Job 3175 | Job. 4386 | ||||||||
Activity | Overhead cost (a) | Activity drivers (b) | Activity rate (c = a ÷ b) | Activity driver incurred (d) | Overhead assigned (e = d × c) | Activity driver incurred (f) | Overhead assigned (g = f × c) | ||
Grinding & Polishing | $480,000 | 18,000 | Machine hours | $26.67 | per machine hour | 300 | $8,001 | 3,000 | $80,010 |
Production modifications | $450,000 | 2,200 | Engineering hours | $204.55 | per engineering hour | 29 | $5,932 | 20 | $4,091 |
Providing power | $260,000 | 19,000 | Direct labor hours | $13.68 | per direct labor hour | 440 | $6,019 | 3,960 | $54,173 |
System calibration | $550,000 | 900 | batches | $611.11 | Per batch | 10 | $6,111 | 30 | $18,333 |
Total overhead costs | $26,063 | $156,607 | |||||||
(/) Number of units | 170 | 2,125 | |||||||
Average overhead costs per unit | $153.31 | $73.70 | |||||||
Calculations:
Grinding & Polishing = $340,000 + $140,000
= $480,000
Activity rate = Overhead costs / Activity drivers
Overhead assigned = Activity rate × Activity driver incurred
Average overhead cost per unit = Total overhead costs / Number of units
! Required information {The following information applies to the questions displayed below.) Craft Pro Machining produces...
Question 10 Required information [The following information applies to the questions displayed below.] Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Indirect Materials Other Overhead Indirect Labor $340,000 $170,000 Production Activity Grinding Polishing Product modification Providing power System calibration 400,000 $210,000 460,000 Additional information on the drivers for its production activities follows. Grinding Polishing Product modification Providing power System calibration 19,000 machine hours 19,000 machine hours...
Check Required information (The following information applies to the questions displayed below] Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Production Activity Grinding Polishing Product modification Providing power Systen calibration Indirect Labor Indirect Materiala Other Overhead 6360, 000 $185,000 600, 000 $220, 000 540,000 Additional information on the drivers for its production activities follows. Grinding Polishing Product modification Providing power Syatem calibration 15,000 machine hours 15,000...
Required information [The following information applies to the questions displayed below) Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records Indirect Labor $340,000 Other Overhead Indirect Materials $220,000 Production Activity Grinding Polishing Product modification Providing power System calibration 500,000 $200,000 520,000 Additional information on the drivers for its production activities follows. 1,600 engineering Grinding 14,000 machine hours Polishing 14,000 machine hours Product modification hours Providing power 14,000...
Required information [The following information applies to the questions displayed below) Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records Indirect Labor $340,000 Other Overhead Indirect Materials $220,000 Production Activity Grinding Polishing Product modification Providing power System calibration 500,000 $200,000 520,000 Additional information on the drivers for its production activities follows. 1,600 engineering Grinding 14,000 machine hours Polishing 14,000 machine hours Product modification hours Providing power 14,000...
Required information [The following information applies to the questions displayed below.] Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Indirect Materials Other Overhead Indirect Labor $390,000 Production Activity Grinding Polishing Product modification Providing power System calibration $185,000 650,000 $255,000 430,000 Additional information on the drivers for its production activities follows. Grinding Polishing Product modification Providing power System calibration 17,000 machine hours 17,000 machine hours 2,100 engineering...
[The following information applies to the questions displayed below.] Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Indirect Materials Other Overhead Indirect Labor $ 330,000 $110,000 Production Activity Grinding Polishing Product modification Providing power System calibration 600,000 $ 240,000 440,000 Additional information on the drivers for its production activities follows. Grinding Polishing Product modification Providing power System calibration 10,000 machine hours 10,000 machine hours 1,900 engineering...
Requlred Information (The following information applies to the questions displayed below.] Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Indirect Materials Other Overhead $185,000 Production Indirect Labor Activity Grinding $350,000 Polishing Product modification 500,000 Providing power System calibration 590,000 $245,000 Additional information on the drivers for its production activities follows. Grinding Polishing Product modification Providing power System calibration 13,000 machine hours 13,000 machine hours 1,600 engineering...
(The following information applies to the questions displayed below.) Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Production Activity Indirect Labor Indirect Materials Other Overhead Grinding $360,000 Polishing $190,000 Product modification 600,000 Providing power $235,000 System calibration 540,000 Additional information on the drivers for its production activities follows. Grinding Polishing Product modification Providing power System calibration 12,000 machine hours 12,000 machine hours 1,800 engineering hours 14,000...
Required information (The following information applies to the questions displayed below. Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Production Activity Indirect Labor Indirect Materials Other Overhead Grinding $310,000 Polishing $115,000 Product modification 450,000 Providing power $220,000 System calibration 580,000 Additional information on the drivers for its production activities follows. Grinding Polishing Product modification Providing power System calibration 16,000 machine hours 16,000 machine hours 1,600 engineering...
Required information (The following information applies to the questions displayed below) Craft Pro Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Part 2 of 3 Indirect Indirect Labor Other Overhead Materials $320,000 $135,000 Production Activity Grinding Polishing Product modification Providing power Systen calibration 600,000 $255,000 500,000 Additional information on the drivers for its production activities follows. Grinding Polishing Product modification Providing power System calibration 13,000 machine hours 13,000...