The City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows:
Code |
Description |
Time (hrs) |
Immediate Predecessor(s) |
A |
Find location; determine resource requirements |
20 |
None |
B |
Requisition of lumber and sand |
65 |
A |
C |
Dig and grade |
95 |
A |
D |
Saw lumber into appropriate sizes |
35 |
B |
E |
Position lumber in correct locations |
25 |
D, C |
F |
Nail lumber together |
15 |
E |
G |
Put sand in and under the equipment |
20 |
F |
H |
Put dirt around the equipment |
15 |
F |
I |
Put grass all over the garden, landscape, paint |
25 |
G, H |
Refer to the legend for the activity that corresponds to each code.
Using the line drawing tool, draw a Gantt chart for activities E through I of the project.
ACTIVITY |
DURATION |
ES |
EF |
LS |
LF |
SLACK |
A |
20 |
0 |
20 |
0 |
20 |
0 |
B |
65 |
20 |
85 |
20 |
85 |
0 |
C |
95 |
20 |
115 |
25 |
120 |
5 |
D |
35 |
85 |
120 |
85 |
120 |
0 |
E |
25 |
120 |
145 |
120 |
145 |
0 |
F |
15 |
145 |
160 |
145 |
160 |
0 |
G |
20 |
160 |
180 |
160 |
180 |
0 |
H |
15 |
160 |
175 |
165 |
180 |
5 |
I |
25 |
180 |
205 |
180 |
205 |
0 |
FORWARD PASS
We calculate the ES and EF values using a forward pass where the ES of an activity is the maximum EF of all the predecessor activities.
BACKWARD PASS
We calculate the LS and LF values using a backward pass where the LF of the activity is the minimum of all the successor activities.
SLACK
Slack is the value which is determined by subtracting EF from the LF or ES from the LS.
CRITICAL PATH
Critical path is the chain in the project network where the slack value of all the activities is 0, what this means is that any delay in these activities would result in delaying the entire project.
CRITICAL PATH = ABDEFGI
DURATION OF PROJECT = 205
The City Commission of Nashville has decided to build a botanical garden and picnic area in...
The City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: Ś Time (hrs) Immediate Predecessor(s) ó 20 None ó 65 105 Code Description Find location; determine resource requirements B Requisition of lumber and sand Dig and grade Saw lumber into appropriate sizes Position lumber in correct locations...
The City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: AH B Time (hrs) Immediate Predecessor(s) c 20 None E- Code Description Find location; determine resource A requirements B Requisition of lumber and sand с Dig and grade D Saw lumber into appropriate sizes E Position lumber...
a B C D The City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: D Time Immediate Code Description (hrs) Predecessor(s) Find location; determine resource А 20 None requirements B Requisition of lumber and sand 60 с Dig and grade 95 D Saw lumber into appropriate sizes...
question 3.12
Chapter 3 Project Management 91 Table for 3.8 Time Activity Immediate Code Description in hours) Predecesur Planning Find location determine resource requirements Purchasing Requisition of lumber and sand Excavation Planning Dig and grade Sawing Planning Saw lumber inte appropriate sizes Placement Purchasing Position lumber in comect locations Sawing. c om Assembly Nail lamber together Placement Tafill Put sand in and under the equipment Ambly Outfill Put dirt a nd the equipment Assembly Decoration Put grass all over the...