Question

CASE 7: RELEVANT COST ANALYSIS (CICA) Fence Company Ltd. (FC) was incorporated in March 20X4, and is equally owned by Robert

Morris Wood estimates that their costs last year were approximately $6 per linear metre for wood and S1 for nails and stain.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

REPORT TO WOODS BROTHERS

Feasibility of Operations

If Fence Company Ltd. is to succeed in business, then its fencing operations must be profitable. The snow removal activities are secondary, so I have not tried to quantify the revenue that may result from them. Instead, I have assumed that the revenue from snow removal will cover variable expenses only. Fixed costs, however, have been computed on the basis of a full year of expenses.

I have used contribution-margin analysis to calculate your break-even point and

have compared that to your capacity to see whether you currently have the resources you need to cover all of your costs.

The contribution approach separates costs into their fixed and variable components. Fixed costs are costs that do not change, regardless of how much business the company is doing. Variable costs, on the other hand, change in direct proportion to changes in levels of activity (how much business the company is doing). The difference between sales and variable costs is called the contribution margin. It is the amount available to recover fixed costs. Contribution margin is a useful tool for planning and tells you how income is affected when selling prices are changed, when different levels of output are produced, and when changes in costs are made. To use it, however, assumptions have to be made regarding different selling prices, levels of output, and so on.

Exhibit 1 shows my analysis of your contribution margin on the various orders you receive (i.e., one-house, two-house, and four-house orders). My assumptions are stated in the exhibit. As you can see, the biggest contribution, $1.66 per linear metre, is achieved on the two-house orders.

Exhibit 2 shows my calculation of your fixed costs. Please study my assumptions in this exhibit to ensure that you agree with them. Based on my assumptions, you have total fixed costs of approximately $100,000.

Using these figures, we can calculate your break-even point. Break-even is the point at which the company covers all its expenses, so there is neither profit nor loss. One problem in using break-even analysis is that an assumption has to be made about the sales mix among the different orders. I have assumed that the two-house order is most typical of your sales. As the two-house order contributes the biggest margin, the break-even in metres calculated below is the least you should sell to achieve a break-even position. If you want me to, I can re-calculate the break-even metres using different assumptions.

  $102,000 = 61,446 linear metres

$1.66

Based on my assumptions, the amount of fencing that must be installed to break even is 61,446 linear metres. This is more than your anticipated production of 50,000 linear metres.

Using the information you have given me, I have calculated the maximum number of metres that you can install. My assumptions, along with calculations, are shown in Exhibit 3. The maximum footage that can be installed in 2010 is 36,000 linear metres. This is less than your anticipated level of 50,000 linear metres. Incremental /fixed costs to increase capacity to 50,000 linear metres were estimated to be $19,500 (Exhibit 5). Assuming that all sales are two-house jobs (i.e., the maximum contribution), the contribution to fixed costs will be

50,000 x $1.66 = $83,000

This will result in a loss of

Contribution to fixed costs

$83,000

less fixed costs

102,000

Net loss

($19,000)

In conclusion, my analysis shows that Fence Company Ltd. will face a severe shortage of cash in the fall and may even face bankruptcy. Clearly, the operation is not feasible based upon the proposed pricing policy and the projected costs and level of output.

Ways to Improve Operations

Fence Company Ltd. can increase the contribution to fixed costs in several ways. It can increase prices, decrease its variable costs, decrease commissions and/or volume discounts, or increase its level of output. If fixed costs can be reduced, then the break-even point may also be reduced.

Increase prices

The contribution-margin analysis reveals that Fence Company Ltd. has a serious pricing problem. FC achieves its greatest contribution margin on sales of two-house installations. The savings from doing four-house instead of only one (economies of scale) do not appear to justify a volume discount or higher commissions. However, the cost figures do not accurately capture the economies of scale that may be present on volume orders, such as

  • more efficient use of labour and less idle time
  • less travel time and gas for transport of wood
  • possible reduced wastage on volume orders

More accurate cost figures would be useful. We do not know how much of FC’s business will be single houses vs. bulk orders, and so forth. Therefore, the previous analysis (which uses the highest contribution margin of two-house fences) is suspect at best, unless the pricing and commission structure is altered to give a uniform contribution margin.

Exhibit 4 shows my analysis of the price increase that would be required to break even at 50,000 linear metres for each of the one-house, two-house, and four-house orders. For the two-house orders the price would have to be $12.38 per metre. This price is only slightly lower than the anticipated price of $13.00. Whether or not such a price can actually be charged will depend on the market conditions prevailing in 2010. Market prices would have to be analyzed to estimate the effect of a price increase on demand.

Decrease commission rate

An alternative to increasing the price is to decrease the commission. Assuming that one salesperson sells all of the budgeted output of 50,000 linear metres, then the salesperson will receive gross commission income of

50,000 x $12 x 0.06 = $36,000

This is a high level of remuneration, given that it represents about six months' work. The commission rate could be decreased to perhaps 3%, plus a small bonus based on performance.

The feasibility of decreasing the commission rate will depend upon negotiations with the salesperson and the arrangements made in the previous year. Possibly one of the Wood brothers could take on the job of selling, to save the entire commission.

The rates of commission should be linked to the contribution margins obtained on the sales. An increased commission on volume sales is unnecessary, since the salesperson will try to sell in bulk wherever possible anyway. The salesperson should not be allowed to give discounts if commission is based on gross revenue. (Salespeople will generally give discounts readily rather than lose sales.) The giving of the discount costs the salesperson only a small amount in remuneration because his or her commission is based on gross revenue, but it costs FC a great deal as a percentage of the contribution margin. By tying the salesperson's commission to the contribution margin, the problem of harmful discounting will disappear, while the salesperson will earn the same amount overall. In short, salespeople will become more aware of profitability.

Increase capacity

Assuming that the prices and commission remain the same as planned, the level of output can be increased. Exhibit 5 shows my analysis of the required level of output and the additional costs that will be incurred to achieve that output. The increased output will be achievable if

  • sufficient sales can be made without reducing price
  • work crews can be hired
  • quality can be maintained without increased supervision
  • FC has financial resources to cope with this higher volume of business
  • warehouse capacity is sufficient

Feasibility of FC revised

Exhibit 6 provides my analysis of the overall impact of the changes suggested above. Assuming the selling price is increased to $13.00 per linear metre and output is projected to be 62,000 metres, FC will make a profit of

$63,880. The Wood brothers will be able to draw a salary of about $93,880, as $30,000 of remuneration is included in the fixed costs.

I cannot tell how likely it is that FC will be able to achieve an increased output at the assumed prices, as I have only a limited knowledge of the industry. However, FC's ability to produce at the increased level, charging a price that will not only produce a profit but will also be acceptable to customers, will determine the company's success. Thus the various options discussed above must be considered in light of the realities of FC's business world.

Inventory Control, Purchasing, Scheduling, and Costing

A systematic way of scheduling jobs must be devised. Customers should be given firm dates and, wherever possible, transportation of wood and machinery should be kept to a minimum. Installation of fences should be done on an area-by-area basis to reduce transportation costs and supervision. FC should purchase in bulk to take advantage of discounts. The company should also try to avoid having excess wood on hand due to costs of financing this inventory and storage problems. Trade-offs may have to be made when deciding on inventory levels, but they cannot be quantified without further information.

The wood allocated to each job should be accounted for by each team and given to them before the job starts. The team supervisor should complete a form showing the wood allocated; the wood remaining; the time spent on the job by employees; the amounts of supplies such as glue, stain used; and any tools broken. The teams should be controlled through site inspection and analysis of the costs.

Costs per metre for various jobs and teams should be reviewed and compared. Eventually, standard costs can be determined for each order on the basis of the above information. Once standard costs are known, it will be possible to use this information in planning future prices and levels of output.

The standards could serve as a benchmark: actual costs incurred on a job can be compared with the standards to identify any inefficiencies and ways of controlling them in the future. Standard costs will also be useful for financial reporting.

Exhibit 1 Contribution Margin Analysis Present Situation 1 House (100 metres) $1,200 2 Houses (200 metres) $2,400 4 Houses (4

It is assumed that two houses will require 200 metres of fencing and other supplies, but this will not be the case exactly, since they will usually have a common boundary. The total linear metres will depend upon the exact circumstances.

Assumptions in contribution-margin analysis

a It is assumed that the salesperson will generally discount to $12 per metre, since his or her commission is based on gross revenue, not on contribution margin.

b The sales commission has been based on the gross revenue before volume discount. The proposed commission scheme is unclear. Basing commission on gross revenue after volume discount would increase gross revenue and contribution margin by $38. The contribution margin per metre would be about $0.62.

c Costs of wood and incidentals have been adjusted for inflation by 10% to reflect assumed price increases.

d Cost of labour is computed as follows:

Three workers can build 100 metres per eight-hour day; therefore, time per 100 metres is 3 x 8 = 24 hours.

Average labour rate was $5 per hour last year; therefore, assume $5.50 per hour this year: ($5.00 + 10% increase)

24 hours x $5.50 = $132 per 100 metres

Exhibit 2 Fixed Costs for the Year April 1, 2010, to March 31, 2011 $30,000 30,000 3,0000 Salary to owners Warehouse lease To

No provision has been made for insurance, office supplies, advertising, idle time, heat, light, power and property taxes at the warehouse, interest expense, and miscellaneous.

a Based on 2009 figures unadjusted.

b Approximate estimate only.

Fixed costs will probably exceed $102,000 due to inflation and items not included.

Exhibit 3 Capacity of Operations Months # of Teams Work Days Max. in metres April May-September October & November 1 3 20 100

Assumptions

  • No provision for idle time or inclement weather; optimum projected crew efficiency is 100 metres per crew-day.
  • Crews do not work overtime and work only a five-day week. If these assumptions are incorrect, the labour costs must be revised upwards.
  • Same number of crews is assumed as last year; otherwise, the cost of gas and maintenance and of tools and truck rental must be increased. (These costs are not truly fixed costs.)

Exhibit 4 Increase Price Fixed costs Capacity Contribution per metre to break-even $102.000 50,000 metres $2.04 Price increas

61.446 metres Exhibit 5 Increase Capacity Break-even capacity fixed costs $102,000 C/M per metre $1.66 Additional fixed costs

This will be attainable with six crews during the period May–September and three crews in October and November. The fixed costs may vary slightly from those given above, since this is a circular calculation.

Exhibit 6 Feasability of FC–Revised Sales price is assumed to be $13 per linear metre. Output is projected to be 62,000 metre

Add a comment
Know the answer?
Add Answer to:
CASE 7: RELEVANT COST ANALYSIS (CICA) Fence Company Ltd. (FC) was incorporated in March 20X4, and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Subject: HRM Introduction and Instructions You have recently been hired as the Director of Human Resources...

    Subject: HRM Introduction and Instructions You have recently been hired as the Director of Human Resources for Wilson Brothers Canada and have HR responsibility for all of the company’s Canadian operations. Bob and John Wilson have asked you to prepare a report for their review focusing specifically on organizational behavior within the company. Review the Wilson Brothers Case Scenario in depth and address the required topic listed below in your analysis report. Marks are allocated for thoroughness of coverage of...

  • do SWOT analysis. CASE 01 Mystic Monk Coffee connect . David L. Turnipseed University of South...

    do SWOT analysis. CASE 01 Mystic Monk Coffee connect . David L. Turnipseed University of South Alabama . wishing to donate to the monks' cause. Father Prior Daniel Mary did not have a great deal of experience in business matters but considered to what extent the monastery could rely on its Mystic Monk Coffee operations to fund the purchase of the ranch. If Mys- tic Monk Coffee was capable of making the vision a reality, what were the next steps...

  • How can we assess whether a project is a success or a failure? This case presents...

    How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...

  • Comprehensive Income Tax Course: Module 1 4. Randy turned 16 last year and had his first...

    Comprehensive Income Tax Course: Module 1 4. Randy turned 16 last year and had his first summer job. Even though his parents are claiming him as a dependent he wants to file a return in order to get his refund. He receives his W-2 and decides he can do his own return using form 1040-EZ. Which of the following information is not found on a Form W-2? a) The taxpayer’s Social Security number b) The taxpayer’s wages, tips and other...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT