Question

If an analyst predicts that the benefits of a three-year project would be $100,000 at the...

If an analyst predicts that the benefits of a three-year project would be $100,000 at the end of the first year, $110,000 at the end of the second year, and $120,000 at the end of the project life, the scrap value of the project is expected to be $25,000 upon resale, and the discount rate is 4%, how much is the present value of total benefits for the project?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Present value of benefits = 100,000*PVF(4%, 1 year) + 110,000*PVF(4%, 2 years) + 120,000*PVF(4%, 3 years) + 25000*PVF(4%,3 years)

= 100,000*0.962 + 110,000*0.925 + 120,000*0.889 + 25000*0.889

= $326,855

Add a comment
Know the answer?
Add Answer to:
If an analyst predicts that the benefits of a three-year project would be $100,000 at the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 2. The government is contemplating project A that yields the following stream of benefits and costs....

    2. The government is contemplating project A that yields the following stream of benefits and costs. Project A Year 2 S10,0000 0 Benefits0 $2,000 $4,000 $6,000 (a) Find the net present value and the benefit cost ratio for this project, assuming a discount rate of 5%. (b) Re-calculate the net present value assuming a discount rate of (i) 3%, (ii) 8 % and (iii) 10%. Use a graph to illustrate how the net present value of the project is affected...

  • Your firm is trying to decide whether to invest in a new project opportunity based on...

    Your firm is trying to decide whether to invest in a new project opportunity based on the following information. The initial cash outlay will total $750,000. The money will be payable immediately upon the start of the project. The company predicts that the project will generate a stream of earnings of $150,000, $100,000, $100,000, $300,000, and $500,000, per year, respectively, starting in Year 2. The required rate of return is 10%, and the expected rate of return is 3%. 1....

  • A project where the projected costs and benefits are spread over five years with the following...

    A project where the projected costs and benefits are spread over five years with the following data: • Estimated costs are $100,000 in Year 1 and $25,000 each for years 2, 3, 4, and 5. • Estimated benefits are $0 in Year 1 and $80,000 each for years 2, 3, 4, and 5. • Use a discount rate of 8% 1.Calculate the following: a. Calculate cash flow b. Show the discount factor c. Show discounted costs and discounted benefits d....

  • Your company is considering a new project that will require $100,000 of new equipment at the...

    Your company is considering a new project that will require $100,000 of new equipment at the start of the project. The equipment will have a depreciable life of 10 years and will be depreciated to a book value of $25,000 using straight-line depreciation. The cost of capital is 11 percent, and the firm's tax rate is 34 percent. Estimate the present value of the tax benefits from depreciation.

  • 6. The government is considering an early education project for children currently aged three. The project...

    6. The government is considering an early education project for children currently aged three. The project involves annual costs of S2500 for 5 years (starting t-1). Annual net benefits of S3000 start in year 15 (once the children reach the age of 22) and last for 20 years. Assume all benefits and costs are incurred at the end of the year. ustrate the timing of benefits and costs using a timeline. (b) (c) There is some uncertainty about the choice...

  • Problem: Your firm is trying to decide whether to invest in a new project opportunity based...

    Problem: Your firm is trying to decide whether to invest in a new project opportunity based on the following information. The initial cash outlay will total $750,000. The money will be payable immediately upon the start of the project. The company predicts that the project will generate a stream of earnings of $150,000, $100,000, $100,000, $300,000, and $500,000, per year, respectively, starting in Year 2. The required rate of return is 10%, and the expected rate of return is 3%....

  • Problem: Your firm is trying to decide whether to invest in a new project opportunity based...

    Problem: Your firm is trying to decide whether to invest in a new project opportunity based on the following information. The initial cash outlay will total $750,000. The money will be payable immediately upon the start of the project. The company predicts that the project will generate a stream of earnings of $150,000, $100,000, $100,000, $300,000, and $500,000, per year, respectively, starting in Year 2. The required rate of return is 10%, and the expected rate of return is 3%....

  • XYZ Ltd is a company that is considering two alternative​ investments: Project A that would cost...

    XYZ Ltd is a company that is considering two alternative​ investments: Project A that would cost ​£40,000 and Project B that would cost £39,000.The chosen project would commence on 1 January next year​ ('Year 1'), when the initial investment would be made.As a result of the​ investment,SettloxLtd can expect to increase its cash flows over the life of the project by the following predicted​ amounts: Year Project C (£) Project D (£) 1 10,000 16,000 2 12,000 4,000 3 21,000...

  • 7. Consider a highway project with the following costs and benefits. This representation of costs and...

    7. Consider a highway project with the following costs and benefits. This representation of costs and benefits assumes the costs occur immediately and the benefits occur at the end of year 1, end of year 2 and the end of year 3. Year 0 Costs $470,000 Benedi 0 $275.00 $295.005$315.000 $275,000$295,000 S315,000 (a) Calculate the net present value of the project. Assume a discount rate of 4%. Now suppose all the benefits occur at the start of each period. What...

  • In year three of a product's life, the cash flows expected are: marketing cost of $100,000,...

    In year three of a product's life, the cash flows expected are: marketing cost of $100,000, production cost of $200,000, and a revenue of $800,000. At 12.4% interest rate, what is the present value (at time zero) of the cash flow of year three? (assume all cash flows occur at the end of the year).

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT