufactures two types of electrical power units, custom and standard, which involve...

    Activity-Based Costing Zeus Industries manufactures two types of electrical power units, custom and standard, which involve four factory overhead activities—production setup, procurement, quality control, and materials management. An activity analysis of the overhead revealed the following estimated activity costs and activity bases for these activities: Activity Activity Cost Activity Base Production setup $ 67,500 Number of setups Procurement 126,000 Number of purchase orders (PO) Quality control 156,000 Number of inspections Materials management 147,000 Number of components Total $496,500 The activity-base...

  • Activity-Based Costing Zeus Industries manufactures two types of electrical power units, custom and standard, which involve...

    Activity-Based Costing Zeus Industries manufactures two types of electrical power units, custom and standard, which involve four factory overhead activities-production setup, procurement, quality control, and materials management. An activity analysis of the overhead revealed the following estimated activity costs and activity bases for these activities: Activity Activity Cost Production setup Procurement $ 58,500 136,500 182,000 200,000 Activity Base Number of setups Number of purchase orders (PO) Number of inspections Number of components Quality control Materials management Total $577,000 The activity-base...

  • Sarasota and Associates produces two products named Loser and Big Winner. Last month 1,000 units of...

    Sarasota and Associates produces two products named Loser and Big Winner. Last month 1,000 units of Loser and 4,000 units of Big Winner were produced and sold. Average prices and costs for the two products for last month follow: Big Loser Winner Selling price $ 88 $ 228 Direct materials 36 99 Direct labour 5 25 Variable overhead 5 15 Product line fixed costs 10 40 Corporate fixed costs 22 22 Average margin per unit $ 10 $ 27 The...

  • Marigold and Associates produces two products named Loser and Big Winner. Last month 1,000 units of...

    Marigold and Associates produces two products named Loser and Big Winner. Last month 1,000 units of Loser and 4,000 units of Big Winner were produced and sold. Average prices and costs for the two products for last month follow: Big Loser Winner Selling price $ 89 $ 229 Direct materials 40 98 Direct labour 5 25 Variable overhead 5 16 Product line fixed costs 10 40 Corporate fixed costs 21 21 Average margin per unit $ 8 $ 29 The...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT