Total cost for JOB P951 | |
Direct Materials | $755 |
Direct Labour | $5000 |
Variable Manufacturing Overhead (150 * 3) |
$450 |
Fixed Manufacturing Overhead ($96000*150/40000) |
$360 |
Total Cost | $6565 |
4Th option is the correct answer.
Total direct labor-hours 40,000 Total foxed manufacturing overhead cost $ 96,000 Variable manufacturing overhead per direct...
Total direct labor-hours:101,000 Total fixed manufacturing overhead cost: $595,900 Variable manufacturing overhead per direct labor-hour: $3.00 loughamy waketech edu My Turbo Tax Login Signint x f Me 2019 Connect Required: Ch 2 Quiz Saved Help Save & Exit Submit Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: points Total direct labor-hours Total fixed manufacturing overhead...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the folowing data: Total direct labor-hours 40,000 Total fixed manufacturing overhead cost $96,000 Variable manufacturing overhead per direct labor- $ 3.00 hour Recently, Job P951 was completed with the following characteristics: Number of units in the job Total direct labor-hours Direct materials Direct labor cost 100 $ 755 $4,000 The...
12 Dehner Corporation uses a job order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per direct labor hour 40,000 $96,000 $ 3.00 02:0753 Recently, Job P951 was completed with the following characteristics Number of units in the job Total direct labor-hours Direct materials Direct labor cost 20 100...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data Total direct labor-hours Total fixed manufacturing overhead cost Variable nanufacturing overhead per direct labor-hour 40,000 96,000 $ 3.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job Total direct labor-hours Direct materials Direct labor cost 20 100 두 755 $4,000 The...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor- hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 40,000 Total fixed manufacturing overhead cost $96,000 Variable manufacturing overhead per direct labor-hour $ 3.00 Recently, Job P951 was completed with the following characteristics Number of units in the job Total direct labor-hours Direct materials Direct labor cost 20 100 $ 755 $4,000...
Dehner Corporation uses a job order costing system with a single plantwide predetermined overhead rate based on direct labor hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 40,000 Total fixed manufacturing overhead cost $96.000 Variable manufacturing overhead per direct labor- $ 3.00 hour Recently, Job P951 was completed with the following characteristics: Number of units in the job Total direct laber-hours Direct materiale Direct labor cost 100 $ 755...
Help Save & Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 40,000 Total fixed manufacturing overhead cost $96,00 Variable manufacturing overhead per direct labor-hour $ 3.ee Recently, Job P951 was completed with the following characteristics: Number of units in the job Total direct labor-hours Direct materials Direct labor cost 20 1ee $...
Direct labor-hours Machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour Variable manufacturing overhead per direct labor-hour Department Cutting Finishing 7,300 65,000 53,100 1,500 $ 370,000 $ 599,000 $ 3.00 - - $ 3.75 Required: 1. Compute the predetermined overhead rate for each department. 2. The job cost sheet for Job 203, which was started and completed during the year, showed the following: Department Cutting Finishing 12 Direct labor-hours Machine-hours Direct materials Direct labor cost 84 $ 720...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per direct labor-hour 72,000 $223,200 $ 3.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job Total direct labor-hours Direct materials Direct labor cost 20 100 $ 890 $7,200 The...
12 Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: 8 01:12:23 Total direct labor-hours 101,000 Total fixed manufacturing overhead cost $595,900 Variable manufacturing overhead per direct labor-hour $ 3.00 Recently, Job P951 was completed with the following characteristics: 25 Number of units in the job Total direct labor-hours Direct materials Direct labor cost 100 $...