Question

Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Tyler
0 0
Add a comment Improve this question Transcribed image text
Answer #1

ANSWER

  • All working forms part of the answer
  • Requirement ‘a’

---Material ‘A’ Variances:

Material Price Variance

(

Standard Rate

-

Actual Rate

)

x

Actual Quantity used

(

$                        2.00

-

$                       2.05

)

x

3750

-187.5

Variance

$                  187.50 [Comment if this answer is NOT correct and I’ll help you out, as this variance is calculated on quantity used NOT on quantity purchased]

Unfavourable-U

Material Quantity Variance

(

Standard Quantity = 900 units x 4 units of A

-

Actual Quantity used

)

x

Standard Rate

(

3600

-

3750

)

x

$                           2.00

-300

Variance

$                  300.00

Unfavourable-U

---Material ‘B’ Variances

Material Price Variance

(

Standard Rate

-

Actual Rate

)

x

Actual Quantity

(

$                        3.00

-

$                       3.10

)

x

905

-90.5

Variance

$                    90.50 [Comment if this answer is NOT correct and I’ll help you out, as this variance is calculated on quantity used NOT on quantity purchased]

Unfavourable-U

Material Quantity Variance

(

Standard Quantity [900 units x 1 unit of B]

-

Actual Quantity used

)

x

Standard Rate

(

900

-

905

)

x

$                           3.00

-15

Variance

$                    15.00

Unfavourable-U

  • Requirement ‘b’

Labor Rate Variance

(

Standard Rate

-

Actual Rate

)

x

Actual Labor Hours

(

$                        8.00

-

$                       8.10

)

x

2690

-269

Variance

$                  269.00

Unfavourable-U

Labour Efficiency Variance

(

Standard Hours

-

Actual Hours

)

x

Standard Rate

(

2700

-

2690

)

x

$                           8.00

80

Variance

$                    80.00

Favourable-

_____________________________________________

If you have any query or any Explanation please ask me in the comment box, i am here to helps you.please give me positive rating.

*****************THANK YOU**************

Add a comment
Know the answer?
Add Answer to:
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity...

    Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Tyler Company for September: Standard cost per unit 4 units of material A x $2.00 per unit Direct materials 1 unit of material B x $3.000 per unit 3 hours x $8.00 per hour Direct labor Activity for September Materials purchased Material A 3,400 units x $2.05 per unit 800 units x $3.10 per unit Material B Materials used Material A 3,050 units...

  • Please show all work to get to answers. Computation of Variable Cost Variances The following information pertains to th...

    Please show all work to get to answers. Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Tyler Company for September: Standard cost per unit Direct materials 4 units of material A $2.00 per unit 1 unit of material B x $3.00 per unit 3 hours x $8.00 per hour Direct labor Activity for September Materials purchased Material A Material B Materials used Material A 4,100 units x $2.05 per unit 1,000...

  • Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity...

    Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Tyler Company for September: Standard cost per unit Direct materials 4 units of material A × $2.00 per unit 1 unit of material B × $3.00 per unit Direct labor 3 hours × $8.00 per hour Activity for September Materials purchased Material A 3,400 units × $2.05 per unit Material B 800 units × $3.10 per unit Materials used Material A 3,050 units...

  • The following information pertains to the standard costs and actual activity for Tyler Company for September:...

    The following information pertains to the standard costs and actual activity for Tyler Company for September: Standard cost per unit Direct materials 4 units of material A x $ 3.00 per unit 1 unit of material B x $ 4.00 per unit Direct labor 3 hours x $ 9.00 per hour Activity for September Materials purchased Material A 4,500 units x $ 3.10 per unit Material B 1,100 units x $ 4.15 per unit Materials used Material A 4,150 units...

  • The following information pertains to the standard costs and actual activity for Repine company for September Stand...

    The following information pertains to the standard costs and actual activity for Repine company for September Standard cost per unit Direct materials 4 units of material A x $ 6.00 per unit 1 unit of material B x $ 8.00 per unit 3 hours x $ 18.00 per hour 6,750 units x $ 6.20 per unit 1,650 units x $ 8.50 per unit Direct labor Activity for September Materials purchased Material A Material B Materials used Material A Material B...

  • Question 13 Partially correct Mark 0.58 out of 1.00 P Flag question Computation of Variable Cost...

    Question 13 Partially correct Mark 0.58 out of 1.00 P Flag question Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Tyler Company for September: Standard cost per unit Direct materials 4 units of material A $2.00 per unit 1 unit of material B $3.00 per unit Direct labor 3 hours $8.00 per hour Activity for September Materials purchased Material A 3,400 units * $2.05 per unit Material B 800 units x...

  • All I need is the Materials Price Variance for Material A & B... thanks! Standard cost...

    All I need is the Materials Price Variance for Material A & B... thanks! Standard cost per unit 4 units of material Ax $ 6.00 per unit Direct materials 1 unit of material B x $ 8.00 per unit 3 hours x $ 18.00 per hour Direct labor Activity for September Materials purchased 6,750 units x $ 6.20 per unit Material A Material B 1,650 units x $ 8.50 per unit Materials used Material A 6,225 units Material B 1,508...

  • Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come...

    Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come from material costs that are higher or lower than expected, material usage that is not what was expected, higher or lower labor costs than expected, or more or less time spent to produce an item than expected. Overhead cost and volume variances are another cause for costs to be higher or lower than what was expected. The total manufacturing variance can be broken down...

  • Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come...

    Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come from material costs that are higher or lower than expected, material usage that is not what was expected, higher or lower labor costs than expected, or more or less time spent to produce an item than expected. Overhead cost and volume variances are another cause for costs to be higher or lower than what was expected. The total manufacturing variance can be broken down...

  • 1. Colina Production Company uses a standard costing system. The following information pertains to the current...

    1. Colina Production Company uses a standard costing system. The following information pertains to the current year. Direct labor hours is the driver used to assign overhead costs to products. Actual production 5,500 units Actual factory overhead costs ($16,500 is fixed) $40,125 Actual direct labor costs (11,250 hours) $131,625 Standard direct labor for 5,500 units: Standard hours allowed 11,000 hours Labor rate $12.00 The factory overhead rate is based on an activity level of 10,000 direct labor hours. Standard cost...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT