Question 16 Let xy be 1 if the project is done an d zero otherwise. What constraint prevents two projects 1 and 2 from being
0 0
Add a comment Improve this question Transcribed image text
Answer #1

x1 + x2 <= 1

If both the projects are done it will be equal to 1 or otherwise it would be equal to 0 hence this formulation will prove the condition to be 1 or 0 depending upon the status of the project.

Add a comment
Know the answer?
Add Answer to:
Question 16 Let xy be 1 if the project is done an d zero otherwise. What...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT