Question
Will someone help with this? I also need to show all work
Use the following to answer question 5: Wilson Co. purchased land as a factory site for $900,000. Wilson paid $80,000 to tear
0 0
Add a comment Improve this question Transcribed image text
Answer #1
5)
The cost of the land that should be recorded by Wilson Co. is
Purchased cost of Land $ 9,00,000.00
Add: Tear Down $    80,000.00
Less: Salvage $    -5,400.00
Legal Fees $      3,480.00
Title Insurance $      2,400.00
Assessment for pavement: $      6,400.00
Total Cost of Land $ 9,86,880.00
6) Henry Company purchased a depreciable asset for $240,000. The estimated salvage value is $22,000, and the estimated useful life is 10 years. The straight-line method will be used for depreciation. What is the depreciation base of this asset?
Depreciation = Cost - SV/Useful life
Depreciation = (240000-22000)/10 $    21,800.00
7) Slotkin Products purchased a machine for $39,000 on July 1, 2014. The company intends to depreciate it over 8 years using the double-declining balance method. Salvage value is $3,000. Depreciation for 2014 to the closest dollar is
Straightline Dep. Rate = 1/8 12.50%
Double declineing rate = 2 x 12.50% 25%
Depreciation = 39000 x 25% x 6/12 months $      4,875.00
8) Klayton Corporation purchased factory equipment that was installed and put into service January 2, 2014, at a total cost of $120,000. Salvage value was estimated at $8,000. The equipment is being depreciated over four years using the double-declining balance method. For the year 2015, Klayton should record depreciation expense on this equipment of
Straightline Dep. Rate = 1/4 25.00%
Double declineing rate = 2 x 25% 50%
Depreciation 2014 = 120000 x 50% $    60,000.00
Depreciation 2015 = (120000 -60000) x 50% $    30,000.00
Add a comment
Know the answer?
Add Answer to:
Will someone help with this? I also need to show all work Use the following to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Wilson Co. purchased land as a factory site for $1,350,000. Wilson paid $120,000 to tear down...

    Wilson Co. purchased land as a factory site for $1,350,000. Wilson paid $120,000 to tear down two buildings on the land. Salvage was sold for $8,100. Legal fees of $5,220 were paid for title investigation and making the purchase. Architect's fees were $46,800. Title insurance cost $3,600, and liability insurance during construction cost $3,900. Excavation cost $15,660. The contractor was paid $4,200,000. An assessment made by the city for pavement was $9,600. Interest costs during construction were $255,000. The cost...

  • please show solution Wilson Co. purchased land as a factory site for $1,350,000. Wilson paid $120,000...

    please show solution Wilson Co. purchased land as a factory site for $1,350,000. Wilson paid $120,000 to tear down two buildings on the land. Salvage was sold for $8,100. Legal fees of $5,220 were paid for title investigation and making the purchase. Architect's fees were $46,800. Title insurance cost $3,600, and liability insurance during construction cost $3,900 Excavation cost $15,660. The contractor was paid $4,200,000. An assessment made by the city for pavement was $9,600 Interest costs during construction were...

  • Crane Company purchased land as a factory site for $1315000. Crane paid $118000 to tear down...

    Crane Company purchased land as a factory site for $1315000. Crane paid $118000 to tear down two buildings on the land. Salvage was sold for $8400. Legal fees of $5380 were paid for title investigation and making the purchase. Architect's fees were $46100. Title insurance cost $3900, and liability insurance during construction cost $4200. Excavation cost $15540. The contractor was paid $4400000. An assessment made by the city for pavement was $9700. Interest costs during construction were $260000. The cost...

  • Use the following information for questions 2, 3, and 4. Automated Audit Company Co. (AACC) purchased...

    Use the following information for questions 2, 3, and 4. Automated Audit Company Co. (AACC) purchased land as a factory site for $1,700,000. AACC paid $250,000 to tear down two buildings on the land. Salvage was sold for $3,800. Legal fees of $150,550 were paid for title investigation and making the purchase. An assessment made by the city for underground water and sewage systems was made for $135,000. Architect's fees for the building were $25,800. The contractor was paid a...

  • Sparky, Co. purchased land as a factory site for $600,000. Sparky paid $42,000 to tear down...

    Sparky, Co. purchased land as a factory site for $600,000. Sparky paid $42,000 to tear down an existing structure on the land and was able to salvage some of the building materials which were sold for $15,400. Legal fees of $5,880 were paid for title insurance on the land purchase. Architect's fees were $32,200. There was an assessment by the city for a drainage project that cost $6,400 that was necessary to keep the land from retaining water during the...

  • Capitalizing Interest A) On April 1, PC Co. began construction of a small building. Payments of...

    Capitalizing Interest A) On April 1, PC Co. began construction of a small building. Payments of $250,640 were made monthly for four months beginning on April 1. The building was completed and ready for occupancy on August 1. For the purpose of determining the amount of interest cost to be capitalized, calculate the weighted-average accumulated expenditures on the building. B) OO Company purchased land as a factory site for $1340000. They paid $115000 to tear down two buildings on the...

  • Part II (01m Section A: Cost of Land and Building y purchased land as a factory...

    Part II (01m Section A: Cost of Land and Building y purchased land as a factory site for $900,000. Rams Company paid $80,000 to wo buildings on the land. Salvage was sold for $5,400. Legal fees of $3,500 were title investigation and making the purchase. Architect's fees were $31,200. Title e cost $2,400, and liability insurance during construction cost $2,600. Excavation cost S10 500. The contractor was paid $2,000,000. Interest costs capitalized during construction were $17,000. 1. The cost of...

  • 1,050,000 2,100,000 66 6796 Net purchases Net sales Percentage markup on cost A fire destroyed Barton's October 31 inventory, leaving undamaged inventory with a cost of $21,000. Using the gro...

    1,050,000 2,100,000 66 6796 Net purchases Net sales Percentage markup on cost A fire destroyed Barton's October 31 inventory, leaving undamaged inventory with a cost of $21,000. Using the gross profit method, the estimated ending inventory destroyed by fire is a. $119,000 b. $539,000. c. $560,000. d. $700,000. 15. Dicer uses the conventional retail method (the preferred approach) to determine its ending inventory at cost. Assume the beginning inventory at cost (retail) were $390,000 ($594,000), purchases during the current year...

  • need help with problems 9-1b and 9-2b Chapter 9 Problems: Set B P9-18 Russo Company organized on January 1. During the first year of Determine acquisition operations, the following plant asset ex...

    need help with problems 9-1b and 9-2b Chapter 9 Problems: Set B P9-18 Russo Company organized on January 1. During the first year of Determine acquisition operations, the following plant asset expenditures and receipts were recorded in costs of land and random order building Debit Accrued real estate taxes paid at time of purchase of real estate 2. Real estate taxes on land paid for the current year 3. Full payment to building contractor 4. Excavation costs for new building...

  • The plant asset and accumulated depreciation accounts of Pell Corporation had the following balances at December...

    The plant asset and accumulated depreciation accounts of Pell Corporation had the following balances at December 31, 2012: Plant Asset Accumulated Depreciation   Land $ 350,000 $ 0   Land improvements 180,000 45,000   Building 1,500,000 350,000   Machinery and equipment 1,158,000 405,000   Automobiles 150,000 112,000 Transactions during 2013 were as follows: a. On January 2, 2013, machinery and equipment were purchased at a total invoice cost of $260,000, which included a $5,500 charge for freight. Installation costs of $27,000 were incurred. b. On...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT