Question

The City Commission of Nashville has decided to build a botanical garden and picnic area in...

The City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as​ follows:

                                                                                 

Code

Description

Time

​(hrs)

Immediate​ Predecessor(s)

A

Find​ location; determine resource requirements

20

None

B

Requisition of lumber and sand

65

A

C

Dig and grade

95

A

D

Saw lumber into appropriate sizes

35

B

E

Position lumber in correct locations

25

​D, C

F

Nail lumber together

15

E

G

Put sand in and under the equipment

20

F

H

Put dirt around the equipment

15

F

I

Put grass all over the​ garden, landscape, paint

25

​G, H

Refer to the legend for the activity that corresponds to each code.

Using the line drawing​ tool, draw a Gantt chart for activities E through I of the project.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

ACTIVITY

DURATION

ES

EF

LS

LF

SLACK

A

20

0

20

0

20

0

B

65

20

85

20

85

0

C

95

20

115

25

120

5

D

35

85

120

85

120

0

E

25

120

145

120

145

0

F

15

145

160

145

160

0

G

20

160

180

160

180

0

H

15

160

175

165

180

5

I

25

180

205

180

205

0


FORWARD PASS

We calculate the ES and EF values using a forward pass where the ES of an activity is the maximum EF of all the predecessor activities.

BACKWARD PASS

We calculate the LS and LF values using a backward pass where the LF of the activity is the minimum of all the successor activities.

SLACK

Slack is the value which is determined by subtracting EF from the LF or ES from the LS.

CRITICAL PATH

Critical path is the chain in the project network where the slack value of all the activities is 0, what this means is that any delay in these activities would result in delaying the entire project.

CRITICAL PATH = ABDEFGI

DURATION OF PROJECT = 205

GANTT CHART 20 95 ACTIVITY 15 15 25 0 50 100 150 200 250

Add a comment
Know the answer?
Add Answer to:
The City Commission of Nashville has decided to build a botanical garden and picnic area in...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The City Commission of Nashville has decided to build a botanical garden and picnic area in...

    The City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: Ś Time (hrs) Immediate Predecessor(s) ó 20 None ó 65 105 Code Description Find location; determine resource requirements B Requisition of lumber and sand Dig and grade Saw lumber into appropriate sizes Position lumber in correct locations...

  • The City Commission of Nashville has decided to build a botanical garden and picnic area in...

    The City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: AH B Time (hrs) Immediate Predecessor(s) c 20 None E- Code Description Find location; determine resource A requirements B Requisition of lumber and sand с Dig and grade D Saw lumber into appropriate sizes E Position lumber...

  • a B C D The City Commission of Nashville has decided to build a botanical garden...

    a B C D The City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: D Time Immediate Code Description (hrs) Predecessor(s) Find location; determine resource А 20 None requirements B Requisition of lumber and sand 60 с Dig and grade 95 D Saw lumber into appropriate sizes...

  • question 3.12 Chapter 3 Project Management 91 Table for 3.8 Time Activity Immediate Code Description in...

    question 3.12 Chapter 3 Project Management 91 Table for 3.8 Time Activity Immediate Code Description in hours) Predecesur Planning Find location determine resource requirements Purchasing Requisition of lumber and sand Excavation Planning Dig and grade Sawing Planning Saw lumber inte appropriate sizes Placement Purchasing Position lumber in comect locations Sawing. c om Assembly Nail lamber together Placement Tafill Put sand in and under the equipment Ambly Outfill Put dirt a nd the equipment Assembly Decoration Put grass all over the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT