3) Given,
Borrow site:
Soil density = 120 pcf
Water content = 15%
Dry density = Soil density / (1+water content) = 120/1.15 = 104.35 pcf
Fill site:
Soil density = 135 pcf
Water content = 17%
Dry density = Soil density/(1+water content) = 135/1.17 = 115.385 pcf
Assume 1 cubic yard to be filled in fill site
V1 = 1.106 cubic yards
Water added to borrow pit = = 104.35 * 1 * 27 * (0.17 - 0.15) = 56.35 lbs
Number of gallons = 56.35/8.34 = 6.76 gallons
on and Volume Change: 10 points An earthwork project has the following conditions: Borrow Site -soil...
Please solve problem 1 and show formulas used Tables for reference: Homework 6- Chapter 9 Problem 1: A crawler hoe having a 2 -cy bucket and whose cost per hour, including the wages to an operator, is $109 will excavate and load haul units under each of the stated conditions. The maximum digging depth of the machine is 22 ft. Determine the cost per bank cubic yard for each condition. (Condition 1: 315 bey/hr, S0.346/bcy; condition 2: 289 bey/hr, S0.377/bcy;...