Question

What are some advantages project network diagrams have over traditional Gantt charts? What is a baseline...

  1. What are some advantages project network diagrams have over traditional Gantt charts?
  2. What is a baseline plan? What purpose does it serve once the project team begins to execute the plan?


    Please post 2 to 3 paragraphs per question and if you used websites please post them after the answer, will rate!!!!
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Que 1

A Gantt chart is a visual presentation used in project management to show overview of timeline for project activities and their inter-dependence. Each project task or activity is represented with a bar chart clearly displaying start and end date. Thus the length of the bar shows the duration required for a task to complete. This way multiple tasks when displayed as bar charts, shows work breakdown structure on a timeline. Essentially Gantt chart shows when an activity starts, completes, how long it will take to complete an activities and also overall project, which is a project schedule.

Que 2

Once approved by the project manager, sponsor & team, the project plan becomes the baseline plan. Baseline plan is used by the mgr to compare the actual schedule to the estimated schedule & actual costs to budgeted costs

Web Site - http://blog.zilicus.com/what-is-a-gantt-chart-advantages-limitations-gantt-chart/

Add a comment
Know the answer?
Add Answer to:
What are some advantages project network diagrams have over traditional Gantt charts? What is a baseline...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Performance Improvement programs and effective project management require an understanding of the four phases of the...

    Performance Improvement programs and effective project management require an understanding of the four phases of the project life-cycle: initiation, planning, execution/implementation, and closure. It is important to have each phase of the project mapped on a timeline and to be sure the project team has the appropriate members with the right skills to ensure a successful program. Using a case study from the text, students will demonstrate their ability to review and evaluate a performance improvement program by arranging the...

  • Need help with this project please! Please name the compiler and software used, would really appr...

    Need help with this project please! Please name the compiler and software used, would really appreciate that information. Don't bother doing the report section on this assignment either. Me and my group will handle it. This is a group project. Group size should be exactly 2 (unless approved earlier by the instructor). Only ne mi imi ma Design a security architecture for a smart electric metering infrastructure. Smart electric meters have embedded hardware for cellular connectivity, and are able to...

  • Please help writing a well structured document using the below Agile Runbook - Our Overall Delivery Process How do we initiate a Project? Any project is a response to a pain point or desire expresse...

    Please help writing a well structured document using the below Agile Runbook - Our Overall Delivery Process How do we initiate a Project? Any project is a response to a pain point or desire expressed by either customers, internal stakeholders, employees, or regulatory authorities. In short, a project is a time bound and specific goal oriented task-system that is born out of an ask from any stakeholder. Project initiation is laying down a new project by defining its goals, objectives,...

  • Please read through the article below and answer the question at the end of the article....

    Please read through the article below and answer the question at the end of the article. What Are the Project Management Knowledge Areas? PMI created a set of standard terminology and guidelines for project management, which is known as the project management knowledge areas. This is an evolving standard that is updated periodically in its PMBOK. Project management knowledge areas coincide with the process groups, which are project initiation, project planning, project execution, monitoring and controlling, and project closing. These...

  • RADICO’S CHALLENGE The executive staff at Radico Corporation was quite pleased with the one-day training program...

    RADICO’S CHALLENGE The executive staff at Radico Corporation was quite pleased with the one-day training program they attended on the benefits of using agile and Scrum on some of their projects. Radico provided products and services to both public and private sector clients, almost all of it through competitive bidding. IT was not required for any of the products and services Radico provided. Agile and Scrum had proven to be successful on internal IT projects, but there were some concerns...

  • Can I have some comments about this post please? The two of my favorer brands on...

    Can I have some comments about this post please? The two of my favorer brands on that list are Apple and Amazon. What’s comes to the mind about Apple are revolutionary and innovative products like the iPod digital music player, iPhone, Apple TV, iPad, Apple watch, iMac computers. The brand that translates to users the whole image of creativity, innovation, design and originality, has become one of the best in the world for decades, led by a genius who has...

  • HEA 285 Wellness Project Guide Sheet The wellness project focuses on the process of changing personal behavior. Th...

    HEA 285 Wellness Project Guide Sheet The wellness project focuses on the process of changing personal behavior. The primary focus is the PROCESS of behavior ou e comfortable working with and sharing with your instructor. Please see your this project. Objective: The purpose of the wellness projet is to 1. Demo nstrate knowledge of lifestyle behaviors that promote wellness & reduce the risk of illness, injury. and disease 2. Demonstrate responsible decision making skillsfor the enhancement of individual Steps to...

  • 3. What are the advantages and disadvantages of the various options that Amelectserv is evaluating ERP...

    3. What are the advantages and disadvantages of the various options that Amelectserv is evaluating ERP IMPLEMENTATION COSTS Berp Corporation: ON Premise Macrosoft ON Premise 4718 4719 Macrosoft Cloud 4.718 2080 1575 2 DOO 2250 2.250 2980 none none 1675 none 349 10.200 InitialHardware Network Costs Workstations UPS for Werkstations Laptops Server Back Server Server UPS Systems Router Network Infrastrutture set-up Total Ongoing Hardware Network Costs Hardware Maintenance Router Maintenance Network in structure Maintance 2MBPS internet line Totalt year) Total...

  • Hi, Kindly assist with my project management assignment below using the attached case study Question 1 Update the project charter for the remainder of the project in response to Adams’ memo (lines 241...

    Hi, Kindly assist with my project management assignment below using the attached case study Question 1 Update the project charter for the remainder of the project in response to Adams’ memo (lines 241 through 246). Question 2 Prepare a plan for the remainder of the project in response to Adams’ memo (lines 241 through 246). Your answers to the above will be assessed in terms of the level of communication displayed, the insights and inferences drawn, and your ability to...

  • How can we assess whether a project is a success or a failure? This case presents...

    How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT