Question

11-2: Net Present Value (NPV) Capital budgeting criteria: mutually exclusive projects Project Scosts $13,000 and its expected

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer: Option III is correct. Project S should be selected since NPV of project S > NPV of project L
1 Year Projects Project L -13000 -36500 4500 8100 4500 8100 4500 8100 4500 8100 4500 8100 NPV= 2084.70 -9347.54 9 Formula use

So, the NPV of project S is positive and the NPV of project L is negative

Mutually exclusive projects are a set of projects out of which only one project should be selected.

In this case, the project with project with positive NPV should be selected.

So, project S should be selected

Add a comment
Know the answer?
Add Answer to:
11-2: Net Present Value (NPV) Capital budgeting criteria: mutually exclusive projects Project Scosts $13,000 and its ex...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 11-11 Capital budgeting criteria: mutually exclusive projects Project S costs $16,000 and its expected cash...

    Problem 11-11 Capital budgeting criteria: mutually exclusive projects Project S costs $16,000 and its expected cash flows would be $5,500 per year for 5 years. Mutually exclusive Project L costs $35,500 and its expected cash flows would be $8,600 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. O I. Project S, since the NPVs > NPVL. O II. Both Projects S and L, since both projects...

  • Problem 11-11 Capital budgeting criteria: mutually exclusive projects Project S costs $15,000 and its expected cash...

    Problem 11-11 Capital budgeting criteria: mutually exclusive projects Project S costs $15,000 and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L costs $30,000 and its expected cash flows would be $9,600 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. O I. Project S, since the NPVS > NPVL. II. Both Projects and L, since both projects have NPV's...

  • CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $18,000 and its expected cash flows would...

    CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $18,000 and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L costs $29,500 and its expected cash flows would be $9,200 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's > 0. b. Neither Project S nor L, since each...

  • Capital budgeting criteria: mutually exclusive projects Project S costs $12,000 and its expected cash flows would...

    Capital budgeting criteria: mutually exclusive projects Project S costs $12,000 and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $49,000 and its expected cash flows would be $12,900 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. I. Project L, since the NPVL > NPVS. II. Both Projects S and L, since both projects have NPV's > 0....

  • Project S requires an initial outlay at t = 0 of $13,000, and its expected cash...

    Project S requires an initial outlay at t = 0 of $13,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $43,000, and its expected cash flows would be $8,000 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. O a. Both Projects S and L, since both projects have...

  • Project S requires an initial outlay at t = 0 of $13,000, and its expected cash...

    Project S requires an initial outlay at t = 0 of $13,000, and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $33,000, and its expected cash flows would be $8,750 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Project L,...

  • Project S costs $11,000 and its expected cash flows would be $4,500 per year for 5...

    Project S costs $11,000 and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $27,000 and its expected cash flows would be $7,500 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. I. Neither S or L, since each project's NPV < 0. II. Project L, since the NPVL > NPVS. III. Both Projects S and L, since both...

  • Project S requires an initial outlay at t = 0 of $20,000, and its expected cash...

    Project S requires an initial outlay at t = 0 of $20,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $36,000, and its expected cash flows would be $14,550 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...

  • Project S requires an initial outlay at t = 0 of $18,000, and its expected cash...

    Project S requires an initial outlay at t = 0 of $18,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $35,000, and its expected cash flows would be $11,400 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...

  • Project S requires an initial outlay at t = 0 of $11,000, and its expected cash...

    Project S requires an initial outlay at t = 0 of $11,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $40,000, and its expected cash flows would be $14,800 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. Oa. Project L, since the NPVL > NPVS. O b. Neither...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT