Requirement 1: $1,113
Calculations:
Finishing | Fabrication | Total | |
Direct material | $ 470 | $ 95 | $ 565 |
Direct labor | $ 196 | $ 84 | $ 280 |
Overhead | |||
[7 direct labor hours x $22] | $ 154 | ||
[$95 direct materials x 120%] | $ 114 | $ 268 | |
Total manufacturing Cost | $ 1,113 |
Direct labor hours for finishing = $196/$28.00 = 7 hours
Requirement 2: $37.10 per unit
Calculations:
Unit product cost = Total manufacturing cost ÷ No. of units
= $1,113 ÷ 30 units
= $37.10
Chapter 2 Homework a Seved Help Save & Exit Submit Check my work 4 Exercise 2-5...
Check my work Exercise 2-5 Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Overhead Rates (LO2-4) 7.5 points Braverman Company has two manufacturing departments-Finishing and Fabrication. The predetermined overhead rates in Finishing and Fabrication are $26.00 per direct labor-hour and 120% of direct materials cost, respectively. The company's direct labor wage rate is $32.00 per hour. The following information pertains to Job 700: eBook materials Finishing $ 352 stening Fabrication S 490 Hint Direct labor Fabrication $...
Exercise 2-5 Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Overhead Rates (LO2-4) Braverman Company has two manufacturing departments—Finishing and Fabrication. The predetermined overhead rates in Finishing and Fabrication are $25.00 per direct labor-hour and 110% of direct materials cost, respectively. The company's direct labor wage rate is $31.00 per hour. The following information pertains to Job 700: Direct materials Direct labor Finishing $ 485 $ 310 Fabrication $ 110 $ 186 Required: 1. What is the...
Exercise 2-5 Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Overhead Rates [LO2-4] Braverman Company has two manufacturing departments—Finishing and Fabrication. The predetermined overhead rates in Finishing and Fabrication are $21.00 per direct labor-hour and 110% of direct materials cost, respectively. The company’s direct labor wage rate is $27.00 per hour. The following information pertains to Job 700: Finishing Fabrication Direct materials $ 465 $ 90 Direct labor $ 162 $ 54 Required: 1. What is the...
Question: Exercise 2-5 Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Overhead Rates [LO2-4] Exercise 2-5 Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Overhead Rates (LO2-4] Braverman Company has two manufacturing departments-Finishing and Fabrication. The predetermined overhead rates in Finishing and Fabrication are $13.00 per direct labor-hour and 120% of direct materials cost, respectively. The company's direct labor wage rate is $20.00 per hour. The following information pertains to Job 700: Direct materials...
Help Save & Exit s Check my w Braverman Company has two manufacturing departments --Finishing and Fabrication. The predetermined overhead rates in Finishing and Fabrication are $23.00 per direct labor-hour and 110% of direct materials cost, respectively. The company's direct labor wage rate is $29.00 per hour. The following information pertains to Job 700: Direct materials Direct labor Finishing $ 475 $ 232 Fabrication $ 100 $ 116 Required: 1. What is the total manufacturing cost assigned to Job 700?...
Exercise 2-5 (Algo) Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Overhead Rates (LO2-4] Braverman Company has two manufacturing departments—Finishing and Fabrication. The predetermined overhead rates in Finishing and Fabrication are $20.00 per direct labor-hour and 120% of direct materials cost, respectively. The company's direct labor wage rate is $26.00 per hour. The following information pertains to Job 700: Direct materials Direct labor Finishing $460 $390 Fabrication $ 85 $286 Required: 1. What is the total manufacturing...
Exercise 2-5 (Algo) Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Overhead Rates (LO2-4] Braverman Company has two manufacturing departments—Finishing and Fabrication. The predetermined overhead rates in Finishing and Fabrication are $24.00 per direct labor-hour and 120% of direct materials cost, respectively. The company's direct labor wage rate is $30.00 per hour. The following information pertains to Job 700: Direct materials Direct labor Finishing $480 $270 Fabrication $105 $150 Required: 1. What is the total manufacturing cost...
Exercise 2-5 Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Overhead Rates (LO2-4] 0.62 points Braverman Company has two manufacturing departments-Finishing and Fabrication. The predetermined overhead rates in Finishing and Fabrication are $18.00 per direct labor-hour and 110% of direct materials cost, respectively. The company's direct labor wage rate is $16.00 per hour. The following information pertains to Job 700: eBook Finishing $410 $128 Fabrication Hint Direct materials $60 $ 48 Direct labor Print References Required: 1....
Braverman Company has two manufacturing departments—Finishing and Fabrication. The predetermined overhead rates in Finishing and Fabrication are $22.00 per direct labor-hour and 120% of direct materials cost, respectively. The company’s direct labor wage rate is $28.00 per hour. The following information pertains to Job 700: FinishingFabricationDirect materials$470$95Direct labor$196$84 Required:1. What is the total manufacturing cost assigned to Job 700?2. If Job 700 consists of 30 units, what is the unit product cost for this job? (Round your answer to 2 decimal places.)
ded Homework Seved Exercise 2-4 Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Overhead Rates (LO2-4) Fickel Company has two manufacturing departments Assembly and Testing & Packaging. The predetermined overhead rates in Assembly and Testing & Packaging are $26.00 per direct labor-hour and $22.00 per direct labor-hour, respectively. The company's direct labor wage rate is $28.00 per hour. The following information pertains to Job N-60: Testing & Packaging $ 53 $ 70 Assembly $410 $322 Direct materials...