Question
Please solve problem 1 and show formulas used

Homework 6- Chapter 9 Problem 1: A crawler hoe having a 2 -cy bucket and whose cost per hour, including the wages to an opera

Tables for reference:



TABLE 9.1 Fill factors for front shovel buckets Fill factor* (%) Material Bank clay; earth Rock-earth mixture (Easy digging)
TABLE 9.4 Fill factors for hydraulic hoe buckets Fill factor (%) Material Moist loam/sandy clay Sand and gravel Rock-poorly b
TABLE 9.6 Bucket fill factors for wheel and track loaders Wheel loader Track loader fill factor (%) Material fill factor (%)
TABLE 9.9 Representative specifications for track loaders Size, heaped bucket сарacity (су) Raise/ Bucket dump clearance (ft)
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution as follows:

Formula for productivity of an excavator:

3600 x Q XFXE Productivity P (CY /hour) = t x 60 x (1 + 5)

In above formula,

Q = Bucket Capacity (CY)

F = Fill Factor

E = Efficiency (min/hr.)

t= cycle time (sec)

S = Free Swell index

  1. Determination of productivity and cost for moist loam, earth

Maximum digging depth for hoe =22 ft

Depth of excavation = 15 ft

% Depth = 15/22 = 68%

Angle of swing = 60o

Hence the hoe is working above average conditions (As per conditions stated in table 9.5)

Q = 2 cy

F = 105% =1.05 (Average value for moist loam from table 9.4)

E = 50 min per hour

t = 19 sec (due to digging depth is 68% of maximum digging depth, additional 2sec per cycle assumed than given in table 5)

S = 0

Hence,

3600 x 2 x 1.05 x 50 Productivity P =- = 331.5789 cy/hour P = 19 x 60 X (1+0)

The above productivity falls under condition 1. Hence haul cost shall be $0.346 per bcy

Cost of hoe per hour = $109

$109 Cost of excavation per cy = 331 5789 = $0.3287per cy

Total Cost for sandy loam, earth = Cost of excavation + Haul cost = $0.3287 + $0.346 = $0.6474 per bcy

  1. Determination of productivity and cost for sand and gravel

Maximum digging depth for hoe =22 ft

Depth of excavation = 12 ft

% Depth = 12/22 = 55%

Angle of swing = 80o

Hence the hoe is working above average conditions (As per conditions stated in table 9.5)

Q = 2 cy

F = 102.5% =1.025 (Average value for sandy clay from table 9.4)

E = 45 min per hour

t = 19 sec (due to angle of swing is 80o, additional 2sec per cycle assumed)

S = 14% = 0.14

Hence,

3600 x 2 x 1.025 x 45 Productivity P = 19 x 60 x (1 + 0.14) y = 19 x 60 X (1+0 14 = 255.5402 cy/hour

The above productivity falls under condition 2. Hence haul cost shall be $0.377 per bcy

Cost of hoe per hour = $109

Cost of excavation per cy = $109 407 = $0.4265per cy

Total Cost for sand and gravel = Cost of excavation + Haul cost = $0.4265 + $0.377 = $0.8035 per bcy

Hope the same is clear. In case of any clarifications, please leave comment in comments section.

Please give us a good rating, if you are satisfied with the response.

How would you rate our reply?

Best Regards

Chegg Expert Team

Add a comment
Know the answer?
Add Answer to:
Please solve problem 1 and show formulas used Tables for reference: Homework 6- Chapter 9 Problem...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Part 2 Based upon the results to part 1, the project requires hauling materials to, or...

    Part 2 Based upon the results to part 1, the project requires hauling materials to, or from, the site. The following equipment is available for earthwork operations: - One 5-cy heaped capacity bucket loader; a 0.5 min cycle time; 90% fill capacity. - One 7-cy heaped capacity bucket loader; a 0.6 min cycle time; 90% fill capacity. 45.9-cy heaped capacity off-road trucks; a 0.5 min dump time; 100% fill capacity. - Loaded trucks travel through the following three sections: Haul...

  • please help me , show all steps , please make your font clear.. Problem 1: A...

    please help me , show all steps , please make your font clear.. Problem 1: A project to move packed earth requires you to decide whether to use a dozer/scraper operation or excavator/truck operation. Determine the most economical operation based on the dozer/scraper operation estimated at S6.25/lcy All equipment carries a rated heaped capacity, has a fill factor of 105%, and works 45-min hours. Excavators costs $95/hr (including operator), cycle time is 0.28 min, and bucket heaped capacity is 3...

  • Part 2 Based upon the results to part 1, the project requires hauling materials to, or...

    Part 2 Based upon the results to part 1, the project requires hauling materials to, or from, the site. The following equipment is available for earthwork operations: - One 5-cy heaped capacity bucket loader; a 0.5 min cycle time; 90% fill capacity. - One 7-cy heaped capacity bucket loader; a 0.6 min cycle time; 90% fill capacity. 45.9-cy heaped capacity off-road trucks; a 0.5 min dump time; 100% fill capacity. - Loaded trucks travel through the following three sections: Haul...

  • Part 1 Complete the following Earthwork Sheet Material: Earth and Gravel, Swell Factor: 83 Strip fill(cy...

    Part 1 Complete the following Earthwork Sheet Material: Earth and Gravel, Swell Factor: 83 Strip fill(cy Total till och Total cut beyl Adj fill (byl Sum (beyl Mass ordinate 1.23 056 2.37 1.20 2.36 3.07 3.60 3.77 3.09 3.01 4.65 Strip cut (boyil 0.04 1.04 097 3.22 2.08 2.33 2.51 1.85 161 1.74 0.88 109 35.70 5.58 18 3.12 2.03 6.77 2.01 2.53 0.82 1.08 1.20 1.92 1.59 1.82 3.95 3.25 2.74 150 7.42 556 80 End-area End area cut...

  • (50) 7. Analyze the following operation. A 385C Excavator will be used to load material into a CAT 740 (no ejector) articulated truck. The excavator is equipped with a 6 cy heaped bucket and is...

    (50) 7. Analyze the following operation. A 385C Excavator will be used to load material into a CAT 740 (no ejector) articulated truck. The excavator is equipped with a 6 cy heaped bucket and is capable of cycling every 30 seconds. The material being loaded weighs 3,300 lbs cy. The job efficiency is 90%. The trucks will be hauling the nmaterial 4000 feet over a road with a total rolling resistance of 9% to the dumpsite and 10% total rolling...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT