Question

Compute the average multifactor productivity for this process.

ogether with labor and material (X-ray film) inputs. The standard charge valueofte data f per unit. Overhead is charged weekl

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Multifactor Productivity = Output/Input

We have to calculate the average multifactor productivity.

Here,

Total Output = 412+364+392+408 = 1576

Dollar Value of Output = 1576*125 = 197000

Input = Total Labor Cost + Total Material cost + Total Overhead Cost

Total Labor Used = 6+5+5+6 = 22

Total Labor Cost = 22*40*16 = 14080

Total Material Used = 2840 + 2550 + 2720 + 2790 = 10900

Total Material Cost = 10900*10 = 109000

Total Overhead Cost = 4*1500 + 0.5*14080 = 13040

Input = 14080 + 109000 + 13040 = 136120

Multifactor Productivity = 197000/136120

Multifactor Productivity = 1.4473

Add a comment
Know the answer?
Add Answer to:
Compute the average multifactor productivity for this process. ogether with labor and material (X-ray film) inputs....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The weekly output of a production process is shown below, together with data for labor and...

    The weekly output of a production process is shown below, together with data for labor and material 3. inputs. The standard inventory value of the output is $125 per unit. Overhead is charged weekly at the rate of $1,500 plus.5 times direct labor cost. Assume a 40-hour week and an hourly wage of $16. Material cost is $10 per nunning foot. What is the average multifactor productivity for this process? Material (t) Week Output 412 #Workers 6 2840 2550 2...

  • A golf specialty wholesaler operates 350 days per year. Management is trying to determine an inventory...

    A golf specialty wholesaler operates 350 days per year. Management is trying to determine an inventory policy for its 1-irons. The cost to place orders with the supplier is $25/order; the demand averages 12,000 items per day, with a standard deviation of 3,000 item. The annual inventory holding cost is $2.00 per item. The lead time form the supplier is 5 days, with a standard deviation of 2 days. It is important to maintain a 95 percent cycle-service level to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT