Shire Computers predetermined overhead rate is based on direct labor cost. Management estimates the company will incur $663,
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Requirement 1:

Overhead Rate
Estimated Overhead Cost / Estimated labor cost = Overhead rate
$663,000 / $510,000 = 1.30

Explanation:

Overhead rate = Estimated Overhead / Estimated labor cost

= $663,000 / $510,000

=$1.30

Add a comment
Know the answer?
Add Answer to:
Shire Computer's predetermined overhead rate is based on direct labor cost. Management estimates the company will...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Shire Computer's predetermined overhead rate is based on direct labor cost. Management estimates the company will...

    Shire Computer's predetermined overhead rate is based on direct labor cost. Management estimates the company will incur $676,000 of overhead costs and $520,000 of direct labor cost for the year. During March, Shire began and completed Job 13-56. 1. What is the predetermined overhead rate for the year? 2. Use the information on the following job cost sheet to determine the total cost of the job. Complete this question by entering your answers in the tabs below. Required 1 Required...

  • Shire Computer's predetermined overhead rate is based on direct labor cost. Management estimates the company will...

    Shire Computer's predetermined overhead rate is based on direct labor cost. Management estimates the company will incur $742,000 of overhead costs and $530,000 of direct labor cost for the year. During March, Shire began and completed Job 13-56. 1. What is the predetermined overhead rate for the year? 2. Use the information on the following job cost sheet to determine the total cost of the job. Complete this question by entering your answers in the tabs below. Required 1 Required...

  • Shire Computer's predetermined overhead rate is based on direct labor cost. Management estimates the company will...

    Shire Computer's predetermined overhead rate is based on direct labor cost. Management estimates the company will incur $672,000 of overhead costs and $560,000 of direct labor cost for the year. During March, Shire began and completed Job 13-56. 1. What is the predetermined overhead rate for the year? 2. Use the information on the following job cost sheet to determine the total cost of the job. Complete this question by entering your answers in the tabs below. Required 1 Required...

  • In December 2016, Shire Computer's management establishes the 2017 predetermined overhead rate based on direct labor...

    In December 2016, Shire Computer's management establishes the 2017 predetermined overhead rate based on direct labor cost. The information used in setting this rate includes estimates that the company will incur $767,000 of overhead costs and $590,000 of direct labor cost in year 2017. During March 2017, Shire began and completed Job 13-56. 1. What is the predetermined overhead rate for 2017? 2. Using the information on the following job cost sheet, determine the total cost of the job. Complete...

  • CH Shire Computer's predetermined overhead rate is based on direct labor cost. Management estimates the company...

    CH Shire Computer's predetermined overhead rate is based on direct labor cost. Management estimates the company will incur $864,000 of overhead costs and $540,000 of direct labor cost for the year. During March, Shire began and completed Job 13-56. 1. What is the predetermined overhead rate for the year? 2. Use the information on the following job cost sheet to determine the total cost of the job. ped Complete this question by entering your answers in the tabs below. ook...

  • In December 2016, Shire Computer's management establishes the 2017 predetermined overhead rate based on direct labor...

    In December 2016, Shire Computer's management establishes the 2017 predetermined overhead rate based on direct labor cost. The information used in setting this rate includes estimates that the company will incur $728,000 of overhead costs and $520,000 of direct labor cost in year 2017. During March 2017, Shire began and completed Job 13-56. 1. What is the predetermined overhead rate for 2017? 2. Using the information on the following job cost sheet, determine the total cost of the job. Complete...

  • In December 2016, Shire Computer's management establishes the 2017 predetermined overhead rate based on direct labor...

    In December 2016, Shire Computer's management establishes the 2017 predetermined overhead rate based on direct labor cost. The information used in setting this rate includes estimates that the company will incur $832,000 of overhead costs and $520,000 of direct labor cost in year 2017. During March 2017, Shire began and completed Job 13-56. 1. What is the predetermined overhead rate for 2017? 2. Using the information on the following job cost sheet, determine the total cost of the job. Complete...

  • In December 2016, Shire Computer's management establishes the 2017 predetermined overhead rate based on direct labor co...

    In December 2016, Shire Computer's management establishes the 2017 predetermined overhead rate based on direct labor cost. The information used in setting this rate includes estimates that the company will incur $812,000 of overhead costs and $580,000 of direct labor cost in year 2017. During March 2017. Shire began and completed Job 13-56. 1. What is the predetermined overhead rate for 2017? 2. Using the information on the following job cost sheet, determine the total cost of the job. Complete...

  • In December 2014, Shire Computer's management establishes the 2015 predetermined overhead rate based on direct labor...

    In December 2014, Shire Computer's management establishes the 2015 predetermined overhead rate based on direct labor cost. The information used in setting this rate includes estimates that the company will incur $747,500 of overhead costs and $575,000 of direct labor cost in year 2015. During March 2015, Shire began and completed Job No. 13-56. 1. What is the predetermined overhead rate for year 2015? Overhead Rate 1 Choose Denominator: Choose Numerator: II Overhead Rate Overhead rate / 11 1 II...

  • I need both required parts In December 2016, Shire Computer's management establishes the 2017 predetermined overhead...

    I need both required parts In December 2016, Shire Computer's management establishes the 2017 predetermined overhead rate based on direct labor cost. The information used in setting this rate includes estimates that the company will incur $714,000 of overhead costs and $510,000 of direct labor cost in year 2017. During March 2017, Shire began and completed Job 13-56. 1. What is the predetermined overhead rate for 2017? 2. Using the information on the following job cost sheet, determine the total...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT