Question

Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the...

Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project A -$250 $80 $80 $80 $215 $215 Project B -$550 $350 $350 $40 $40 $40 Which project would you recommend? Select the correct answer. I. Project A, since the NPVA > NPVB. II. Neither A or B, since each project's NPV < 0. III. Project B, since the NPVB > NPVA. IV. Both Projects A and B, since both projects have NPV's > 0. V. Both Projects A and B, since both projects have IRR's > 0.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

step 1: Calculation of each project's NPV

-Project A

Year 0 1 2 3 4 5
Interest Rate 10% 10% 10% 10% 10% 10%
Cashflow(in $) -250 80 80 80 215 215
Present Value ($)             (250.00)                 72.73                       66.12                   60.11                 146.85                 133.50

NPV= $229.29 (72.73+66.12+60.11+146.85+133.50-250)

-Project B

Year 0 1 2 3 4 5
Interest Rate 10% 10% 10% 10% 10% 10%
Cashflow(in $) -550 350 350 40 40 40
Present Value ($)             (550.00)              318.18                     289.26                   30.05                   27.32                   24.84

NPV = $139.65 (318.18+289.26+30.05+27.32+24.84-550)

Formula to calculate PV in excel is as follows

"=PV(interest rate,Year,0,cashflow)"

You can use the equation Cashflow * 1/(1+i)n to find present value using calculator

Analysis: Since the projects are mutually exclusive,only one project can be selected. So select Project A since it has higher NPV.

Add a comment
Know the answer?
Add Answer to:
Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the...

    CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$400 $45 $45 $45 $230 $230 Project 2 -$650 $200 $200 $40 $40 $40 Which project would you recommend? Select the correct answer. a. Neither Project 1 nor 2, since each project's NPV < 0. b. Project 2, since the NPV2 > NPV1. c. Both Projects 1 and 2, since both projects...

  • Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the...

    Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$200 $60 $60 $60 $225 $225 Project 2 -$500 $200 $200 $50 $50 $50 Which project would you recommend? Select the correct answer. I. Project 1, since the NPV1 > NPV2. II. Neither A or B, since each project's NPV < 0. III. Both Projects 1 and 2, since both projects have...

  • A firm with a WACC of 10% is considering the following mutually exclusive projects: 1 2...

    A firm with a WACC of 10% is considering the following mutually exclusive projects: 1 2 - 4 5 $50 $215 $215 Project 1 -$400 $50 $50 Project 2 -$600 $350 $350 Which project would you recommend? $110 $110 $110 Select the correct answer. O 10 10 O O a. Project 1, since the NPV1 > NPV2 b. Both Projects 1 and 2, since both projects have NPV's > 0. c. Neither Project 1 nor 2, since each project's NPV...

  • aptel Ed-or-Chapter Problems Problem 11-10 Capital budgeting criteria: mutually exclusive projects A firm with a WACC...

    aptel Ed-or-Chapter Problems Problem 11-10 Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the following mutually exclusive projects: 2 3 5 Project 1 Project 2 -$400 $65 $65 $65 $200 $200 -$400 $250 $250 $50 $50 $50 Which project would you recommend? Select the correct answer. 1. Project 1, since the NPV1> NPV2 II. Both Projects 1 and 2, since both projects have IRR's> 0. III. Project 2, since the NPV2> NPV1 IV....

  • A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1...

    A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$450 $40 $40 $40 $165 $165 Project 2 -$450 $350 $350 $110 $110 $110 Which project would you recommend? Select the correct answer. a. Both Projects 1 and 2, since both projects have IRR's > 0. b. Project 2, since the NPV2 > NPV1. c. Neither Project 1 nor 2, since each project's NPV < 0. d. Project...

  • A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1...

    A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$500 $70 $70 $70 $215 $215 Project 2 -$400 $300 $300 $65 $65 $65 Which project would you recommend? Select the correct answer. a. Project 2, since the NPV2 > NPV1. b. Neither Project 1 nor 2, since each project's NPV < 0. c. Both Projects 1 and 2, since both projects have NPV's > 0. d. Project...

  • A firm with a WACC of 10% is considering the following mutually exclusive projects: $55 $120...

    A firm with a WACC of 10% is considering the following mutually exclusive projects: $55 $120 $215 $120 $215 $120 Project 1 - $500 $55 $55 Project 2 - $650 $300 $300 Which project would you recommend? Select the correct answer. O O O a. Both Projects 1 and 2, since both projects have NPV's > 0. b. Project 2, since the NPV2 > NPV1. c. Neither Project 1 nor 2, since each project's NPV < 0. O d. Project...

  • CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $18,000 and its expected cash flows would...

    CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $18,000 and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L costs $29,500 and its expected cash flows would be $9,200 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's > 0. b. Neither Project S nor L, since each...

  • Capital budgeting criteria: mutually exclusive projects Project S costs $12,000 and its expected cash flows would...

    Capital budgeting criteria: mutually exclusive projects Project S costs $12,000 and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $49,000 and its expected cash flows would be $12,900 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. I. Project L, since the NPVL > NPVS. II. Both Projects S and L, since both projects have NPV's > 0....

  • A firm with a WACC of 10% is considering the following mutually exclusive projects: o 1...

    A firm with a WACC of 10% is considering the following mutually exclusive projects: o 1 2 3 4 5 Project 1 Project 2 -$200 -$700 $75 $350 $75 $350 $75 $100 $230 $100 $230 $100 Which project would you recommend? Select the correct answer. a. Both Projects 1 and 2, since both projects have NPV's > 0. Ob. Project 2, since the NPV2 > NPV1. Oc. Neither Project 1 nor 2, since each project's NPV < 0. O d....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT