calculation of direct material price variance: |
= (Standard price per unit of material - Actual price per unit of material) × Actual quantity |
= ($0.31/Micron - $0.29/Micron ) × 79000 Micron = $1580 F |
Calculation of direct material quantity variance |
=(standard quantity of material required for actual production - actual quantity used) × Standard price per unit |
((7 Micron X 4600 Unit)-40250 Pound )X $0.31 = $2496 UF |
* Actual Qty used = 79000-38750=40250 Micron |
Calculation of direct labor rate variance |
= (Standard direct labor rate per hour - actual direct labor rate per hour) × Actual hours used |
= ($7.50/hour - $8.10/hour) × 5560 Hours= $3336 UF |
* Actual Hourly Rate:=$45036/5560=$8.10 / Hour |
Calculation of direct labor efficiency variance: |
= (standard hours required for actual production - actual hours used) × standard overhead recovery rate |
= (1.1 Hour × 4600 Unit - 5560) × $7.50 = $3750 U F |
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 6 microns per toy at $0.35 per micron Direct labor: 1.1 hours per toy at $6.50 per hour During July, the company produced 4,600 Maze toys. The toy's production data for the month are as follows: Direct materials: 72,000 microns were purchased at a cost of...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 6 microns per toy at $1.50 per micron Direct labor: 1.3 hours per toy at $21 per hour During July, the company produced 3,000 Maze toys. The toy's production data for the month are as follows: Direct materials. 25,000 microns were purchased at a cost of...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 6 microns per toy at $0.31 per micron Direct labor: 1.4 hours per toy at $7.20 per hour During July, the company produced 5,100 Maze toys. The toy's production data for the month are as follows: Direct materials. 75,000 microns were purchased at a cost of...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy Direct materials: 6 microns per toy at $0.34 per micron Direct labor: 12 hours per toy at $710 per hour During July, the company produced 4,800 Maze toys. The toy's production data for the month are as follows: Direct materials: 74,000 microns were purchased at a cost of...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 8 microns per toy at $0.33 per micron Direct labor: 1.4 hours per toy at $7.10 per hour During July, the company produced 4,900 Maze toys. The toy's production data for the month are as follows: Direct materials: 79,000 microns were purchased at a cost of...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 6 microns per toy at $0.33 per micron Direct labor: 1.4 hours per toy at $7.30 per hour During July, the company produced 5,200 Maze toys. The toy's production data for the month are as follows: Direct materials: 76,000 microns were purchased at a cost of...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 7 microns per toy at $0.34 per micron Direct labor: 1.3 hours per toy at $7.50 per hour During July, the company produced 4,700 Maze toys. The toy's production data for the month are as follows: Direct materials: 72,000 microns were purchased at a cost of...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 7 microns per toy at $0.31 per micron Direct labor: 1.1 hours per toy at $6.80 per hour During July, the company produced 5,500 Maze toys. The toy's production data for the month are as follows: Direct materials: 77,000 microns were purchased at a cost of...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 8 microns per toy at $0.32 per micron Direct labor: 1.4 hours per toy at $7.10 per hour During July, the company produced 4,700 Maze toys. The toy's production data for the month are as follows: Direct materials: 73,000 microns were purchased at a cost of...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 7 microns per toy at $0.35 per micron Direct labor: 1.5 hours per toy at $7.10 per hour During July, the company produced 4,500 Maze toys. The toy's production data for the month are as follows: Direct materials: 70,000 microns were purchased at a cost of...