Shire Computers predetermined overhead rate is based on direct labor cost. Management estimates the company will incur $672,
Using the information on the following job cost sheet, determine the total cost of the job. (Round your answers to the neares
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Predetermined overhead rate = Estimated overhead cost /Estimated direct labor cost

                           = 672000 / 560000

                           = 1.20 or 120% of direct labor cost

b)

JOB COST SHEET
Customer's Name :Keiser co Job No: 13-56
Job description :5 Plasma monitors -61Inch
Direct material Direct labor Overhead Total cost
Date Requisition No. Amount Time Ticket no. Amount cost applied
Mar 8 4-129 6000 T-306 670 670*120%=804 7474
Mar11 4-142 6500 T-432 1340 1340*120%= 1608 9448
Mar 18 4-167 3700 T-456 1300 1300*120%= 1560 6560
16200 3310 23482
Add a comment
Know the answer?
Add Answer to:
Shire Computer's predetermined overhead rate is based on direct labor cost. Management estimates the company will...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Shire Computer's predetermined overhead rate is based on direct labor cost. Management estimates the company will...

    Shire Computer's predetermined overhead rate is based on direct labor cost. Management estimates the company will incur $676,000 of overhead costs and $520,000 of direct labor cost for the year. During March, Shire began and completed Job 13-56. 1. What is the predetermined overhead rate for the year? 2. Use the information on the following job cost sheet to determine the total cost of the job. Complete this question by entering your answers in the tabs below. Required 1 Required...

  • Shire Computer's predetermined overhead rate is based on direct labor cost. Management estimates the company will...

    Shire Computer's predetermined overhead rate is based on direct labor cost. Management estimates the company will incur $747,500 of overhead costs and $575,000 of direct labor cost for the year. During March, Shire began and completed Job 13- 56. 1. What is the predetermined overhead rate for the year? 2. Use the information on the following job cost sheet to determine the total cost of the job. Check (2) $22,710 JOB COST SHEET Job No. 13-56 Customer's Name Keiser Co....

  • CH Shire Computer's predetermined overhead rate is based on direct labor cost. Management estimates the company...

    CH Shire Computer's predetermined overhead rate is based on direct labor cost. Management estimates the company will incur $864,000 of overhead costs and $540,000 of direct labor cost for the year. During March, Shire began and completed Job 13-56. 1. What is the predetermined overhead rate for the year? 2. Use the information on the following job cost sheet to determine the total cost of the job. ped Complete this question by entering your answers in the tabs below. ook...

  • Shire Computer's predetermined overhead rate is based on direct labor cost. Management estimates the company will...

    Shire Computer's predetermined overhead rate is based on direct labor cost. Management estimates the company will incur $742,000 of overhead costs and $530,000 of direct labor cost for the year. During March, Shire began and completed Job 13-56. 1. What is the predetermined overhead rate for the year? 2. Use the information on the following job cost sheet to determine the total cost of the job. Complete this question by entering your answers in the tabs below. Required 1 Required...

  • In December 2016, Shire Computer's management establishes the 2017 predetermined overhead rate based on direct labor...

    In December 2016, Shire Computer's management establishes the 2017 predetermined overhead rate based on direct labor cost. The information used in setting this rate includes estimates that the company will incur $728,000 of overhead costs and $520,000 of direct labor cost in year 2017. During March 2017, Shire began and completed Job 13-56. 1. What is the predetermined overhead rate for 2017? 2. Using the information on the following job cost sheet, determine the total cost of the job. Complete...

  • Shire Computer's predetermined overhead rate is based on direct labor cost. Management estimates the company will...

    Shire Computer's predetermined overhead rate is based on direct labor cost. Management estimates the company will incur $663,000 of overhead costs and $510,000 of direct labor cost for the year. During March, Shire began and completed Job 13-56. 1. What is the predetermined overhead rate for the year? 2. Use the information on the following job cost sheet to determine the total cost of the job. Complete this question by entering your answers in the tabs below. Required 1 Required...

  • In December 2016, Shire Computer's management establishes the 2017 predetermined overhead rate based on direct labor co...

    In December 2016, Shire Computer's management establishes the 2017 predetermined overhead rate based on direct labor cost. The information used in setting this rate includes estimates that the company will incur $812,000 of overhead costs and $580,000 of direct labor cost in year 2017. During March 2017. Shire began and completed Job 13-56. 1. What is the predetermined overhead rate for 2017? 2. Using the information on the following job cost sheet, determine the total cost of the job. Complete...

  • In December 2016, Shire Computer's management establishes the 2017 predetermined overhead rate based on direct labor...

    In December 2016, Shire Computer's management establishes the 2017 predetermined overhead rate based on direct labor cost. The information used in setting this rate includes estimates that the company will incur $832,000 of overhead costs and $520,000 of direct labor cost in year 2017. During March 2017, Shire began and completed Job 13-56. 1. What is the predetermined overhead rate for 2017? 2. Using the information on the following job cost sheet, determine the total cost of the job. Complete...

  • In December 2014, Shire Computer's management establishes the 2015 predetermined overhead rate based on direct labor...

    In December 2014, Shire Computer's management establishes the 2015 predetermined overhead rate based on direct labor cost. The information used in setting this rate includes estimates that the company will incur $747,500 of overhead costs and $575,000 of direct labor cost in year 2015. During March 2015, Shire began and completed Job No. 13-56. 1. What is the predetermined overhead rate for year 2015? Overhead Rate 1 Choose Denominator: Choose Numerator: II Overhead Rate Overhead rate / 11 1 II...

  • Exercise 15-11 Overhead rate; costs assigned to jobs LO P3 Shire Computer's predetermined overhead rate is...

    Exercise 15-11 Overhead rate; costs assigned to jobs LO P3 Shire Computer's predetermined overhead rate is based on direct labor cost. Management estimates the company will incur $636,000 of overhead costs and $530,000 of direct labor cost for the year. During March, Shire began and completed Job 13-56. 1. What is the predetermined overhead rate for the year? 2. Use the information on the following job cost sheet to determine the total cost of the job. Complete this question by...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT