Question

Lambda Computer Products competed for and won a contract to produce two prototype units of a new type of computer that is bas
0 0
Add a comment Improve this question Transcribed image text
Answer #1
TOTAL LABOUR HOURS AND MATERIAL COST REQUIRED FOR FIRST TWO UNITS ARE SHOWN BELOW
UNIT HOURS COST
1 5,000 2,50,000
2 3,750 2,00,000
DETRERMINE THE AMOUNT OF LC
INITIALLY DETERMINE THE LEARNING RATE FOR 1-2 UNITS
LEARNING RATE 3750/5000*100 75%
MATERRIAL AND EQUIPMENT USAGE RATE 200000/250000 80%
TWO UNITS ALREADY HAS BEEN ALREADY PRODUCED HENCE TOTAL UNITS = 12 UNITS
USING CUMILATIVE VALUES WE CAN DETERMINE THE CUMILATIVE IMPROVEMENT FACTORS
AMOUNT ($)
WORK HOURS 3750*5.589( 75% AND 10 UNITS) *$30 PER HOUR 6,28,762.50
MATERIAL AND EQUIPMENT 200000*6.315(80% AND 10 UNITS) 12,63,000.00
TOTAL ACCUMULATED COST FOR 10 UNITS 18,91,762.50
Add a comment
Know the answer?
Add Answer to:
Lambda Computer Products competed for and won a contract to produce two prototype units of a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Lambda Computer Products competed for and won a contract to produce two prototype units of a...

    Lambda Computer Products competed for and won a contract to produce two prototype units of a new type of computer that is based on laser optics rather than on electronic binary bits. The company expects "learning" to occur relative to labor and also relative to the pricing of materials, equipment and supplies. The first unit produced by Lambda took 5,000 hours to produce and required $250,000 worth of material, equipment usage, and supplies. The second unit took 3,500 hours and...

  • Lambda Computer Products competed for and won a contract to produce two prototype units of a...

    Lambda Computer Products competed for and won a contract to produce two prototype units of a new type of computer that is based on laser optics rather than on electronic binary bits. The first unit produced by Lambda took 5,000 hours to produce and required $250,000 worth of material, equipment usage, and supplies. The second unit took 3,500 hours and used $200,000 worth of material, equipment usage, and supplies. Labor is $30 per hour. (a) Lambda was asked to present...

  • United Research Associates (URA) had received a contract to produce two units of a new cruise...

    United Research Associates (URA) had received a contract to produce two units of a new cruise missile guidance control. The first unit took 4,000 hours to complete and cost $30,000 in materials and equipment usage. The second took 2,800 hours and cost $18,000 in materials and equipment usage. Labor cost is charged at $22 per hour. The prime contractor has now approached URA and asked to submit a bid for the cost of producing another 20 guidance controls. Use Exhibit...

  • Problem 6-10 United Research Associates (URA) had received a contract to produce two units of a...

    Problem 6-10 United Research Associates (URA) had received a contract to produce two units of a new cruise missile guidance control. The first unit took 4,000 hours to complete and cost $40,000 in materials and equipment usage. The second took 3,600 hours and cost $32,000 in materials and equipment usage. Labor cost is charged at $20 per hour. The prime contractor has now approached URA and asked to submit a bid for the cost of producing another 20 guidance controls....

  • Operations Management - Learning curve homework

    United Research Associates (URA) has received a contract to produce two units of a new cruise missile guidance control. The first unit took 4,000 hours to complete and cost $30,000 in materials and equipment usage. The second took 2,800 hours and cost $18,000 in materials and equipment usage. Labor cost is charged at $22 per hour. The prime contractor has now approached URA and asked to submit a bid for the cost of producing another 20 guidance controls. Use Exhibit...

  • 4. Perform a SWOT analysis for Fitbit. Based on your assessment of these, what are some strategic options for Fitbit go...

    4. Perform a SWOT analysis for Fitbit. Based on your assessment of these, what are some strategic options for Fitbit going forward? 5. Analyze the company’s financial performance. Do trends suggest that Fitbit’s strategy is working? 6.What recommendations would you make to Fitbit management to address the most important strategic issues facing the company? Fitbit, Inc., in 2017: Can Revive Its Strategy and It Reverse Mounting Losses? connect ROCHELLE R. BRUNSON Baylor University MARLENE M. REED Baylor University in the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT