Question

Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity...

Computation of Variable Cost Variances
The following information pertains to the standard costs and actual activity for Tyler Company for September:

Standard cost per unit
Direct materials 4 units of material A × $2.00 per unit
1 unit of material B × $3.00 per unit
Direct labor 3 hours × $8.00 per hour
Activity for September
Materials purchased
Material A 3,400 units × $2.05 per unit
Material B 800 units × $3.10 per unit
Materials used
Material A 3,050 units
Material B 705 units
Direct labor used 2,050 hours × $8.30 per hour
Production output 700 units

There were no beginning direct materials inventories.

(a) Determine the materials price and quantity variances.

Material A Material B
Materials price variance Answer

Incorrect
Mark 0.00 out of 1.00

AnswerFU

Correct
Mark 1.00 out of 1.00

Answer

Incorrect
Mark 0.00 out of 1.00

AnswerFU

Correct
Mark 1.00 out of 1.00

Materials quantity variance Answer

Incorrect
Mark 0.00 out of 1.00

AnswerFU

Correct
Mark 1.00 out of 1.00

Answer

Incorrect
Mark 0.00 out of 1.00

AnswerFU

Correct
Mark 1.00 out of 1.00

(b) Determine the labor rate and efficiency variances.

Labor rate variance Answer

Incorrect
Mark 0.00 out of 1.00

AnswerFU

Correct
Mark 1.00 out of 1.00

Labor efficiency variance Answer

Incorrect
Mark 0.00 out of 1.00

AnswerFU

Correct
Mark 1.00 out of 1.00

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Material A Material B
Material price Variance 170UF 80UF
Material Quantity Variance 500UF 15UF
Labour Rate Variance 615 UF
Labour Efficiency Variance 400F

Detail Working for your Easy Understanding

Material A
calculation of direct material price variance:
= (Standard price per unit of material - Actual price per unit of material) × Actual quantity
= ($2/Unit - $2.05/Unit ) × 3400Unit = $170 U F
Calculation of direct material quantity variance
=(standard quantity of material required for actual production - actual quantity used) × Standard price per unit
((4Units    X 700 Unit)-3050 Unit )X $2 = $500U F
Material B
calculation of direct material price variance:
= (Standard price per unit of material - Actual price per unit of material) × Actual quantity
= ($3/Unit - $3.10/Unit ) × 800Unit = $80 U F
Calculation of direct material quantity variance
=(standard quantity of material required for actual production - actual quantity used) × Standard price per unit
((1Units    X 700 Unit)-705 Unit )X $3 = $15 UF
Calculation of direct labor rate variance
= (Standard direct labor rate per hour - actual direct labor rate per hour) × Actual hours used
= ($8/hour - $8.30/hour) × 2050 Hours= $615 UF
Calculation of direct labor efficiency variance:
= (standard hours required for actual production - actual hours used) × standard Rate
= (3 Hour × 700Unit - 2050) × $8 = $400 F
Add a comment
Know the answer?
Add Answer to:
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity...

    Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Tyler Company for September: Standard cost per unit 4 units of material A x $2.00 per unit Direct materials 1 unit of material B x $3.000 per unit 3 hours x $8.00 per hour Direct labor Activity for September Materials purchased Material A 3,400 units x $2.05 per unit 800 units x $3.10 per unit Material B Materials used Material A 3,050 units...

  • Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity...

    Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Tyler Company for September: Standard cost per unit Direct materials 4 units of material A x $2.00 unit per 1 unit of material B x $3.00 per unit Direct labor 3 hours x $8.00 per hour Activity for September Materials purchased Material A 4,100 units x $2.05 per unit Material B 1,000 units x $3.10 per unit Materials used Material A 3,750 units...

  • The following information pertains to the standard costs and actual activity for Tyler Company for September:...

    The following information pertains to the standard costs and actual activity for Tyler Company for September: Standard cost per unit Direct materials 4 units of material A x $ 3.00 per unit 1 unit of material B x $ 4.00 per unit Direct labor 3 hours x $ 9.00 per hour Activity for September Materials purchased Material A 4,500 units x $ 3.10 per unit Material B 1,100 units x $ 4.15 per unit Materials used Material A 4,150 units...

  • Question 13 Partially correct Mark 0.58 out of 1.00 P Flag question Computation of Variable Cost...

    Question 13 Partially correct Mark 0.58 out of 1.00 P Flag question Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Tyler Company for September: Standard cost per unit Direct materials 4 units of material A $2.00 per unit 1 unit of material B $3.00 per unit Direct labor 3 hours $8.00 per hour Activity for September Materials purchased Material A 3,400 units * $2.05 per unit Material B 800 units x...

  • The following information pertains to the standard costs and actual activity for Repine company for September Stand...

    The following information pertains to the standard costs and actual activity for Repine company for September Standard cost per unit Direct materials 4 units of material A x $ 6.00 per unit 1 unit of material B x $ 8.00 per unit 3 hours x $ 18.00 per hour 6,750 units x $ 6.20 per unit 1,650 units x $ 8.50 per unit Direct labor Activity for September Materials purchased Material A Material B Materials used Material A Material B...

  • Please show all work to get to answers. Computation of Variable Cost Variances The following information pertains to th...

    Please show all work to get to answers. Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Tyler Company for September: Standard cost per unit Direct materials 4 units of material A $2.00 per unit 1 unit of material B x $3.00 per unit 3 hours x $8.00 per hour Direct labor Activity for September Materials purchased Material A Material B Materials used Material A 4,100 units x $2.05 per unit 1,000...

  • All I need is the Materials Price Variance for Material A & B... thanks! Standard cost...

    All I need is the Materials Price Variance for Material A & B... thanks! Standard cost per unit 4 units of material Ax $ 6.00 per unit Direct materials 1 unit of material B x $ 8.00 per unit 3 hours x $ 18.00 per hour Direct labor Activity for September Materials purchased 6,750 units x $ 6.20 per unit Material A Material B 1,650 units x $ 8.50 per unit Materials used Material A 6,225 units Material B 1,508...

  • Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come...

    Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come from material costs that are higher or lower than expected, material usage that is not what was expected, higher or lower labor costs than expected, or more or less time spent to produce an item than expected. Overhead cost and volume variances are another cause for costs to be higher or lower than what was expected. The total manufacturing variance can be broken down...

  • Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Kiosse Corporation’s May...

    Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Kiosse Corporation’s May operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs Direct material Standard (3 lb. @ $2.00/lb.) $6 Actual (6,200 lb. @ $2.20/lb.) $13,640 Direct labor Standard (0.5 hr. @ $14/hr.) $7 Actual (980 hrs. @ $13.70/hr.) 13,426 Variable overhead Standard (0.5 hr. @ $4/hr.) $2 Actual - 4,200 Total...

  • Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come...

    Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come from material costs that are higher or lower than expected, material usage that is not what was expected, higher or lower labor costs than expected, or more or less time spent to produce an item than expected. Overhead cost and volume variances are another cause for costs to be higher or lower than what was expected. The total manufacturing variance can be broken down...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT