on and Volume Change: 10 points An earthwork project has the following conditions: Borrow Site -soil density is 120 PCF with
0 0
Add a comment Improve this question Transcribed image text
Answer #1

3) Given,

Borrow site:

Soil density = 120 pcf

Water content = 15%

Dry density = Soil density / (1+water content) = 120/1.15 = 104.35 pcf

Fill site:

Soil density = 135 pcf

Water content = 17%

Dry density = Soil density/(1+water content) = 135/1.17 = 115.385 pcf

Assume 1 cubic yard to be filled in fill site

Vi V2 701

Vi 115.385 104.35

V​​​​​​1 = 1.106 cubic yards

Water added to borrow pit = 7aV(W2 – w1 = 104.35 * 1 * 27 * (0.17 - 0.15) = 56.35 lbs

Number of gallons = 56.35/8.34 = 6.76 gallons

Add a comment
Know the answer?
Add Answer to:
on and Volume Change: 10 points An earthwork project has the following conditions: Borrow Site -soil...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Please solve problem 1 and show formulas used Tables for reference: Homework 6- Chapter 9 Problem...

    Please solve problem 1 and show formulas used Tables for reference: Homework 6- Chapter 9 Problem 1: A crawler hoe having a 2 -cy bucket and whose cost per hour, including the wages to an operator, is $109 will excavate and load haul units under each of the stated conditions. The maximum digging depth of the machine is 22 ft. Determine the cost per bank cubic yard for each condition. (Condition 1: 315 bey/hr, S0.346/bcy; condition 2: 289 bey/hr, S0.377/bcy;...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT