Computation of
Variable Cost Variances
The following information pertains to the standard costs and actual
activity for Tyler Company for September:
Standard cost per unit | |
Direct materials | 4 units of material A × $2.00 per unit |
1 unit of material B × $3.00 per unit | |
Direct labor | 3 hours × $8.00 per hour |
Activity for September | |
Materials purchased | |
Material A | 3,400 units × $2.05 per unit |
Material B | 800 units × $3.10 per unit |
Materials used | |
Material A | 3,050 units |
Material B | 705 units |
Direct labor used | 2,050 hours × $8.30 per hour |
Production output | 700 units |
There were no
beginning direct materials inventories.
(a) Determine the materials price and quantity variances.
Material A | Material B | |||
---|---|---|---|---|
Materials price variance |
Answer
Incorrect |
AnswerFU
Correct |
Answer
Incorrect |
AnswerFU
Correct |
Materials quantity variance |
Answer
Incorrect |
AnswerFU
Correct |
Answer
Incorrect |
AnswerFU
Correct |
(b) Determine the labor rate and efficiency variances.
Labor rate variance |
Answer
Incorrect |
AnswerFU
Correct |
Labor efficiency variance |
Answer
Incorrect |
AnswerFU
Correct |
Material A | Material B | |
Material price Variance | 170UF | 80UF |
Material Quantity Variance | 500UF | 15UF |
Labour Rate Variance | 615 UF | |
Labour Efficiency Variance | 400F |
Detail Working for your Easy Understanding
Material A |
calculation of direct material price variance: |
= (Standard price per unit of material - Actual price per unit of material) × Actual quantity |
= ($2/Unit - $2.05/Unit ) × 3400Unit = $170 U F |
Calculation of direct material quantity variance |
=(standard quantity of material required for actual production - actual quantity used) × Standard price per unit |
((4Units X 700 Unit)-3050 Unit )X $2 = $500U F |
Material B |
calculation of direct material price variance: |
= (Standard price per unit of material - Actual price per unit of material) × Actual quantity |
= ($3/Unit - $3.10/Unit ) × 800Unit = $80 U F |
Calculation of direct material quantity variance |
=(standard quantity of material required for actual production - actual quantity used) × Standard price per unit |
((1Units X 700 Unit)-705 Unit )X $3 = $15 UF |
Calculation of direct labor rate variance |
= (Standard direct labor rate per hour - actual direct labor rate per hour) × Actual hours used |
= ($8/hour - $8.30/hour) × 2050 Hours= $615 UF |
Calculation of direct labor efficiency variance: |
= (standard hours required for actual production - actual hours used) × standard Rate |
= (3 Hour × 700Unit - 2050) × $8 = $400 F |
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity...
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Tyler Company for September: Standard cost per unit 4 units of material A x $2.00 per unit Direct materials 1 unit of material B x $3.000 per unit 3 hours x $8.00 per hour Direct labor Activity for September Materials purchased Material A 3,400 units x $2.05 per unit 800 units x $3.10 per unit Material B Materials used Material A 3,050 units...
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Tyler Company for September: Standard cost per unit Direct materials 4 units of material A x $2.00 unit per 1 unit of material B x $3.00 per unit Direct labor 3 hours x $8.00 per hour Activity for September Materials purchased Material A 4,100 units x $2.05 per unit Material B 1,000 units x $3.10 per unit Materials used Material A 3,750 units...
The following information pertains to the standard costs and actual activity for Tyler Company for September: Standard cost per unit Direct materials 4 units of material A x $ 3.00 per unit 1 unit of material B x $ 4.00 per unit Direct labor 3 hours x $ 9.00 per hour Activity for September Materials purchased Material A 4,500 units x $ 3.10 per unit Material B 1,100 units x $ 4.15 per unit Materials used Material A 4,150 units...
Question 13 Partially correct Mark 0.58 out of 1.00 P Flag question Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Tyler Company for September: Standard cost per unit Direct materials 4 units of material A $2.00 per unit 1 unit of material B $3.00 per unit Direct labor 3 hours $8.00 per hour Activity for September Materials purchased Material A 3,400 units * $2.05 per unit Material B 800 units x...
The following information pertains to the standard costs and actual activity for Repine company for September Standard cost per unit Direct materials 4 units of material A x $ 6.00 per unit 1 unit of material B x $ 8.00 per unit 3 hours x $ 18.00 per hour 6,750 units x $ 6.20 per unit 1,650 units x $ 8.50 per unit Direct labor Activity for September Materials purchased Material A Material B Materials used Material A Material B...
Please show all work to get to answers. Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Tyler Company for September: Standard cost per unit Direct materials 4 units of material A $2.00 per unit 1 unit of material B x $3.00 per unit 3 hours x $8.00 per hour Direct labor Activity for September Materials purchased Material A Material B Materials used Material A 4,100 units x $2.05 per unit 1,000...
All I need is the Materials Price Variance for Material A & B... thanks! Standard cost per unit 4 units of material Ax $ 6.00 per unit Direct materials 1 unit of material B x $ 8.00 per unit 3 hours x $ 18.00 per hour Direct labor Activity for September Materials purchased 6,750 units x $ 6.20 per unit Material A Material B 1,650 units x $ 8.50 per unit Materials used Material A 6,225 units Material B 1,508...
Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come from material costs that are higher or lower than expected, material usage that is not what was expected, higher or lower labor costs than expected, or more or less time spent to produce an item than expected. Overhead cost and volume variances are another cause for costs to be higher or lower than what was expected. The total manufacturing variance can be broken down...
Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Kiosse Corporation’s May operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs Direct material Standard (3 lb. @ $2.00/lb.) $6 Actual (6,200 lb. @ $2.20/lb.) $13,640 Direct labor Standard (0.5 hr. @ $14/hr.) $7 Actual (980 hrs. @ $13.70/hr.) 13,426 Variable overhead Standard (0.5 hr. @ $4/hr.) $2 Actual - 4,200 Total...
Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come from material costs that are higher or lower than expected, material usage that is not what was expected, higher or lower labor costs than expected, or more or less time spent to produce an item than expected. Overhead cost and volume variances are another cause for costs to be higher or lower than what was expected. The total manufacturing variance can be broken down...