Question

Tej Dhakars company wants to establish kanbans to feed a newly established work cell. The following data have been provided.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Number of Kanbans = (Average Demand During Lead time + Safety Stock)/container size

Average Demand = 250

Production lead time = 1 day

Safety Stock = 0.5 day

Size = 50

Number of Kanbans = (250 + 0.5)/50

= 5.01 Containers.

Add a comment
Know the answer?
Add Answer to:
Tej Dhakar's company wants to establish kanbans to feed a newly established work cell. The following...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Maggie Moylan Motorcycle Corp. uses kanbans to support its transmission assembly line. Determine the size of...

    Maggie Moylan Motorcycle Corp. uses kanbans to support its transmission assembly line. Determine the size of the kanban for the mainshaft assembly and the number of kanbans needed. Setup cost $20 Annual holding cost $220 per mainshaft Daily production 320 mainshafts/day Annual usage 20,000 (50 weeks 5 days each x daily usage of 80 mainshafts) Lead time 4 days Safety stock 0.50 days' production Kanban container size = 60mainshafts (round your response to the nearest whole number). Number of kanbans...

  • Maggie Moylan Motorcycle Corp. uses kanbans to support its transmission assembly line. Determine the size of...

    Maggie Moylan Motorcycle Corp. uses kanbans to support its transmission assembly line. Determine the size of the kanban for the mainshaft assembly and the number of kanbans needed Setup cost Annual holding cost $400 per mainshaft $20 320 mainshafts/day Daily production Annual usage 20,000 (50 weeks x5 days each x daily usage of 80 mainshafts) 3 days Lead time 1.00 days' production Safety stock Kanban container size = 52 mainshafts (round your response to the nearest whole number) Number of...

  • Maggie Moylan Motorcycle Corp. uses kanbans to support its transmission assembly line. Determine the size of...

    Maggie Moylan Motorcycle Corp. uses kanbans to support its transmission assembly line. Determine the size of the kanban for the mainshaft assembly and the number of kanbans needed. Setup cost $20 Annual holding cost $200 per mainshaft Daily production 360 mainshafts/day Annual usage 25,000 (50 weeks x 5 days each x daily usage of 100 mainshafts) Lead time 3 days Safety stock 1.00 days' production Kanban container size = mainshafts (round your response to the nearest whole number).

  • Pauline Found Manufacturing, Inc., is moving to kanbans to support its telephone switching-board assembly lines. Determine...

    Pauline Found Manufacturing, Inc., is moving to kanbans to support its telephone switching-board assembly lines. Determine the size of the kanban for subassemblies and the number of kanbans needed Setup cost $30 Annual holding cost $125 per subassembly Daily production 40 subassemblies Annual usage 3,000 (50 weeks 5 days each x daily usage of 12 subassemblies) Lead time 14 days Safety stock 4 days' production Kanban container size units (round your response to the nearest whole number).

  • Pauline Found Manufacturing, Inc., is moving to kanbans to support its telephone swilching-board assembly lines. Determine...

    Pauline Found Manufacturing, Inc., is moving to kanbans to support its telephone swilching-board assembly lines. Determine the size of the kanban for subassemblie and the number of kanbans needed. Setup cost$30 Annual holding cost $125 per subassembly Daily production 20 subassemblies Annual usage 4,500 (50 weeks x 5 days each x daily usage of 18 subassemblies) 16 days Lead time Safety stock2 days' production Kanban container size # | | units (round your response to the nearest whole number).

  • Pauline Found Manufacturing, Inc., is moving to kanbans to support its telephone switching-board assembly lines. Determine...

    Pauline Found Manufacturing, Inc., is moving to kanbans to support its telephone switching-board assembly lines. Determine the size of the kanban for subassemblies and the number of kanbans needed. Setup cost $30 Annual holding cost $120 per subassembly Daily production 30 subassemblies Annual usage 4,000 (50 weeks x 5 days each x daily usage of 16 subassemblies) Lead time 10 days Safety stock 2 days' production Kanban container size = units (round your response to the nearest whole number).

  • Pauline Found Manufacturing, Inc., is moving to kanbans to support its telephone switching-board assembly lines. Determine...

    Pauline Found Manufacturing, Inc., is moving to kanbans to support its telephone switching-board assembly lines. Determine the size of the kanban for suba and the number of kanbans needed. Setup cost $30 Annual holding cost $100 per subassembly Daily production 20 subassemblies Annual usage 2,500 (50 weeks 5 days each x daily usage of 10 subassemblies) Lead time 10 days Safety stock 4 days' production Kanban container size = units (round your response to the nearest whole number).

  • Kanban container size = 63 units (round your response to the nearest whole number). Number of...

    Kanban container size = 63 units (round your response to the nearest whole number). Number of kanbans needed = kanbans (round your response to the nearest whole number). Pauline Found Manufacturing, Inc., is moving to kanbans to support its telephone switching-board assembly lines. Determine the size of the kanban for subassemblies and the number of kanbans needed. Setup cost $30 Annual holding cost $120 per subassembly Daily production 30 subassemblies Annual usage 4,000 (50 weeks 5 days each x daily...

  • Perkins Lighting wishes to employ a kanban in their new floor lamp production system. They will...

    Perkins Lighting wishes to employ a kanban in their new floor lamp production system. They will create production orders in the size of the kanban. For the floor lamp base, they have provided the following information: Daily demand 500 units Holding cost $15/unit/year Order cost $100/order Lead time 3 days Safety stock 500 units Find the size of the kanban and the number of kanbans required. Perkins believes in minimizing the total of the their ordering and holding costs.

  • Hartley Bectronics, Inc., in Nashville produces short runs of custom airwave scanners for the defense industry....

    Hartley Bectronics, Inc., in Nashville produces short runs of custom airwave scanners for the defense industry. You have been asked by the owner, Janet Hartley, to reduce inventory by introducing a kanban system. Aher several hours of analysis, you develop the following data for scanner connectors used in one work col. How many kanbans do you need for this connector? Daily demand 1,400 connectors Lead time 3 days Safety stock 150 days Kanban size 500 connectors Number of karbans-kanbare found...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT