Question

Project S requires an initial outlay at t = 0 of $11,000, and its expected cash flows would be $4,000 per year for 5 years. M

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Project S

Time 0 1 2 3 4 5
Cash flow of S   -11000 4000 4000   4000   4000   4000

WACC of S = 12%

NPV of the projects can be calculated using the formula:

NPV = C0 + C1/(1+r)1 + C2/(1+r)2+ C3/(1+r)3+ C4/(1+r)4+ C5/(1+r)5

Cash flow of S is: C0 = -11000, C1 = 4000, C2 = 4000, C3 = 4000, C4 = 4000, C5 = 4000

NPV of S = -11000 + 4000/(1.12)1 + 4000/(1.12)2 + 4000/(1.12)3 + 4000/(1.12)4​​​​​​​ + 4000/(1.12)5​​​​​​​ = -11000+3571.428571+3188.77551+2847.120991+2542.072314+2269.707423 = 3419.104809

NPV of project S = 3419.104809

Project L

Time 0 1 2 3 4 5
Cash flow of L -33500 13100 13100 13100 13100 13100

WACC of L = 12%

NPV of the projects can be calculated using the formula:

NPV = C0 + C1/(1+r)1 + C2/(1+r)2+ C3/(1+r)3+ C4/(1+r)4+ C5/(1+r)5

Cash flow of L is: C0 = -33500, C1 = 13100, C2 = 13100, C3 = 13100, C4 = 13100, C5 = 13100

NPV of L = -33500 + 13100/(1.12)1 + 13100/(1.12)2 + 13100/(1.12)3​​​​​​​ + 13100/(1.12)4​​​​​​​ + 13100/(1.12)5​​​​​​​ = -33500+11696.428571+10443.239796+9324.321246+8325.286827+7433.29181 = 13722.5682507196

NPV of Project L = 13722.568

Since the projects are mutally exclusive, we can only select one project with highest NPV

NPVL > NPVS

So, we should select Project L as NPVL > NPVS

Option b is the correct option

Correct Answer -> Project L, since NPVL > NPVS

Add a comment
Know the answer?
Add Answer to:
Project S requires an initial outlay at t = 0 of $11,000, and its expected cash...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Project S requires an initial outlay at t = 0 of $11,000, and its expected cash...

    Project S requires an initial outlay at t = 0 of $11,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $40,000, and its expected cash flows would be $14,800 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. Oa. Project L, since the NPVL > NPVS. O b. Neither...

  • Project S requires an initial outlay at t = 0 of $13,000, and its expected cash...

    Project S requires an initial outlay at t = 0 of $13,000, and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $33,000, and its expected cash flows would be $8,750 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Project L,...

  • Project S requires an initial outlay at t = 0 of $20,000, and its expected cash...

    Project S requires an initial outlay at t = 0 of $20,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $36,000, and its expected cash flows would be $14,550 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...

  • Project S requires an initial outlay at t = 0 of $18,000, and its expected cash...

    Project S requires an initial outlay at t = 0 of $18,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $35,000, and its expected cash flows would be $11,400 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...

  • Project S requires an initial outlay at t = 0 of $13,000, and its expected cash...

    Project S requires an initial outlay at t = 0 of $13,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $43,000, and its expected cash flows would be $8,000 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. O a. Both Projects S and L, since both projects have...

  • eBook Project S requires an initial outlay at t - 0 of $10,000, and its expected...

    eBook Project S requires an initial outlay at t - 0 of $10,000, and its expected cash flows would be $6,500 per year for 5 years, Mutually exclusive Project L requires an initial outlay at t = 0 of $48,000, and its expected cash flows would be $9,550 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer a. Project L, since the NPV > NPV- b. Both...

  • 0 of $17,000, and its expected cash flows would be $7,000 per year for 5 years....

    0 of $17,000, and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L requires Project S requires an initial outlay at t an initial outlay at t 0 of $37,000, and its expected cash flows would be $14,600 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer a. Project s, since the NPVs > NPV O b. Project L, since...

  • Project S costs $11,000 and its expected cash flows would be $4,500 per year for 5...

    Project S costs $11,000 and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $27,000 and its expected cash flows would be $7,500 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. I. Neither S or L, since each project's NPV < 0. II. Project L, since the NPVL > NPVS. III. Both Projects S and L, since both...

  • CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $18,000 and its expected cash flows would...

    CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $18,000 and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L costs $29,500 and its expected cash flows would be $9,200 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's > 0. b. Neither Project S nor L, since each...

  • Capital budgeting criteria: mutually exclusive projects Project S costs $12,000 and its expected cash flows would...

    Capital budgeting criteria: mutually exclusive projects Project S costs $12,000 and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $49,000 and its expected cash flows would be $12,900 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. I. Project L, since the NPVL > NPVS. II. Both Projects S and L, since both projects have NPV's > 0....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT