Project S costs $11,000 and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $27,000 and its expected cash flows would be $7,500 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend?
Select the correct answer.
|
|||
|
|||
|
|||
|
|||
|
When projects are mutually exclusive, we always choose the project with the higher NPV.
Project S:
NPV = Present value of cash inflows - present value of cash outflows
NPV = Annuity * [1 - 1 / (1 + r)n] / r - Initial investment
NPV = 4,500 * [1 - 1 / (1 + 0.13)5] / 0.13 - 11,000
NPV = 4,500 * [1 - 0.54276] / 0.13 - 11,000
NPV = 4,500 * 3.517231 - 11,000
NPV = $4,827.54
Project L:
NPV = Present value of cash inflows - present value of cash outflows
NPV = Annuity * [1 - 1 / (1 + r)n] / r - Initial investment
NPV = 7,500 * [1 - 1 / (1 + 0.13)5] / 0.13 - 27,000
NPV = 7,500 * [1 - 0.54276] / 0.13 - 27,000
NPV = 7,500 * 3.517231 - 27,000
NPV = -620.77
V. Project S, since the NPVS > NPVL
Project S costs $11,000 and its expected cash flows would be $4,500 per year for 5...
Capital budgeting criteria: mutually exclusive projects Project S costs $12,000 and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $49,000 and its expected cash flows would be $12,900 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. I. Project L, since the NPVL > NPVS. II. Both Projects S and L, since both projects have NPV's > 0....
2. Project S costs $10,000 and its expected cash flows would be $5,500 per year for 5 years. Mutually exclusive Project L costs $45,000 and its expected cash flows would be $10,250 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's > 0. b. Both Projects S and L, since both projects have IRR's > 0....
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $18,000 and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L costs $29,500 and its expected cash flows would be $9,200 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's > 0. b. Neither Project S nor L, since each...
Project S requires an initial outlay at t = 0 of $11,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $40,000, and its expected cash flows would be $14,800 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. Oa. Project L, since the NPVL > NPVS. O b. Neither...
Project S requires an initial outlay at t = 0 of $18,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $35,000, and its expected cash flows would be $11,400 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...
Problem 11-11 Capital budgeting criteria: mutually exclusive projects Project S costs $16,000 and its expected cash flows would be $5,500 per year for 5 years. Mutually exclusive Project L costs $35,500 and its expected cash flows would be $8,600 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. O I. Project S, since the NPVs > NPVL. O II. Both Projects S and L, since both projects...
Problem 11-11 Capital budgeting criteria: mutually exclusive projects Project S costs $15,000 and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L costs $30,000 and its expected cash flows would be $9,600 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. O I. Project S, since the NPVS > NPVL. II. Both Projects and L, since both projects have NPV's...
0 of $17,000, and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L requires Project S requires an initial outlay at t an initial outlay at t 0 of $37,000, and its expected cash flows would be $14,600 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer a. Project s, since the NPVs > NPV O b. Project L, since...
Project S requires an initial outlay at t = 0 of $13,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $43,000, and its expected cash flows would be $8,000 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. O a. Both Projects S and L, since both projects have...
Project S requires an initial outlay at t = 0 of $11,000, and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $33,500, and its expected cash flows would be $13,100 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project S, since the NPVs > NPVĻ. b. Project L,...