Question

Help Save & Exit s Check my w Braverman Company has two manufacturing departments --Finishing and Fabrication. The predetermi
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1. Total manufacturing cost = Direct material cost + Direct labor + manufacturing overhead

Calculating Manufacturing overhead :

For finishing- $23 per Direct labor hour (given in question)

So, for calculating overhead costs for finishing, we need to calculate the Direct labor hour.

The company's wage rate is given $29 per hour and the direct labour cost for finishing is $232. So, number of direct labor hour for finishing is = $232/ $29 = 8 hours.

Now, the finishing overhead = $23 ×8 = $184

For Fabrication overhead = 110% of direct material cost

Direct material cost for fabrication = $100

So, fabrication overhead = $110

Total overhead cost = finishing overhead costs + fabrication overhead costs

= $184 + $110 = $294

Total direct materials cost = finishing material cost + fabrication overhead costs

= $475 + $100 = $575

Total direct labor cost = finishing labor cost + fabrication labor cost

= $232 + $116 = $348

Now, total manufacturing cost assigned to job 700 = total overhead cost + total material cost + total labor cost

= $294 + $575 + $348 = $1217

2. If job 700 has 5 units, then this means total cost of 5 units is $1217. So, to calculate unit product cost = $1217 / 5 = $ 243.4

Unit product cost= $243.4

Add a comment
Know the answer?
Add Answer to:
Help Save & Exit s Check my w Braverman Company has two manufacturing departments --Finishing and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Braverman Company has two manufacturing departments—Finishing and Fabrication. The predetermined overhead rates in Finishing and Fabrication...

    Braverman Company has two manufacturing departments—Finishing and Fabrication. The predetermined overhead rates in Finishing and Fabrication are $10.00 per direct labor-hour and 110% of direct materials cost, respectively. The company’s direct labor wage rate is $17.00 per hour. The following information pertains to Job 700: Finishing Fabrication Direct materials $ 415 $ 40 Direct labor $ 102 $ 34 Required: 1. What is the total manufacturing cost assigned to Job 700? 2. If Job 700 consists of 5 units, what...

  • Braverman Company has two manufacturing departments—Finishing and Fabrication. The predetermined overhead rates in Finishing and Fabrication...

    Braverman Company has two manufacturing departments—Finishing and Fabrication. The predetermined overhead rates in Finishing and Fabrication are $17.00 per direct labor-hour and 120% of direct materials cost, respectively. The company’s direct labor wage rate is $24.00 per hour. The following information pertains to Job 700: Finishing Fabrication Direct materials $ 450 $ 75 Direct labor $ 312 $ 216 Required: 1. What is the total manufacturing cost assigned to Job 700? 2. If Job 700 consists of 10 units, what...

  • Braverman Company

    Braverman Company has two manufacturing departments—Finishing and Fabrication. The predetermined overhead rates in Finishing and Fabrication are $22.00 per direct labor-hour and 120% of direct materials cost, respectively. The company’s direct labor wage rate is $28.00 per hour. The following information pertains to Job 700: FinishingFabricationDirect materials$470$95Direct labor$196$84 Required:1. What is the total manufacturing cost assigned to Job 700?2. If Job 700 consists of 30 units, what is the unit product cost for this job? (Round your answer to 2 decimal places.)

  • Chapter 2 Homework a Seved Help Save & Exit Submit Check my work 4 Exercise 2-5...

    Chapter 2 Homework a Seved Help Save & Exit Submit Check my work 4 Exercise 2-5 (Algo) Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Overhead Rates (LO2-4) 7.22 points Braverman Company has two manufacturing departments—Finishing and Fabrication. The predetermined overhead rates Finishing and Fabrication are $22.00 per direct labor-hour and 120% of direct materials cost, respectively. The company's direct labor wage rate is $28.00 per hour. The following information pertains to Job 700: X 02:38:29 Skipped...

  • Fickel Company has two manufacturing departments-Assembly and Testing & Packaging. The predetermined overhead rates in Assembly...

    Fickel Company has two manufacturing departments-Assembly and Testing & Packaging. The predetermined overhead rates in Assembly and Testing & Packaging are $24.00 per direct labor-hour and $20.00 per direct labor-hour, respectively. The company's direct labor wage rate is $26.00 per hour. The following information pertains to Job N-60: Testing & Packaging $ 49 $ 39 Assembly $ 400 $ 273 Direct materials Direct labor Required: 1. What is the total manufacturing cost assigned to Job N-60? (Do not round intermediate...

  • Check my work Exercise 2-5 Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined...

    Check my work Exercise 2-5 Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Overhead Rates (LO2-4) 7.5 points Braverman Company has two manufacturing departments-Finishing and Fabrication. The predetermined overhead rates in Finishing and Fabrication are $26.00 per direct labor-hour and 120% of direct materials cost, respectively. The company's direct labor wage rate is $32.00 per hour. The following information pertains to Job 700: eBook materials Finishing $ 352 stening Fabrication S 490 Hint Direct labor Fabrication $...

  • Exercise 2-5 Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Overhead Rates (LO2-4)...

    Exercise 2-5 Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Overhead Rates (LO2-4) Braverman Company has two manufacturing departments—Finishing and Fabrication. The predetermined overhead rates in Finishing and Fabrication are $25.00 per direct labor-hour and 110% of direct materials cost, respectively. The company's direct labor wage rate is $31.00 per hour. The following information pertains to Job 700: Direct materials Direct labor Finishing $ 485 $ 310 Fabrication $ 110 $ 186 Required: 1. What is the...

  • Exercise 2-5 Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Overhead Rates [LO2-4]...

    Exercise 2-5 Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Overhead Rates [LO2-4] Braverman Company has two manufacturing departments—Finishing and Fabrication. The predetermined overhead rates in Finishing and Fabrication are $21.00 per direct labor-hour and 110% of direct materials cost, respectively. The company’s direct labor wage rate is $27.00 per hour. The following information pertains to Job 700: Finishing Fabrication Direct materials $ 465 $ 90 Direct labor $ 162 $ 54 Required: 1. What is the...

  • Exercise 2-5 (Algo) Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Overhead Rates...

    Exercise 2-5 (Algo) Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Overhead Rates (LO2-4] Braverman Company has two manufacturing departments—Finishing and Fabrication. The predetermined overhead rates in Finishing and Fabrication are $20.00 per direct labor-hour and 120% of direct materials cost, respectively. The company's direct labor wage rate is $26.00 per hour. The following information pertains to Job 700: Direct materials Direct labor Finishing $460 $390 Fabrication $ 85 $286 Required: 1. What is the total manufacturing...

  • Exercise 2-5 (Algo) Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Overhead Rates...

    Exercise 2-5 (Algo) Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Overhead Rates (LO2-4] Braverman Company has two manufacturing departments—Finishing and Fabrication. The predetermined overhead rates in Finishing and Fabrication are $24.00 per direct labor-hour and 120% of direct materials cost, respectively. The company's direct labor wage rate is $30.00 per hour. The following information pertains to Job 700: Direct materials Direct labor Finishing $480 $270 Fabrication $105 $150 Required: 1. What is the total manufacturing cost...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT