Question

Valentine Accessories Plus produces brass handles for the furniture industry in a four -stage process-mixing, moulding,...

Valentine Accessories Plus produces brass handles for the furniture industry in a four -stage process-mixing, moulding, Polishing and Packaging.Costs incurred in the polishing department during January are summarized as follows:

                  DR                                                WIP-Polishing Process A/C                                              CR

Particulars

units

$

Particulars

Units

$

January 1 Bal

0

Transfer from moulding

20000

1310000

Direct Material Added

391600

Direct Labour

638000

Manufacturing Overhead

307400

Normal Losses are estimated to be 2 ½% of input during the period. Inspection takes place during the processing operation, at which point damaged handles are separated from goods handles and sold as scrap to local furniture manufactures at $85 each.

At inspection,2000 handles were rejected as scrap. These units had reached the following degree of completion:

Transfer from moulding 100%

Direct Material added    40%

Conversion costs             20%

Work-in-progress at the end of January was 4000 handles and had reached the following degree of completion:

Transfer from moulding 100%

Direct material added     80%

Conversion Costs              50%

Direct Materials added and Conversion costs are incurred uniformly throughout the process.

Required:

  1. Compute the equivalent units and cost per equivalent units for direct materials( from moulding & Direct Materials added) and conversion costs.
  1. Compute the:( I) Cost of the unexpected losses (II) Total cost of the handles completed and transferred out of the packaging department .(III)Cost of ending work in process inventory in the polishing Department.

  1. Complete the work in process inventory -polishing process T account, clearly showing the ending balance.

  1. Prepare the Journal entries for the:(I)Assignment of direct materials, direct labour incurred and the manufacturing overhead applied to polishing process.(II)cost of the units completed and transferred out to the packaging process.

  1. Given that 30% of the unexpected Losses were as a result of Pilferage, Calculate Valentine Accessories true loss for the polishing Department.

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Statement of Equivalent Units
Degree of completion
Direct Material Direct Labor Manufacturing O/H
Particulars Units Particulars Units % Units % Units % Units
Transferred units 20000 Normal Loss 500 - - - - - -
Abnormal Loss 2000 100% 2000 40% 800 20% 400
Transferred to 13500 100% 13500 100% 13500 100% 13500
next process (F.G)
Closing WIP 4000 100% 4000 80% 3200 50% 2000
20000 20000 19500 17500 15900

Notes: 1) Degree of completion of Normal loss is always taken as NIL

2) It is assumed that 100% of input has been utilized in Abnormal Loss, Finished goods transferred to next process and Closing WIP   

Cost per equivalent units
Element of cost Cost Units Cost per equivalent units
Input 1310000 19500 67.17949
Direct Material 349100 19500 17.90256
Direct Labor 638000 17500 36.45714
Manu. O/H 307400 15900 19.33333
Total 140.8725

Note: Cost of Direct Material = $ 391,600 - ( 500 units * $ 85)

= $ 349100

Statement of revaluation
Cost of Abnormal Loss
Elements Units Cost Per Unit Amount
Input 2000 67.17948718 134359
Materials 2000 17.9025641 35805.13
Labor 800 36.45714286 29165.71
O/H 400 19.33333333 7733.333
Total 207063.2
Cost of Finished Goods transferred
13500 units * $ 140.8725 = 1901779
Cost of Closing WIP
Elements Units Cost Per Unit Amount
Input 4000 67.17948718 268717.9
Materials 4000 17.9025641 71610.26
Labor 3200 36.45714286 116662.9
O/H 2000 19.33333333 38666.67
Total 495657.7
WIP- Polishing Process A/c
Particulars Units Rate Amount Particulars Units Rate Amount
Transfer from 20000 65.5 1310000 Normal Loss 500 85 42500
moulding
Abnormal Loss 2000 103.53158 207063
Direct Materials 391600
Finisehd goods 13500 140.87253 1901779
Direct labour 638000 transferred
Manu. OH 307400 Closing WIP 4000 123.91443 495658
20000 2647000 20000 2647000
Add a comment
Know the answer?
Add Answer to:
Valentine Accessories Plus produces brass handles for the furniture industry in a four -stage process-mixing, moulding,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Wilkman uses three departments to produce plastic handles for screwdrivers: Mixing, Moulding, and Drying. The Assembly...

    Wilkman uses three departments to produce plastic handles for screwdrivers: Mixing, Moulding, and Drying. The Assembly Department attaches the screwdriver shanks to the handles. Wilkman's Drying Department requires no direct materials. Conversion costs are incurred evenly throughout the drying process. Other process costing information follows: 3: (Click the icon to view the information.) After the drying process, the screwdrivers are completed by assembling the handles and shanks and packaging for shipment to retail outlets. Requirements i Data Table Start Complete...

  • requirement 1 pls Tradition uses three departments to produce plastic handles for ser v ers Mixing,...

    requirement 1 pls Tradition uses three departments to produce plastic handles for ser v ers Mixing, Moulding, and Drying The Assembly Department attaches the screwdriver shanks to the handles Tradition's Drying Department requires no direct materials. Conversion costs are incurred overly throughout the drying process. Other process costing information follows: (Click the loon to view the Information) After the drying process, the screwdrivers are completed by assembling the handles and sharks and packaging for shipment to retail outlets Requirements Requirement...

  • Question 2    Kasten Company manufactures bowling balls through two processes: moulding and packaging. In the moulding...

    Question 2    Kasten Company manufactures bowling balls through two processes: moulding and packaging. In the moulding department, urethane, rubber, plastic, and other materials are moulded into bowling balls. In the packaging department, the balls are placed in cartons and sent to the finished goods warehouse. All materials are entered at the beginning of each process.    Labour and manufacturing overhead are incurred uniformly throughout each process. Production and cost data for the moulding department during June 2020 are presented below: Question...

  • Agro Business operates several production processes including the production of bulk animal feed for cattle. One...

    Agro Business operates several production processes including the production of bulk animal feed for cattle. One such product is produced in three separate process operations – Testing, Mixing & Packaging. The information below is of the costs incurred in, and output from the Mixing Process during the period just completed. (i) Input from Testing: 120,000 kilos valued at an average cost of $24.05 per kilo (ii) Other manufacturing costs incurred during the period: Direct material added $790,500 Direct labour $380,400...

  • Agro Business operates several production processes including the production of bulk animal feed for cattle. One...

    Agro Business operates several production processes including the production of bulk animal feed for cattle. One such product is produced in three separate process operations- Testing, Mixing & Packaging. The information below is of the costs incurred in, and output from the Mixing Process during the period just completed. (11) Input from Testing: 120,000 kilos valued at an average cost of $24.05 per kilo Other manufacturing costs incurred during the period: Direct material added $790,500 Direct labour $380,400 Manufacturing overhead...

  • Agro Business operates several production processes including the production of bulk animal feed for cattle. One such pr...

    Agro Business operates several production processes including the production of bulk animal feed for cattle. One such product is produced in three separate process operations – Testing, Mixing & Packaging. The information below is of the costs incurred in, and output from the Mixing Process during the period just completed. (i) Input from Testing: 120,000 kilos valued at an average cost of $24.05 per kilo (ii) Other manufacturing costs incurred during the period: Direct material added Direct labour Manufacturing overhead...

  • need help with this please Discussion Question_Process Costing to Discussion Question Agro Business operates several production...

    need help with this please Discussion Question_Process Costing to Discussion Question Agro Business operates several production processes including the production of bulk animal feed for cattle. One such product is produced in three separate process operations- Testing, Mixing & Packaging. The information below is of the costs incurred in and output from the Mixing Process during the period just completed. (1) (ii) Input from Testing: 120,000 kilos valued at an average cost of $24.05 per kilo Other manufacturing costs incurred...

  • Question 4 Kasten Company manufactures bowling balls through two processes: moulding and packaging. In the moulding...

    Question 4 Kasten Company manufactures bowling balls through two processes: moulding and packaging. In the moulding department, urethane, rubber, plastic, and other materials are moulded into bowling balls. In the packaging department, the balls are placed in cartons and sent to the finished goods warehouse. All materials are entered at the beginning of each process. Labour and manufacturing overhead are incurred uniformly throughout each process. Production and cost data for the moulding department during June 2020 are presented below: June...

  • Wilkin Products Ltd. makes a single product using two processes. Quality control check takes place during...

    Wilkin Products Ltd. makes a single product using two processes. Quality control check takes place during the process, at which point, rejected units are separated from good units. The following details relate to production for the month of April 20X7, for Process 2. (i) Work-in-process, beginning inventory: -0- (ii) Transfer from Process 1: 15,000 units valued at $51.40 each (iii) Other manufacturing costs incurred during April: Direct material added $513,000 Direct labour   $365,000 Manufacturing overhead   $211,000 (iv) Normal losses were...

  • Need all of requirements 1,2,3 please. thanks. Tradition uses three departments to produce plastic handles for...

    Need all of requirements 1,2,3 please. thanks. Tradition uses three departments to produce plastic handles for ser v ers Mixing, Moulding, and Drying The Assembly Department attaches the screwdriver shanks to the handles Tradition's Drying Department requires no direct materials. Conversion costs are incurred every throughout the drying process. Other process costing information follows: (Click the loon to view the Information) After the drying process, the screwdrivers are completed by assembling the handles and sharks and packaging for shipment to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT