Solution a:
Compuation of NPV and Profitability index | ||||||
Particulars | Period | PV Factor | Option A | Option B | ||
Amount | Present value | Amount | Present value | |||
Cash Outflows: | ||||||
Initial Cost | 0 | 1 | $181,000 | $181,000 | $283,000 | $283,000 |
Annual cash outflows | 1-7 | 5.582381 | $30,200 | $168,588 | $25,100 | $140,118 |
Cost to rebuild | 4 | 0.792094 | $48,000 | $38,020 | $0 | $0 |
Present value of cash outflows (A) | $387,608 | $423,118 | ||||
Cash Inflows: | ||||||
Annual Cash Inflows | 1-7 | 5.582381 | $73,000 | $407,514 | $82,400 | $459,988 |
Salvage Value | 7 | 0.665057 | $0 | $0 | $8,300 | $5,520 |
Present Value of cash inflows (B) | $407,514 | $465,508 | ||||
NPV (B-A) | $19,905 | $42,390 | ||||
Profitability Index (PV of cash inflows / PV of cash outflows) | 1.05 | 1.10 |
To compute IRR let calculate NPV of option A at 9% and 10% discount rate. Further lets calculate NPV of option B at 10% and 11% discount rate. IRR is the rate at which NPV of project will be zero.
Compuation of NPV - Option A at 9% and 10% | ||||||
Particulars | Period | Amount | PV Factor at 9% | Present Value at 9% | PV Factor at 10% | Present Value at 10% |
Cash Outflows: | ||||||
Initial Cost | 0 | $181,000.00 | 1 | $181,000.00 | 1 | $181,000.00 |
Annual cash outflows | 1-7 | $30,200.00 | 5.032952835 | $151,995.18 | 4.868418818 | $147,026.25 |
Cost to rebuild | 4 | $48,000.00 | 0.708425211 | $34,004.41 | 0.683013455 | $32,784.65 |
Present value of cash outflows (A) | $366,999.59 | $360,810.89 | ||||
Cash Inflows: | ||||||
Annual Cash Inflows | 1-7 | $73,000.00 | 5.032952835 | $367,405.56 | 4.868418818 | $355,394.57 |
Salvage Value | 7 | $0.00 | 0.547034245 | $0.00 | 0.513158118 | $0.00 |
Present Value of cash inflows (B) | $367,405.56 | $355,394.57 | ||||
NPV (B-A) | $405.97 | -$5,416.32 | ||||
As we have to round IRR at zero decimal place, therefore IRR for option A is 9%, becuase at 10% NPV is negative.
Compuation of NPV - Option B at 10% and 11% | ||||||
Particulars | Period | Amount | PV Factor at 10% | Present Value at 10% | PV Factor at 11% | Present Value at 11% |
Cash Outflows: | ||||||
Initial Cost | 0 | $283,000.00 | 1 | $283,000.00 | 1 | $283,000.00 |
Annual cash outflows | 1-7 | $25,100.00 | 4.868418818 | $122,197.31 | 4.712196265 | $118,276.13 |
Cost to rebuild | 4 | $0.00 | 0.683013455 | $0.00 | 0.658730974 | $0.00 |
Present value of cash outflows (A) | $405,197.31 | $401,276.13 | ||||
Cash Inflows: | ||||||
Annual Cash Inflows | 1-7 | $82,400.00 | 4.868418818 | $401,157.71 | 4.712196265 | $388,284.97 |
Salvage Value | 7 | $8,300.00 | 0.513158118 | $4,259.21 | 0.481658411 | $3,997.76 |
Present Value of cash inflows (B) | $405,416.92 | $392,282.74 | ||||
NPV (B-A) | $219.61 | -$8,993.39 |
As we have to round IRR at zero decimal place, therefore IRR for option B is 10%, becuase at 11% NPV is negative.
Kimmel, Accounting, 6e Help I System Announcements CALCULATOR??pRINTER VERSIONI : 4EACK Brooks Clinic is considering investing...
Problem 25-03A Brooks Clinic is considering investing in new heart-monitoring equipment. It has two options. Option A would have an initial lower cost but would require a significant expenditure for rebuilding after 4 years. Option B would require no rebuilding expenditure, but its maintenance costs would be higher. Since the Option B machine is of initial higher quality, it is expected to have a salvage value at the end of its useful life. The following estimates were made of the...
Problem 25-03A Brooks Clinic is considering investing in new heart-monitoring equipment. It has two options. Option A would have an initial lower cost but would require a significant expenditure for rebuilding after 4 years. Option B would require no rebuilding expenditure, but its maintenance costs would be higher. Since the Option B machine is of initial higher quality, it is expected to have a salvage value at the end of its useful life. The following estimates were made of the...
Brooks Clinic is considering investing in new heart-monitoring equipment. It has two options. Option A would have an initial lower cost but would require a significant expenditure for rebuilding after 4 years. Option B would require no rebuilding expenditure, but its maintenance costs would be higher. Since the Option B machine is of initial higher quality, it is expected to have a salvage value at the end of its useful life. The following estimates were made of the cash flows....
Brooks Clinic is considering investing in new heart-monitoring equipment. It has two options. Option A would have an initial lower cost but would require a significant expenditure for rebuilding after 4 years. Option B would require no rebuilding expenditure, but its maintenance costs would be higher. Since the Option B machine is of initial higher quality, it is expected to have a salvage value at the end of its useful life. The following estimates were made of the cash flows....
Brooks Clinic is considering investing in new heart-monitoring equipment. It has two options. Option A would have an initial lower cost but would require a significant expenditure for rebuilding after 4 years. Option B would require no rebuilding expenditure, but its maintenance costs would be higher. Since the Option B machine is of initial higher quality, it is expected to have a salvage value at the end of its useful life. The following estimates were made of the cash flows....
Brooks Clinic is considering investing in new heart-monitoring equipment. It has two options. Option A would have an initial lower cost but would require a significant expenditure for rebuilding after 4 years. Option B would require no rebuilding expenditure, but its maintenance costs would be higher. Since the Option B machine is of initial higher quality, it is expected to have a salvage value at the end of its useful life. The following estimates were made of the cash flows....
Brooks Clinic is considering investing in new heart-monitoring equipment. It has two options. Option A would have an initial lower cost but would require a significant expenditure for rebuilding after 4 years. Option B would require no rebuilding expenditure, but its maintenance costs would be higher. Since the Option B machine is of initial higher quality, it is expected to have a salvage value at the end of its useful life. The following estimates were made of the cash flows....
Problem 25-03A Brooks Clinic is considering investing in new heart-monitoring equipment. It has two options. Option A would have an initial lower cost but would require a significant expenditure for rebuilding after 4 years. Option B would require no rebuilding expenditure, but its maintenance costs would be higher. Since the Option B machine is of initial higher quality, it is expected to have a salvage value at the end of its useful life. The following estimates were made of the...
Problem 25-03A Brooks Clinic is considering investing in new heart-monitoring equipment. It has two options. Option A would have an initial lower cost but would require a significant expenditure for rebuilding after 4 years. Option B would require no rebuilding expenditure, but its maintenance costs would be higher. Since the Option B machine is of initial higher quality, it is expected to have a salvage value at the end of its useful life. The following estimates were made of the...
Problem 25-03A a-b (Video) (Part Level Submission) Bonita Clinic is considering investing in new heart-monitoring equipment. It has two options. Option A would have an initial lower cost but would require a significant expenditure for rebuilding after 4 years. Option B would require no rebuilding expenditure, but its maintenance costs would be higher. Since the Option B machine is of initial higher quality, it is expected to have a salvage value at the end of its useful life. The following...