Actual time = 63,000 hours
Actual rate = $13 per hour
Standard rate = $12 per hour
Labour rate variance = Actual time x (Standard rate - Actual rate)
= 63,000 x (12-13)
= 63,000 x (-1)
= $63,000 unfavorable
The labour rate variancec for March = $63,000 unfavorable
Kindly comment if you need further assistance. Thanks
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: 55.00 36.00 Direct materials: 5 $ kg at $11.00 per kg Direct labour: 3 hours at $12 per hour Variable overhead: 3 hours at $7 per hour 21.00 $ 112.00 Total standard cost per unit The company planned to produce and sell The company planned to produce and sell 21,000 units in March. However,...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: 55.00 36.00 Direct materials: 5 $ kg at $11.00 per kg Direct labour: 3 hours at $12 per hour Variable overhead: 3 hours at $7 per hour 21.00 $ 112.00 Total standard cost per unit The company planned to produce and sell The company planned to produce and sell 21,000 units in March. However,...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: 55.00 36.00 Direct materials: 5 $ kg at $11.00 per kg Direct labour: 3 hours at $12 per hour Variable overhead: 3 hours at $7 per hour 21.00 $ 112.00 Total standard cost per unit The company planned to produce and sell The company planned to produce and sell 21,000 units in March. However,...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: 55.00 36.00 Direct materials: 5 $ kg at $11.00 per kg Direct labour: 3 hours at $12 per hour Variable overhead: 3 hours at $7 per hour 21.00 $ 112.00 Total standard cost per unit The company planned to produce and sell The company planned to produce and sell 21,000 units in March. However,...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: 55.00 36.00 Direct materials: 5 $ kg at $11.00 per kg Direct labour: 3 hours at $12 per hour Variable overhead: 3 hours at $7 per hour 21.00 $ 112.00 Total standard cost per unit The company planned to produce and sell The company planned to produce and sell 21,000 units in March. However,...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 4 kg at $9.00 per kg $ 36.00 Direct labour: 3 hours at $12 per hour 36.00 Variable overhead: 3 hours at $8 per hour 24.00 Total standard cost per unit $ 96.00 The company planned to produce and sell 28,000 units in March. However, during March the company actually produced and...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 5 kg at $9.00 per kg $ 45.00 Direct labour: 3 hours at $14 per hour 42.00 Variable overhead: 3 hours at $9 per hour 27.00 Total standard cost per unit $ 114.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 6 kg at $8.00 per kg $ 48.00 Direct labour: 4 hours at $13 per hour 52.00 Variable overhead: 4 hours at $5 per hour 20.00 Total standard cost per unit $ 120.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 6 kg at $9.00 per kg Direct labour: 3 hours at $15 per hour Variable overhead: 3 hours at $5 per hour $ 54.00 45.00 15.00 Total standard cost per unit $ 114.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 6 kg at $8.00 per kg $ 48.00 Direct labour: 4 hours at $13 per hour 52.00 Variable overhead: 4 hours at $5 per hour 20.00 Total standard cost per unit $ 120.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...