Answer-52)-Tool Time’s total labor variance =$160 F.

53)-Tool Time’s labor price variance =$280 F.

54)-Tool Time’s labor quantity variance = $120 U.

Explanation-Total direct labor cost variance = Standard cost- actual cost

= (690 hours*$12 per hour)- $8120

= $8280-$8120

= $160 Favorable

Direct Labor price variance = (Standard rate – Actual rate) * Actual hours

= {$12 per hour – ($8120/700 hours)}* 700 hours   

= ($12 per hour – $11.60 per hour)* 700 hours   

= $280 Favorable

Direct Labor Quantity variance=(Standard hours-Actual hours)*Standard rate per hour

=(690 hours – 700 hours)*$12 per hour

= $120 Unfavorable

Where-Standard Hours = No. of hours per unit*Actual output

= 3 hours per unit *230 units

= 690 hours

Add a comment
Know the answer?
Add Answer to:
need asap Use the following information for questions 52 - 54 ToolTime has a standard of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Use the following information to answer the next six questions. Kartman Corporation makes a product with...

    Use the following information to answer the next six questions. Kartman Corporation makes a product with the following standard costs: Standard Quantity Standard Cost or Hours Standard Price or Rate Per Unit Direct materials 6.5 pounds $ 7.00 per pound $ 45.50 Direct labor 0.6 hours $ 24.00 per hour $ 14.40 Variable overhead 0.6 hours $ 4.00 per hour $ 2.40 In June the company's budgeted production was 3.400 units but the actual production was 3,500 units. The company...

  • Use the following information to answer the next six questions, Kartman Corporation makes a product with...

    Use the following information to answer the next six questions, Kartman Corporation makes a product with the following standard costs Direct materials Direct labor Variable overhead Standard Quantity or Hours 6.5 pounds 0.6 hours 0.6 hours Standard Cost Standard Price or Rate Per Unit $ 7.00 per pound $ 45.50 $24.00 per hour $ 14.40 $ 4.00 per hour S 2.40 In June the company's budgeted production was 3.400 units but the actual production was 3,500 s of the direct...

  • Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity...

    Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Tyler Company for September: Standard cost per unit 4 units of material A x $2.00 per unit Direct materials 1 unit of material B x $3.000 per unit 3 hours x $8.00 per hour Direct labor Activity for September Materials purchased Material A 3,400 units x $2.05 per unit 800 units x $3.10 per unit Material B Materials used Material A 3,050 units...

  • Exercise 24-07 (Video) Levine Inc., which produces a single product, has prepared the following standard cost...

    Exercise 24-07 (Video) Levine Inc., which produces a single product, has prepared the following standard cost sheet for one unit of the product. $20 Direct materials (8 pounds at $2.50 per pound) Direct labor (3 hours at $12.00 per hour) $36 During the month of April, the company manufactures 230 units and incurs the following actual costs. Direct materials purchased and used (1,900 pounds) Direct labor (700 hours) $5,035 $8,120 Compute the total, price, and quantity variances for materials and...

  • Use the following information to answer Questions 1 through 4. Skokie Company produces aquariums. During the...

    Use the following information to answer Questions 1 through 4. Skokie Company produces aquariums. During the year 150,000 aquariums were produced. Direct materials and direct labor standards for producing the aquariums are as follows. SKOKIE COMPANY DIRECT MATERIALS AND DIRECT LABOR STANDARDS FOR PRODUCTION OF AQUARIUMS Direct materials (2 sheets of glass at $2.00 per sheet) S 4.00 Direct labor (3 hours at $8.00 per hour) 24.00 Skokie purchased and used 310,000 sheets of glass at $1.50 each and its...

  • Sharp Company manufactures a product for which the following standards have been set: Standard Quantity or...

    Sharp Company manufactures a product for which the following standards have been set: Standard Quantity or Hours 3 feet ? hours Direct materials Direct labor Standard Price or Rate $5 per foot ? per hour Standard Cost $ 15 ? During March, the company purchased direct materials at a cost of $42,660, all of which were used in the production of 2,250 units of product. In addition, 4,600 direct labor-hours were worked on the product during the month. The cost...

  • 3) (Information for problems 3 through 8): Bulluck Corporation makes a product with the following standard...

    3) (Information for problems 3 through 8): Bulluck Corporation makes a product with the following standard costs: Direct materials Direct labor Variable overhead Standard Quantity or Hours 3.5 grams 0.7 hours hours Standard Price or Rate 1.00 per gram 11.00 per hour 2.00 per hour 0.7 The company reported the following results concerning this product in July. units Actual output Raw materials used in production Actual direct labor-hours Purchases of raw materials Actual price of raw materials purchased Actual direct...

  • Pippin Inc. has provided the following data concerning one of the products in its standard cost...

    Pippin Inc. has provided the following data concerning one of the products in its standard cost system. Variable manufacturing overhead is applied to basis of direct labor-hours. Standard Quantity or Hours per Standard Price or Inputs Direct materials Direct labor Variable manufacturing overhead Unit of Output 5.0 grams 0.30 hours 0.30 hours Rate $ 7.00 per gram S 21.30 per hour S 9.60 per hour The company has reported the following actual results for the product for June Actual output...

  • Use the following information to answer Questions 9 through 13. Urbana Company calculates its predetermined manufacturing...

    Use the following information to answer Questions 9 through 13. Urbana Company calculates its predetermined manufacturing overhead rates using normal capacity, which is 288,000 units. The standard cost system allows 2 direct labor hours per unit produced. Manufacturing overhead is applied using direct labor hours. The total budgeted manufacturing overhead is $3,168,000, of which $864,000 is fixed manufacturing overhead. The actual results for the year are as follows. URBANA COMPANY ACTUAL RESULTS FOR PRODUCTION FOR CURRENT YEAR 280,000 Units produced...

  • Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity...

    Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Tyler Company for September: Standard cost per unit Direct materials 4 units of material A x $2.00 unit per 1 unit of material B x $3.00 per unit Direct labor 3 hours x $8.00 per hour Activity for September Materials purchased Material A 4,100 units x $2.05 per unit Material B 1,000 units x $3.10 per unit Materials used Material A 3,750 units...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT