Q: Complete the following "Reason column" for your software engineering risk analysis project.
Please Note that there is a sample for filling the reason column please see it.
Risk |
Probability |
Effects |
Reason |
Organizational financial problems force reductions in the project budget (7). |
Low |
Catastrophic |
|
It is impossible to recruit staff with the skills required for the project (3). |
High |
Catastrophic |
|
Key staff are ill at critical times in the project (4). |
Moderate |
Serious |
|
Faults in reusable software components have to be repaired before these components are reused. (2). |
Moderate |
Serious |
|
Changes to requirements that require major design rework are proposed (10). |
Moderate |
Serious |
|
The organization is restructured so that different management are responsible for the project (6). |
High |
Serious |
|
The database used in the system cannot process as many transactions per second as expected (1). |
Moderate |
Serious |
|
The time required to develop the software is underestimated (12). |
High |
Serious |
|
Software tools cannot be integrated (9). |
High |
Tolerable |
|
Customers fail to understand the impact of requirements changes (11). |
Moderate |
Tolerable |
|
Required training for staff is not available (5). |
Moderate |
Tolerable |
|
The rate of defect repair is underestimated (13). |
Moderate |
Tolerable |
|
The size of the software is underestimated (14). |
High |
Tolerable |
|
Code generated by code generation tools is inefficient (8). |
Moderate |
Insignificant |
A sample for Completing the reason column :-
Risk |
Probability |
Effects |
Reason |
Development of the wrong user interface which will result in redesign and implementation from scratch.(1) |
High |
Catastrophic |
Probability of such risk is high due to the presence of more than one service and different requirements. It causes a catastrophic effect because it basically doesn’t meet the assigned requirements. |
Depending on a technology that is still being developed. (2) |
Low |
Serious |
The occurrence of this risk due to the presence of only one technology but it doesn’t usually happen and it causes a serious issue in the time and cost of the project. |
Too much conflicts among team members developing the software will result in poor communication and therefore poor designing, incomplete work and late delivery of the product.(3) |
Moderate |
Catastrophic |
Too much disagreement in any team designing has a chance of 50% occurring due to each member having a different point of view. If such risk occurs, it is going to cause a huge mess and an imbalance. Therefore, the project will not be delivered correctly and on time. |
Replacement of team members or change in tasks among between the team members. (4) |
High |
Serious |
Sometimes a member or more in a team can fail to complete his task and therefore pass it to another team member or probably switch tasks due to improper division of work. Also, team members might leave and therefore replaced by others which will cause conflicts related with time and organization. |
Failing to integrate the software tools. (5) |
High |
Tolerable |
In most cases, incorporating software tools along with the project is a concern. However, it is not that much of a concern because it can be easily fixed by training or by seeking the help of a specialist. |
Introduction of new requirements according to the customer’s desire.(6) |
Very High |
Serious |
Customers have unlimited requirements and expectations. This is why the risk of introducing new requirements is really high. In addition, it will cause re-developing or re-designing some software functions of the system and this is costly and time-consuming. |
Software productivity rate is overestimated.(7) |
High |
Tolerable |
Software productivity is often assumed to be quick by most developers. Nevertheless, they get surprised that it is not. However, it does not cause that much of a great impact on the development. |
The size of the software and integration effort is underestimated. (8) |
High |
Serious |
Misinterpretation of the amount of effort to build the software is always an issue. Developers don’t realise this issue until they start actually developing the functions of the system which is approximately halfway through the development process. They also don’t realise how bad it can get when time starts running out and the project is not even past halfway the assigned time for the project. |
We need at least 10 more requests to produce the answer.
0 / 10 have requested this problem solution
The more requests, the faster the answer.
Q: Complete the following "Reason column" for your software engineering risk analysis project. Please Note that...
1 You are the project manager in an engineering project and have recently signed a contract with a software vendor for the development of a complicated control solution. The software will be used to control machinery equipment which your project team is currently developing. The contract is a lump-sum contract. The contractor has target cost estimated which seem rather low to you. Which of the following statements is not true for this situation? a It is the contractor's risk in...
Please help writing a well structured document using the below Agile Runbook - Our Overall Delivery Process How do we initiate a Project? Any project is a response to a pain point or desire expressed by either customers, internal stakeholders, employees, or regulatory authorities. In short, a project is a time bound and specific goal oriented task-system that is born out of an ask from any stakeholder. Project initiation is laying down a new project by defining its goals, objectives,...
Select two of the discussion questions and analyze the case study using project management principles. Apply your knowledge of project management to the facts presented in the case study to describe how you would proceed. We only need to answer one of the questions. A thorough answer will probably require 300 to 500 words for each question. Feel free to use text bullets, tables, or graphics to summarize your points. Questions Q1: Make or Buy decision – Describe the make...
What an Executive Summary Is An executive summary is a specific type of document that does two things: it summarizes a research article, and it offers recommendations as to how information from the article can be used. Some long reports can contain an executive summary section, as indicated in the Pearson handbook. Write a 2 pahe Executive Summary In business contexts, an executive summary is always written for a specific purpose: to explain the information in the article to a...
RADICO’S CHALLENGE The executive staff at Radico Corporation was quite pleased with the one-day training program they attended on the benefits of using agile and Scrum on some of their projects. Radico provided products and services to both public and private sector clients, almost all of it through competitive bidding. IT was not required for any of the products and services Radico provided. Agile and Scrum had proven to be successful on internal IT projects, but there were some concerns...
QUESTION 1: Why must project manager should have good technical skills but also good management skills? QUESTION 2: **Communication and Communicator are related" This quote from the text suppose that the communication process is lead by the spokeperson. Do you think is it a gift" to be a good communicator or a skill to improve ( use example of your knowledge to answer)? QUESTION 3: Look at the text paragraph yellow highlighted, and do you think that in today's world...
Summary should briefly analyze the central problems and issues of the case and provide some analysis and suggestions. Thank you. Lean Initiatives and Growth at Orlando Metering Company It was late August 2002 and Ed Cucinelli, vice president of Orlando Metering Company (OMC), sat in his office on a late Saturday morning. He had come in to prepare for some strategic planning meetings that were scheduled for the upcoming week. As he noticed the uncommon silence in the building, Ed...
How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...
Please help! Your task is to select an idea, improvement or opportunity that could be applied in a business operation. Describe the business and the project you might initiate. You will need to describe and define the project in context. Explain why such a project would be beneficial. What procedures might you use to ensure that the project was sponsored and supported by the organisation? Define the project, write a project narrative and develop a project plan, including the processes...
Please help! Your task is to select an idea, improvement or opportunity that could be applied in a business operation. Describe the business and the project you might initiate. You will need to describe and define the project in context. Explain why such a project would be beneficial. What procedures might you use to ensure that the project was sponsored and supported by the organisation? Define the project, write a project narrative and develop a project plan, including the processes...