Question

Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs duri
If Job P includes 30 units, what is its unit product cost? Jnit product cost
0 0
Add a comment Improve this question Transcribed image text
Answer #1
3
Job P Job Q
Direct labor cost 22500 10500
Divide by Average Direct labor hours worked 1500 700
Direct labor hourly wage rate 15 15
4
Predetermined overhead rate 6.40 =1.40+(12000/2400)
Job P
Direct materials 15000
Direct labor cost 22500
Overhead applied 9600 =1500*6.40
Total manufacturing cost 47100
Divide by Units 30
Unit product cost 1570
Add a comment
Know the answer?
Add Answer to:
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....

    Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs P and Q (all data...

  • Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....

    Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs P and Q (all data...

  • Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....

    Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs P and Q (all data...

  • Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....

    Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs P and Q (all data...

  • Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....

    Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs P and Q (all data...

  • Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....

    Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs P and Q (all data...

  • Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....

    Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March-Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs P and Q (all data...

  • Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....

    Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March-Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs P and Q (all data...

  • Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....

    Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs P and Q (all data...

  • Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....

    Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs P and Q (all data...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT