Solution :
(1) Activity Rate :
Activity | Activity Rate |
Machining | $ 4.10 per MH |
Designing | $ 9.40 per Designing Hour |
Set Up | $ 143.40 per Setup |
(2) Classification
Activity | Activity Rate |
Machining | Unit Level |
Designing | Product Level |
Set Up | Batch Level |
(3) Overhead Allocation :
Total Overhead Assigned | |
Product A | $ 168,896 |
Product B | $ 214,438 |
Product C | $ 112,769 |
Working :
(1) Activity Rate :
Activity | Activity OH (a) | Activity Drivers (b) | Activity Rate (c = a / b) |
Machining | $ 345,220 | 84,200 MH | $ 4.10 per MH |
Designing | $ 79,900 | 8,500 Designing Hours | $ 9.40 per Designing Hour |
Set Up | $ 70,983 | 495 Setups | $ 143.40 per Setup |
(3) Overhead Allocation :
Activity | Activity Rate (a) | Product A | Product B | Product C | |||
Activity Driver (b) | OH Allocated (a * b) | Activity Driver (c) | OH Allocated (a * c) | Activity Driver (d) | OH Allocated (a * d) | ||
Machining | $ 4.10 per MH | 32,000 | $ 131,200 | 42,000 | $ 172,200 | 10,200 | $ 41,820 |
Designing | $ 9.40 per Designing Hour | 3,400 | $ 31,960 | 1,900 | $ 17,860 | 3,200 | $ 30,080 |
Set Up | $ 143.40 per Setup | 40 | $ 5,736 | 170 | $ 24,378 | 285 | $ 40,869 |
OH Assigned | $ 168,896 | $ 214,438 | $ 112,769 |
Please vote up and write your doubts in comment section. Would be glad to help you further.
Please please help me with this problem, theyre all together. Thank you so much! Required information...
Check my work 1 Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: 1 points Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $345, 220 Number of machine hours 79,900 Number of design hours 70,983 Number of batches Estimated Cost Driver 84,200 8,500 495 eBook Hint Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch,...
Required information E4-3, E4-4 and E4-5 Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $345, 220 Number of machine hours 79,900 Number of design hours 70,983 Number of batches Estimated Cost Driver 84,200 8,500 495 E4-3 (Algo) Calculating Activity Rates, Classifying Activities (LO 4-2, 4-4] Required: 1. Compute the activity rate for each activity. 2. Classify...
Required information 14-3, E4-4 and 54-5 Gable Company uses three activity cost pools. Each pool has a cost driver Information for Gable Company follows: Total Estimated Activity Cost Cost of Cost Pools Pool Cost Driver Driver BAE Number of Machining $345, 220 84,200 machine hours Designing 79,900 Number of design ign 8,500 costs hours Setup costs 70 982 Number of 10,903 batches 495 E4-4 (Algo) Assigning Costs Using Activity Rates (LO 4-4) Suppose that Gable Company manufactures three products, A....
Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $183,300 Number of machine hours 47,725 Number of design hours 71,150 Number of batches Estimated Cost Driver 61,100 5,750 500 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your...
Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $ 250,680 Number of machine hours 61,600 Number of design hours 66,482 Number of batches Estimated Cost Driver 71,600 7.ee 465 Required: 1. Compute the activity rate for each activity 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering...
Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $171,100 Number of machine hours 45,100 Number of design hours 66,123 Number of batches Estimated Cost Driver 59,000 5,500 465 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your...
Required Information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,eee Number of machine hours 73,6ee Number of design hours 71,600 Number of batches Estimated Cost Driver Be, evo 8, eae 500 Re 1. red: mpute the activity rate for each activity. 1551fy each activity as facility, product, batch, or unit level. complete this question by...
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,000 Number of machine hours 73,600 Number of design hours 71,600 Number of batches Estimated Cost Driver 80,000 8,000 500 Required: 1. Compute the activity rate for each activity. (Round your answers to 2 decimal places.) Activity Rate per Machine Hour Activity Machining Design Costs Setup per Design...
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,000 Number of machine hours 73,600 Number of design hours 71,600 Number of batches Estimated Cost Driver 80,000 8,000 500 Required: 1. Compute the activity rate for each activity. (Round your answers to 2 decimal places.) Activity Rate per Machine Hour Activity Machining Design Costs Setup per Design...
Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $328,400 Number of machine hours 76,725 Number of design hours 74,516 Number of batches Estimated Cost Driver 82,100 8,250 520 Required: m. Compute the activity rate for each activity, 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering your...