An old existing timber bridge with a concrete deck is currently in service in the south...
An old existing timber bridge with a concrete deck is currently in service in the south west of Western Australia. It has been proposed to increase the strength of the bridge by adding steel plates to the timber beams to enable larger trucks to use the road on which the bridge is located. The existing bridge has 460* 100mm timber beams at 1.8 metre centres. The concrete deck (which is fixed to the timber beams to enable composite action) is...
Part A- Answer all questions (Total Marks for Part A: 120) Part A- Question 1 (Total Marks for Part A - Question 1: 24) A 140mm thick concrete slab is supported by a series of parallel 460UB82.1 steel beams at 2400mm centres. Assume there is sufficient bond between the steel beam and the concrete slab to enable the materials to act together as a composite unit Assume for steel E 200 GPa ? 280 MPa for concrete E-25 GPa ?...
Problem: A 7 m wide concrete bridge deck (with a span of 9.1 m) is supported by two identical simply supported lightly welded I-beams. The 350 mm thick concrete deck acts as a continuous lateral restraint along the whole length of the beams. The bridge is subjected to a uniformly distributed live load (Q) of 10 kPa. The dead load consists of the self- weight of the I-beams and the concrete deck. If the yield stress of the beams fy...
Question 1 (Total 100/3 Marks) Figure 1 (all units are mm) shows a simply supported beam of span 2500 mm with a 5 kN/m load. The cross-section of the beam is a composite section made from two steel plates attached to the top and bottom of a timber section. The top steel plate is 5 mm wide and 20 mm deep. The bottom steel plate is also 5 mm wide but 10 mm deep. The timber section is 50 mm...