Question 1 At the site of a proposed building, 12 m of sand (k = 3.5 x 10-5 m/s, e = 0.55, Gs = 2.65) overlies impermeable be

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Cal value of k will be obtained by using flow net. The discharge in pumping will be equal to the seepage flow of soil into thod loss per equipotential drop- 9 = 0.44m. nead loss at outside wall on 1.5 m above the base of wall = 0.44x3 =1.32m. · porepore water pressure inside the wall above 15m base of the wall - Pressure head at point thead loss yet to occure at that poin(y). Chitical hydraulic gradient (ie) = Oh! He - 2.657 H0.55 -0.419 The distance be the last last two equipotantials is im. .fos for hearing = Effective wt above the base of wall pore pressure at base of the au Pop оf bаcе од огц — 3+D-чухч ХҮo = 46.

Add a comment
Know the answer?
Add Answer to:
Question 1 At the site of a proposed building, 12 m of sand (k = 3.5...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 3) At a construction site, a site investigation has been carried out. At ground level (-1...

    3) At a construction site, a site investigation has been carried out. At ground level (-1 m NAP) a clay layer with a thickness of 4 m is found (y = 16 kN/m”, k = 2.0x10-12 m/s, Cp = 15), followed by a sand layer of 6 m thickness (y = 20 kN/m², k = 5.0x10-7 m/s), another clay layer of 4m thickness (y = 18 kN/m3, k = 4.5x10-11 m/s, Cp = 25), and finally another sand layer (y...

  • Question 4 In order to determine the in-situ density of the soil at a site, the...

    Question 4 In order to determine the in-situ density of the soil at a site, the sand replacement test conducted and the following results were obtained: 2.12 kg 1.85 kg Mass of soil extracted from the hole Mass of soil after oven drying Mass of sand pouring cylinder initially 5.45 kg Mass of sand pouring cylinder finally 3.27 kg Volume of cone in sand pouring cylinder 0.25x103 m3 Density of sand in cylinder 1579 kg/m If the specific gravity of...

  • PLEASE SOLVE FOR DAM SITE 4. POND TOP 15 m POND BOTTOM 5m 1 Th= h...

    PLEASE SOLVE FOR DAM SITE 4. POND TOP 15 m POND BOTTOM 5m 1 Th= h = 15m Rock 25m below pond bottom h = 3m 25 m h = 12m h = 9m h = 6m EXAM #2 (3-31-2020), SECTION 002 Students, Last Name Begins DAM SITE A TOC D TOL МТО Р O TOZ SOIL PERMEABILITY (Meters/Sec) 1 X 10 -(minus) 5 1 x 10- (minus) 3 4 X 10 - (minus) 6 7 X 10 -(minus) 5...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT