Question

Problem 11-11 Capital budgeting criteria: mutually exclusive projects Project S costs $16,000 and its expected cash flows wou

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Since projects are mutually exclusive, we choose the project having the highe NPV

Project S:

NPV = Present value of cash inflows - present value of cash outflows

NPV = Annuity * [1 - 1 / (1 + r)n]/r - Initial investment

NPV = 5500 * [1 - 1 / (1 + 0.16)5]/ 0.16 - 16,000

NPV = 5500 * [1 - 0.476113] / 0.16 - 16,000

NPV = 5500 * 3.274294 - 16,000

NPV = $2,008.62

Project L:

NPV = Present value of cash inflows - present value of cash outflows

NPV = Annuity * [1 - 1 / (1 + r)n]/r - Initial investment

NPV = 8600 * [1 - 1 / (1 + 0.16)5]/ 0.16 - 35,500

NPV = 8600 * [1 - 0.476113] / 0.16 - 35,500

NPV = 8600 * 3.274294 - 35,500

NPV = -7,341.07

Project S, since the NPVs > NPVL

Add a comment
Know the answer?
Add Answer to:
Problem 11-11 Capital budgeting criteria: mutually exclusive projects Project S costs $16,000 and its expected cash...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 11-11 Capital budgeting criteria: mutually exclusive projects Project S costs $15,000 and its expected cash...

    Problem 11-11 Capital budgeting criteria: mutually exclusive projects Project S costs $15,000 and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L costs $30,000 and its expected cash flows would be $9,600 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. O I. Project S, since the NPVS > NPVL. II. Both Projects and L, since both projects have NPV's...

  • CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $18,000 and its expected cash flows would...

    CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $18,000 and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L costs $29,500 and its expected cash flows would be $9,200 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's > 0. b. Neither Project S nor L, since each...

  • Capital budgeting criteria: mutually exclusive projects Project S costs $12,000 and its expected cash flows would...

    Capital budgeting criteria: mutually exclusive projects Project S costs $12,000 and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $49,000 and its expected cash flows would be $12,900 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. I. Project L, since the NPVL > NPVS. II. Both Projects S and L, since both projects have NPV's > 0....

  • 11-2: Net Present Value (NPV) Capital budgeting criteria: mutually exclusive projects Project Scosts $13,000 and its ex...

    11-2: Net Present Value (NPV) Capital budgeting criteria: mutually exclusive projects Project Scosts $13,000 and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $36,500 and its expected cash flows would be $8,100 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. O I. Both Projects S and L, since both projects have IRR's > 0. O II. Project...

  • Project S costs $11,000 and its expected cash flows would be $4,500 per year for 5...

    Project S costs $11,000 and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $27,000 and its expected cash flows would be $7,500 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. I. Neither S or L, since each project's NPV < 0. II. Project L, since the NPVL > NPVS. III. Both Projects S and L, since both...

  • Project S requires an initial outlay at t = 0 of $13,000, and its expected cash...

    Project S requires an initial outlay at t = 0 of $13,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $43,000, and its expected cash flows would be $8,000 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. O a. Both Projects S and L, since both projects have...

  • 2. Project S costs $10,000 and its expected cash flows would be $5,500 per year for...

    2. Project S costs $10,000 and its expected cash flows would be $5,500 per year for 5 years. Mutually exclusive Project L costs $45,000 and its expected cash flows would be $10,250 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's > 0. b. Both Projects S and L, since both projects have IRR's > 0....

  • Project S requires an initial outlay at t = 0 of $13,000, and its expected cash...

    Project S requires an initial outlay at t = 0 of $13,000, and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $33,000, and its expected cash flows would be $8,750 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Project L,...

  • Project S requires an initial outlay at t = 0 of $20,000, and its expected cash...

    Project S requires an initial outlay at t = 0 of $20,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $36,000, and its expected cash flows would be $14,550 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...

  • Project S requires an initial outlay at t = 0 of $18,000, and its expected cash...

    Project S requires an initial outlay at t = 0 of $18,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $35,000, and its expected cash flows would be $11,400 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT