The following information pertains to the standard costs and actual activity for Tyler Company for September:
Standard cost per unit | |
Direct materials | 4 units of material A x $ 3.00 per unit |
1 unit of material B x $ 4.00 per unit | |
Direct labor | 3 hours x $ 9.00 per hour |
Activity for September | |
Materials purchased | |
Material A | 4,500 units x $ 3.10 per unit |
Material B | 1,100 units x $ 4.15 per unit |
Materials used | |
Material A | 4,150 units |
Material B | 1,005 units |
Direct labor used | 2,950 hours x $ 9.40 per hour |
Production output | 1,000 |
There were no beginning direct materials inventories.
(a) Determine the materials price and quantity variances.
Do not round final answers.
Material A | Material B | |||
---|---|---|---|---|
Materials price variance | Answer | AnswerFU | Answer | AnswerFU |
Materials quantity variance | Answer | AnswerFU | Answer | AnswerFU |
(b) Determine the labor rate and efficiency variances.
Labor rate variance | Answer | AnswerFU |
Labor efficiency variance | Answer | AnswerFU |
Please answer all parts of the question.
PreviousSave AnswersNext
For material A : | ||
Standard quantity of materials for actual production = Actual units produced * Standard quantity of material per unit = 1000 * 4 | 4000 | |
Materials price variance = ( Actual price - Standard price ) * Actual quantity = ( 3.10 - 3.00 ) * 4150 | 415 | U |
Materials quantity variance = ( Actual quantity - Standard quantity ) * Standard price = ( 4150 - 4000 ) * 3.00 | 450 | U |
For material B : | ||
Standard quantity of materials for actual production = Actual units produced * Standard quantity of material per unit = 1000 * 1 | 1000 | |
Materials price variance = ( Actual price - Standard price ) * Actual quantity = ( 4.15 - 4.00 ) * 1005 | 151 | U |
Materials quantity variance = ( Actual quantity - Standard quantity ) * Standard price = ( 1005 - 1000 ) * 4.00 | 20 | U |
Material A | Material B | |||
Materials price variance | 415 | U | 151 | U |
Materials quantity variance | 450 | U | 20 | U |
(b) | ||
Standard labor hours for actual production = Actual units production * Standard labor hours per unit = 1000 * 3 | 3000 | |
Labor rate variance = ( Actual rate - Standard rate ) * Actual hours = ( 9.40 - 9.00 ) * 2950 | 1180 | U |
Labor efficiency variance = ( Actual hours - Standard hours ) * Standard rate = ( 2950 - 3000 ) * 9.00 | (450) | F |
Note : In the absence of information regarding rounding off, the answers are rounded off to the nearest whole dollar. |
The following information pertains to the standard costs and actual activity for Tyler Company for September:...
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Tyler Company for September: Standard cost per unit Direct materials 4 units of material A × $2.00 per unit 1 unit of material B × $3.00 per unit Direct labor 3 hours × $8.00 per hour Activity for September Materials purchased Material A 3,400 units × $2.05 per unit Material B 800 units × $3.10 per unit Materials used Material A 3,050 units...
The following information pertains to the standard costs and actual activity for Repine company for September Standard cost per unit Direct materials 4 units of material A x $ 6.00 per unit 1 unit of material B x $ 8.00 per unit 3 hours x $ 18.00 per hour 6,750 units x $ 6.20 per unit 1,650 units x $ 8.50 per unit Direct labor Activity for September Materials purchased Material A Material B Materials used Material A Material B...
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Tyler Company for September: Standard cost per unit 4 units of material A x $2.00 per unit Direct materials 1 unit of material B x $3.000 per unit 3 hours x $8.00 per hour Direct labor Activity for September Materials purchased Material A 3,400 units x $2.05 per unit 800 units x $3.10 per unit Material B Materials used Material A 3,050 units...
Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Tyler Company for September: Standard cost per unit Direct materials 4 units of material A x $2.00 unit per 1 unit of material B x $3.00 per unit Direct labor 3 hours x $8.00 per hour Activity for September Materials purchased Material A 4,100 units x $2.05 per unit Material B 1,000 units x $3.10 per unit Materials used Material A 3,750 units...
Please show all work to get to answers. Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Tyler Company for September: Standard cost per unit Direct materials 4 units of material A $2.00 per unit 1 unit of material B x $3.00 per unit 3 hours x $8.00 per hour Direct labor Activity for September Materials purchased Material A Material B Materials used Material A 4,100 units x $2.05 per unit 1,000...
Question 13 Partially correct Mark 0.58 out of 1.00 P Flag question Computation of Variable Cost Variances The following information pertains to the standard costs and actual activity for Tyler Company for September: Standard cost per unit Direct materials 4 units of material A $2.00 per unit 1 unit of material B $3.00 per unit Direct labor 3 hours $8.00 per hour Activity for September Materials purchased Material A 3,400 units * $2.05 per unit Material B 800 units x...
All I need is the Materials Price Variance for Material A & B... thanks! Standard cost per unit 4 units of material Ax $ 6.00 per unit Direct materials 1 unit of material B x $ 8.00 per unit 3 hours x $ 18.00 per hour Direct labor Activity for September Materials purchased 6,750 units x $ 6.20 per unit Material A Material B 1,650 units x $ 8.50 per unit Materials used Material A 6,225 units Material B 1,508...
The following summarized manufacturing data relate to Thomas Corporation's April operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours. Standard Units Costs Total Actual Costs Direct material Standard (2 lb. @ $11.00/lb.) $22 Actual (4,200 lb. @ $12.00/lb.) $50,400 Direct labor Standard (0.5 hr. @ $26/hr.) $13 Actual (950 hrs. @ $25.20/hr.) 23,940 Variable overhead Standard (0.5 hr. @ $8/hr.) $4 Actual - 8,450 Total $39 $82,790 Determine the following variances:...
1. Colina Production Company uses a standard costing system. The following information pertains to the current year. Direct labor hours is the driver used to assign overhead costs to products. Actual production 5,500 units Actual factory overhead costs ($16,500 is fixed) $40,125 Actual direct labor costs (11,250 hours) $131,625 Standard direct labor for 5,500 units: Standard hours allowed 11,000 hours Labor rate $12.00 The factory overhead rate is based on an activity level of 10,000 direct labor hours. Standard cost...
Prime costs for Teagan's Toys to produce ping pong nets for table tops are: Actual materials purchases 320,000 pounds for $1,241,600 Actual cost (to produce 38.000 units): Direct materials 285,000 pounds Direct labor 84% of $180,000 labor costs 100,000 direct labor hours Standard cost (to produce 1 unit): Direct materials 8.5 pounds @ $3.60/pound Direct labor 25 hour @ $16/hour REQUIREMENTS Compute the following variances and indicate favorable or unfavorable. a. Direct Material Price Variance b. Direct Material Quantity Variance...