Question

S 23-9 Scrap or rework LO A1 Signal mistakenly produced 1,300 defective cell phones. The phones cost $70 each to produce. A salvage company will buy the defective phones as they are for $33 each. It would cost Signal $86 per phone to rework the phones. If the phones are reworked, Signal could sell them for $142 each. Assume there is no opportunity cost associated with reworking the phones. Compute the incremental net income from reworking the phones. Scrap Rework Sales Rework costs Total
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Scrap Rework
Sales $ 42,900 $ 184,600
Rework Costs - 111,800
Total $ 42,900 $ 72,800

Incremental net income from reworking the phones : $ 72,800 - $ 42,900 = $ 29,900.

The cost of $ 70 for producing the cell phones is a sunk (unavoidable) cost, and hence is not relevant.

Add a comment
Know the answer?
Add Answer to:
S 23-9 Scrap or rework LO A1 Signal mistakenly produced 1,300 defective cell phones. The phones...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Check my work QS 23-9 Scrap or rework LO A1 1.42 points Signal mistakenly produced 1,025...

    Check my work QS 23-9 Scrap or rework LO A1 1.42 points Signal mistakenly produced 1,025 defective cell phones. The phones cost $69 each to produce. A salvage company will buy the defective phones as they are for $34 each. It would cost Signal $88 per phone to rework the phones. If the phones are reworked, Signal could sell them for $148 each. Assume there is no opportunity cost associated with reworking the phones. Compute the incremental net income from...

  • Signal mistakenly produced 1,325 defective cell phones. The phones cost $65 each to produce. A salvage company will buy...

    Signal mistakenly produced 1,325 defective cell phones. The phones cost $65 each to produce. A salvage company will buy the defective phones as they are for $33 each. It would cost Signal $84 per phone to rework the phones. If the phones are reworked, Signal could sell them for $130 each. Assume there is no opportunity cost associated with reworking the phones. Compute the incremental net income from reworking the phones. ork the phones, the phones are rewo Scrap Rework...

  • Exercise 10-6 Scrap or rework LO A1 A company must decide betwee that cost $5.40 per...

    Exercise 10-6 Scrap or rework LO A1 A company must decide betwee that cost $5.40 per unit to manufacture. The units can be sold for the full price of $8.70 each. If the units are sold as is, the company will be able to build 16,000 replacement units at a cost of n scrapping or reworking units that do not pass inspection. The company has 16,000 defective units sold as is for $3.30 each, or they can be reworked for...

  • Marco mistakenly made 1,275 defective bikes. The bikes cost $61 each to make. A salvage company...

    Marco mistakenly made 1,275 defective bikes. The bikes cost $61 each to make. A salvage company decided to purchase the defective bikes as is for $32 each. It would cost Marco $84 per bike to rework the bikes. If Marco rework the bikes, he could sell them for $146 each. No opportunity cost is associated with reworking the bikes. What is the incremental net income from reworking the bikes. Scrap Rework Sales Rework costs Total

  • Saved Help Exercise 23-4 Scrap or rework LO P2 A company with excess capacity must decide...

    Saved Help Exercise 23-4 Scrap or rework LO P2 A company with excess capacity must decide between scrapping or reworking units that do not pass inspection. The company has 13,000 defective units that cost $5.50 per unit to manufacture. The units can be a) sold as is for $2.60 each, or b) reworked for $4.50 each and then sold for the full price of $8.10 each. What is the incremental income from selling the units as scrap and reworking and...

  • Marco mistakenly made 1,150 defective bikes. The bikes cost $69 each to make. A salvage company...

    Marco mistakenly made 1,150 defective bikes. The bikes cost $69 each to make. A salvage company decided to purchase the defective bikes as is for $31 each. It would cost Marco $88 per bike to rework the bikes. If Marco rework the bikes, he could sell them for $132 each. No opportunity cost is associated with reworking the bikes. What is the incremental net income from reworking the bikes.

  • Check my work Exercise 23-4 Scrap or rework LO P2 points A company with excess capacity must decide between scrapping o...

    Check my work Exercise 23-4 Scrap or rework LO P2 points A company with excess capacity must decide between scrapping or reworking units that do not pass inspection. The company has 10,000 defective units that cost $5.40 per unit to manufacture. The units can be a) sold as is for $2.90 each, or b) reworked for $4.80 each and then sold for the full price of $8.30 each. Skipped What is the incremental income from selling the units as scrap...

  • Exercise 23-7 Scrap or rework LO A1 Varto Company has 11,000 units of its sole product...

    Exercise 23-7 Scrap or rework LO A1 Varto Company has 11,000 units of its sole product in inventory that it produced last year at a cost of $24 each. This year's model is superior to last year's, and the 11,000 units cannot be sold at last year's regular selling price of $47 each. Varto has two alternatives for these items: (1) they can be sold to a wholesaler for $12 each, or (2) they can be reworked at a cost...

  • Problem 23-4A Sell or process LO A1 Harold Manufacturing produces denim clothing. This year, it produced...

    Problem 23-4A Sell or process LO A1 Harold Manufacturing produces denim clothing. This year, it produced 5,180 denim jackets at a manufacturing cost of $41.00 each. These jackets were damaged in the warehouse during storage. Management investigated the matter and identified three alternatives for these jackets. 1. Jackets can be sold to a secondhand clothing shop for $7.00 each. 2. Jackets can be disassembled at a cost of $33,000 and sold to a recycler for $11.00 each. 3. Jackets can...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT