Neptune Inc. uses a standard cost system and has the following information for the most recent month, April:
Actual direct labor hours (DLHs) worked | 24,000 | ||
Standard DLHs allowed for good output produced this period | 25,000 | ||
Actual total factory overhead costs incurred | $ | 55,000 | |
Budgeted fixed factory overhead costs | $ | 10,700 | |
Denominator activity level, in direct labor hours (DLHs) | 17,000 | ||
Total factory overhead application rate per standard DLH | $ | 2.70 | |
The total underapplied or overapplied factory overhead in April for Neptune, Inc., to the nearest whole dollar, was:
Multiple Choice
$11,200 underapplied.
$11,200 overapplied.
$12,500 underapplied.
$12,500 overapplied.
$14,400 overapplied.
We need at least 10 more requests to produce the answer.
0 / 10 have requested this problem solution
The more requests, the faster the answer.
Neptune Inc. uses a standard cost system and has the following information for the most recent...
Neptune Inc. uses a standard cost system and has the following information for the most recent month, April: Actual direct labor hours (DLHs) worked 14,000 Standard DLHs allowed for good output produced this period 19,000 Actual total factory overhead costs incurred $ 38,400 Budgeted fixed factory overhead costs $ 10,300 Denominator activity level, in direct labor hours (DLHs) 13,000 Total factory overhead application rate per standard DLH $ 2.70 The fixed overhead production volume variance in April for Neptune, Inc.,...
The Chuba Corporation uses a standard cost system in which manufacturing overhead is applied on the basis of standard direct labor-hours (DLHs). During December, the company actually used 7,200 direct labor-hours and made 1,900 units of finished product. The standard cost card for one unit of product includes the following data concerning manufacturing overhead: Variable overhead: 4 DLHs @ $5.25 per DLH Fixed overhead: 4 DLHs @ $2.00 per DLH For December, the company incurred $16,550 in fixed manufacturing overhead...
The following information is available from the Terry Company: Actual total factory overhead cost incurred $ 37,000 Actual fixed overhead cost incurred $ 11,200 Budgeted fixed overhead expenses $ 21,000 Actual direct labor hours (DLH) worked 5,300 Standard DLHs for this period’s production (output) 4,800 Standard variable overhead rate per DLH $ 3.00 Standard fixed overhead rate per DLH $ 2.50 What is the total overhead spending variance for Terry Company for the period, to the nearest whole dollar? $100...
Prepare a standard cost card for the company's product. (Round your answer Lane Company manufactures a single product that requires a great deal of hand labor. Overhead cost is applied on the basis of standard direct labor-hours. The budgeted variable manufacturing overhead is $5.00 per direct labor-hour and the budgeted fixed manufacturing overhead is $2.295.000 per year. The standard quantity of materials is 4 pounds per unit and the standard cost is $10.50 per pound. The standard direct labor-hours per...
Lane Company manufactures a single product that requires a great deal of hand labor. Overhead cost is applied on the basis of standard direct labor-hours. The budgeted variable manufacturing overhead is $5.80 per direct labor-hour and the budgeted fixed manufacturing overhead is $3,087,000 per year. The standard quantity of materials is 4 pounds per unit and the standard cost is $12.50 per pound. The standard direct labor-hours per unit is 1.5 hours and the standard labor rate is $13.90 per...
Lane Company manufactures a single product that requires a great deal of hand labor. Overhead cost is applied on the basis of standard direct labor-hours. The budgeted variable manufacturing overhead is $5.60 per direct labor-hour and the budgeted fixed manufacturing overhead is $2,880,000 per year. The standard quantity of materials is 4 pounds per unit and the standard cost is $12.00 per pound. The standard direct labor-hours per unit is 1.5 hours and the standard labor rate is $13.80 per...
Lane Company manufactures a single product that requires a great deal of hand labor. Overhead cost is applied on the basis of standard direct labor-hours. The budgeted variable manufacturing overhead is $5.00 per direct labor-hour and the budgeted fixed manufacturing overhead is $2,295,000 per year. The standard quantity of materials is 4 pounds per unit and the standard cost is $10.50 per pound. The standard direct labor-hours per unit is 1.5 hours and the standard labor rate is $13.50 per...
A manufacturing company has a standard costing system based on standard direct labor-hours (DLHs) as the measure of activity. Data from the company's flexible budget for manufacturing overhead are given below: A manufacturing company has a standard costing system based on standard direct labor-hours (DLHS) as the measure of activity. Data from the company's flexible budget for manufacturing overhead are given below: 6,800 DLHS Denominator level of activity Overhead costs at the denominator activity level: Variable overhead cost Fixed overhead...
Lane Company manufactures a single product that requires a great deal of hand labor. Overhead cost is applied on the basis of standard direct labor-hours. The budgeted variable manufacturing overhead is $3.40 per direct labor-hour and the budgeted fixed manufacturing overhead is $999,000 per year. The standard quantity of materials is 4 pounds per unit and the standard cost is $6.50 per pound. The standard direct labor-hours per unit is 1.5 hours and the standard labor rate is $12.70 per...
Lane Company manufactures a single product that requires a great deal of hand labor. Overhead cost is applied on the basis of standard direct labor-hours. The budgeted variable manufacturing overhead is $4.40 per direct labor-hour and the budgeted fixed manufacturing overhead is $1,764,000 per year. The standard quantity of materials is 4 pounds per unit and the standard cost is $9.00 per pound. The standard direct labor-hours per unit is 1.5 hours and the standard labor rate is $13.20 per...