Capital budgeting criteria: mutually exclusive projects Project S costs $12,000 and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $49,000 and its expected cash flows would be $12,900 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. I. Project L, since the NPVL > NPVS. II. Both Projects S and L, since both projects have NPV's > 0. III. Neither S or L, since each project's NPV < 0. IV. Project S, since the NPVS > NPVL. V. Both Projects S and L, since both projects have IRR's > 0
NPV of both project is calculated in excel and screen shot provided below:
NPV of project S is $3,448.86 and NPV of project L is -$4,713.26.
Since, NPV of project S is higher than NPV of project L. So, based on NPV, Project S should be accepted.
So, Option (IV) is correct answer.
Capital budgeting criteria: mutually exclusive projects Project S costs $12,000 and its expected cash flows would...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $18,000 and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L costs $29,500 and its expected cash flows would be $9,200 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's > 0. b. Neither Project S nor L, since each...
Problem 11-11 Capital budgeting criteria: mutually exclusive projects Project S costs $16,000 and its expected cash flows would be $5,500 per year for 5 years. Mutually exclusive Project L costs $35,500 and its expected cash flows would be $8,600 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. O I. Project S, since the NPVs > NPVL. O II. Both Projects S and L, since both projects...
Problem 11-11 Capital budgeting criteria: mutually exclusive projects Project S costs $15,000 and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L costs $30,000 and its expected cash flows would be $9,600 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. O I. Project S, since the NPVS > NPVL. II. Both Projects and L, since both projects have NPV's...
11-2: Net Present Value (NPV) Capital budgeting criteria: mutually exclusive projects Project Scosts $13,000 and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $36,500 and its expected cash flows would be $8,100 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. O I. Both Projects S and L, since both projects have IRR's > 0. O II. Project...
Project S costs $11,000 and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $27,000 and its expected cash flows would be $7,500 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. I. Neither S or L, since each project's NPV < 0. II. Project L, since the NPVL > NPVS. III. Both Projects S and L, since both...
2. Project S costs $10,000 and its expected cash flows would be $5,500 per year for 5 years. Mutually exclusive Project L costs $45,000 and its expected cash flows would be $10,250 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's > 0. b. Both Projects S and L, since both projects have IRR's > 0....
Project S requires an initial outlay at t = 0 of $13,000, and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $33,000, and its expected cash flows would be $8,750 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Project L,...
Project S requires an initial outlay at t = 0 of $20,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $36,000, and its expected cash flows would be $14,550 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...
Project S requires an initial outlay at t = 0 of $18,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $35,000, and its expected cash flows would be $11,400 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...
Project S requires an initial outlay at t = 0 of $11,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $40,000, and its expected cash flows would be $14,800 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. Oa. Project L, since the NPVL > NPVS. O b. Neither...