Select all false statements.
A. One way that project management differs from management of more traditional activities is the limited scale of activities.
B. A Gantt chart is used to display precedence relationships.
C. PERT and CPM are nearly identical in terms of analysis and procedures.
D. The main function of dummy activities is to clarify relationships in network diagrams.
E. The total cost of crashing any one activity should never exceed 50 percent of the total cost of the original project
F. A disadvantage of AOA diagrams is the occasional need for dummy activities.
B. A Gantt chart is used to display precedence relationships. FALSE Gantt charts cannot show sequential relationships.
F. A disadvantage of AOA diagrams is the occasional need for dummy activities.
Select all false statements. A. One way that project management differs from management of more traditional...
question 3.12 Chapter 3 Project Management 91 Table for 3.8 Time Activity Immediate Code Description in hours) Predecesur Planning Find location determine resource requirements Purchasing Requisition of lumber and sand Excavation Planning Dig and grade Sawing Planning Saw lumber inte appropriate sizes Placement Purchasing Position lumber in comect locations Sawing. c om Assembly Nail lamber together Placement Tafill Put sand in and under the equipment Ambly Outfill Put dirt a nd the equipment Assembly Decoration Put grass all over the...