Project S
Time | 0 | 1 | 2 | 3 | 4 | 5 |
Cash flow of S | -11000 | 4000 | 4000 | 4000 | 4000 | 4000 |
WACC of S = 12%
NPV of the projects can be calculated using the formula:
NPV = C0 + C1/(1+r)1 + C2/(1+r)2+ C3/(1+r)3+ C4/(1+r)4+ C5/(1+r)5
Cash flow of S is: C0 = -11000, C1 = 4000, C2 = 4000, C3 = 4000, C4 = 4000, C5 = 4000
NPV of S = -11000 + 4000/(1.12)1 + 4000/(1.12)2 + 4000/(1.12)3 + 4000/(1.12)4 + 4000/(1.12)5 = -11000+3571.428571+3188.77551+2847.120991+2542.072314+2269.707423 = 3419.104809
NPV of project S = 3419.104809
Project L
Time | 0 | 1 | 2 | 3 | 4 | 5 |
Cash flow of L | -33500 | 13100 | 13100 | 13100 | 13100 | 13100 |
WACC of L = 12%
NPV of the projects can be calculated using the formula:
NPV = C0 + C1/(1+r)1 + C2/(1+r)2+ C3/(1+r)3+ C4/(1+r)4+ C5/(1+r)5
Cash flow of L is: C0 = -33500, C1 = 13100, C2 = 13100, C3 = 13100, C4 = 13100, C5 = 13100
NPV of L = -33500 + 13100/(1.12)1 + 13100/(1.12)2 + 13100/(1.12)3 + 13100/(1.12)4 + 13100/(1.12)5 = -33500+11696.428571+10443.239796+9324.321246+8325.286827+7433.29181 = 13722.5682507196
NPV of Project L = 13722.568
Since the projects are mutally exclusive, we can only select one project with highest NPV
NPVL > NPVS
So, we should select Project L as NPVL > NPVS
Option b is the correct option
Correct Answer -> Project L, since NPVL > NPVS
Project S requires an initial outlay at t = 0 of $11,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $11,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $40,000, and its expected cash flows would be $14,800 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. Oa. Project L, since the NPVL > NPVS. O b. Neither...
Project S requires an initial outlay at t = 0 of $13,000, and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $33,000, and its expected cash flows would be $8,750 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Project L,...
Project S requires an initial outlay at t = 0 of $20,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $36,000, and its expected cash flows would be $14,550 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...
Project S requires an initial outlay at t = 0 of $18,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $35,000, and its expected cash flows would be $11,400 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...
Project S requires an initial outlay at t = 0 of $13,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $43,000, and its expected cash flows would be $8,000 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. O a. Both Projects S and L, since both projects have...
eBook Project S requires an initial outlay at t - 0 of $10,000, and its expected cash flows would be $6,500 per year for 5 years, Mutually exclusive Project L requires an initial outlay at t = 0 of $48,000, and its expected cash flows would be $9,550 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer a. Project L, since the NPV > NPV- b. Both...
0 of $17,000, and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L requires Project S requires an initial outlay at t an initial outlay at t 0 of $37,000, and its expected cash flows would be $14,600 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer a. Project s, since the NPVs > NPV O b. Project L, since...
Project S costs $11,000 and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $27,000 and its expected cash flows would be $7,500 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. I. Neither S or L, since each project's NPV < 0. II. Project L, since the NPVL > NPVS. III. Both Projects S and L, since both...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $18,000 and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L costs $29,500 and its expected cash flows would be $9,200 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's > 0. b. Neither Project S nor L, since each...
Capital budgeting criteria: mutually exclusive projects Project S costs $12,000 and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $49,000 and its expected cash flows would be $12,900 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. I. Project L, since the NPVL > NPVS. II. Both Projects S and L, since both projects have NPV's > 0....