Estimated machine hours of molding department = 2,500
Estimated variable manufacturing overhead per machine hour of molding department = $1.50
Estimated total variable manufacturing overhead of molding department = Estimated machine hours of molding department x Estimated variable manufacturing overhead per machine hour of molding department
= 2,500 x 1.50
= $3,750
Estimated machine hours of fabrication department = 1,500
Estimated variable manufacturing overhead per machine hour of fabrication department = $2.30
Estimated total variable manufacturing overhead of fabrication department = Estimated machine hours of fabrication department x Estimated variable manufacturing overhead per machine hour of fabrication department
= 1,500 x 2.30
= $3,450
Total estimated variable manufacturing overhead = Estimated total variable manufacturing overhead of molding department + Estimated total variable manufacturing overhead of fabrication department
= 3,750+3,450
= $7,200
Estimated total fixed manufacturing overhead = $25,400
Total estimated manufacturing overhead = Total estimated variable manufacturing overhead + Estimated total fixed manufacturing overhead
= 7,200+25,400
= $32,600
Total estimated machine hours = 4,000
Predetermined overhead rate = Total estimated manufacturing overhead/ Total estimated machine hours
= 32,600/4,000
= $8.15 per machine hour
Actual machine hours used in Job P = 2,500
Manufacturing overhead applied for Job P = Actual machine hours used in Job P x Predetermined overhead rate
= 2,500 x 8.15
= $20,375
Total manufacturing cost assigned to Job P = Direct materials + Direct labor + Manufacturing overhead applied
= 14,000+21,800+20,375
= $56,175
Kindly comment if you need further assistance. Thanks
The Foundational 15 (LO2-1, LO2-2, LO2-3, LO2-4] [The following information applies to the questions displayed below.)...
The Foundational 15 [LO2-1, LO2-2, LO2-3, LO2-4] [The following information applies to the questions displayed below.] Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments—Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month...
The Foundational 15 (LO2-1, LO2-2, LO2-3, LO2-4) [The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the...
The Foundational 15 [LO2-1, LO2-2, LO2-3, LO2-4) [The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the...
Required information The
Foundational 15 [LO2-1, LO2-2, LO2-3, LO2-4] [The following
information applies to the questions displayed below.] Sweeten
Company had no jobs in progress at the beginning of March and no
beginning inventories. The company has two manufacturing
departments—Molding and Fabrication. It started, completed, and
sold only two jobs during March—Job P and Job Q. The following
additional information is available for the company as a whole and
for Jobs P and Q (all data and questions relate to...
The Foundational 15 [LO2-1, LO2-2, LO2-3, LO2-4] [The following information applies to the questions displayed below.] Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments—Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month...
The Foundational 15 (LO2-1, LO2-2, LO2-3, LO2-4) (The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the...
he Foundational 15 [LO2-1, LO2-2, LO2-3, LO2-4] [The following information applies to the questions displayed below.] Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments—Molding and Fabrication. It started, completed, and sold only two jobs during March—Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month...
Required Information The Foundational 15 (LO2-1, LO2-2, LO2-3, LO2-4) [The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March-Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to...
Required information The Foundational 15 [LO2-1, LO2-2, LO2-3, LO2-4] [The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments—Molding and Fabrication. It started, completed, and sold only two jobs during March, Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate...
help me please
Required information The Foundational 15 (LO2-1, LO2-2, LO2-3, LO2-4) (The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data...