A production process has two machines. The first machine has a capacity of 500 units per hour and the second machine has a capacity of 350 units per hour. Demand for the process is 100 units per hour.
(a) In a push process, what would be the utilization of the first machine?
Utilization of the first machine is ___%?
(b) How would the situation change with a pull system?
The utilization would drop to ___%?
A. ) push system means producing at maximum capacity which means 500 units will be produced at 100% utilization rate.
B.) In pull system, demand decides the production rate.
Demand is 100 units.
First machine alone can produce 100 units even if it slowed down to the capacity of 2and machine.
Utilization of first machine(in pull system) = 100/ 500 = 20%.
A production process has two machines. The first machine has a capacity of 500 units per...
A factory manufactures two products, each requiring the use of three machines. The first machine can be used at most 70 hours; the second machine at most 40 hours; and the third machine at most 90 hours. The first product requires 2 hours on machine 1, 1 hour on machine 2, and 1 hour on machine 3; the second product requires 1 hour on machines 1 and 2 and 3 hours on machine 3. The profit is $40 per unit...
1. Consider a single workstation comprising one machine. (i) What will be the production rate of this workstation, assuming all parts processed on it take (ii) Assume that the demand is 10/day, where the day has 8 working hours, what will be the (ii) What will be the utilization of the workstation given the demand in (ii)? 20 min? throughput? (iv) If a 2nd identical machine is added to the workstation, what will be the capacity of the workstation for...
Buzz Appliances manufactures two products: Food Processors and Espresso Machines. The following data are available: Food Processors Espresso Makers Sales price $125 $265 Variable costs $50 $170 The company can manufacture either two food processors per machine hour or three espresso machines per machine hour. The company's production capacity is 1,400 machine hours per month. The company has demand of 2,700 espresso machines. How many espresso machines and food processors should they produce based on demand and available machine hours?...
A process has two stages. In the first stage, a machine makes two components, call them type A and B. It takes 250 seconds to switch production between the component types. During that time no production occurs. When in production, each component (A or B) requires 0.6 seconds to be completed. In the second stage, the components, A and B, are assembled to make a final product, call it C. The assembly stage can combine the two components into 1...
A manager is trying to decide whether to buy one machine or two. If only one machine is purchased and demand proves to be excessive, the second machine can be purchased later. Some sales would be lost, however, because the lead time for delivery of this type of machine is six months. In addition, the cost per machine will be lower if both machines are purchased at the same time. The probability of low demand is estimated to be 0.20...
W on Hep Buzz Appliances manufactures two products: Food Processors and Espresso Machines. The following data are available: Food Processors Espresso Makers Sales price $155 $255 Variable costs $60 $190 The company can manufacture either two food processors per machine hour or three espresso machines per machine hour. The company's production capacity is 1.500 machine hours per month To maximize profits, what product and how many units should the company produce in a month (assuming unlimited demand for both products/...
Metalco is in the process of hiring a repairperson for a 10-machine shop. Two candidates are under consideration. The first candidate can carry our repairs at the rate of 5 machines per hour and earns $15 an hour. The second candidate, being more skilled, receives $20 an hour and can repair 8 machines per hour. Metalco estimates that each broken machine will incur a cost of $50 an hour because of lost production. Assuming that machines break down according to...
#12 $245 Buzz Appliances manufactures two products: Food Process and Espresso Machines. The following data are available Food Processo Espresso Makers Sales price $145 Variable costs $180 The company can manufacture either two food processors per machine hour or the espresso machines per machine hour. The company's production capacity is 1.200 machine hours per month What is the contribution margin per machine hour for espresso machines? O A. $705 O B. $65 OC. $110 OD. $195
Two-step Process Utilization: A two- used to finish a product: painting and drying. There are 5 workers and each one takes an average of 60 minutes to paint each unit. Drying takes place in an oven that can hold up to 100 units and it takes 5 minutes to load each unit. Once all the units are loaded into the oven, it takes 6 hours to dry each load. Assume that the process is capacity constrained (so the demand rate...
A work cell in a local manufacturer has a workstation with 4 machines and each unit needs to pass through each machine in order to be completed. Each machine has a production capacity of four units per hour. What is the process time of the work cell in minutes per unit?