Question

Qwerty Corp. is about to begin production on two homes in a new housing subdivision. Qwerty...

Qwerty Corp. is about to begin production on two homes in a new housing subdivision. Qwerty Corp. anticipates that it will need 80,000 square feet of lumber over its 450 day construction cycle. Ordering and holding costs are $6/order and $8/sq.ft., respectively. Qwerty Corp.'s turnaround time on a lumber order is 2 days.

Round intermediate calculations, but round final answer to 2 decimal places.

Part 1. How many orders should Qwerty Corp. make to minimize inventory costs?

Part 2. At what inventory level should Qwerty Corp. order lumber if the company wants to minimize inventory costs?

Part 3. What is the total cost per inventory order for Qwerty Corp.?

Part 4. How many units of lumber will Qwerty Corp. have in its inventory at the end of the 3rd day of construction?

0 0
Add a comment Improve this question Transcribed image text
Request Professional Answer

Request Answer!

We need at least 10 more requests to produce the answer.

0 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the answer will be notified once they are available.
Know the answer?
Add Answer to:
Qwerty Corp. is about to begin production on two homes in a new housing subdivision. Qwerty...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Economic Order Quantity Ottis, Inc., uses 656,100 plastic housing units each year in its production of...

    Economic Order Quantity Ottis, Inc., uses 656,100 plastic housing units each year in its production of paper shredders. The cost of placing an order is $24. The cost of holding one unit of inventory for one year is $12. Currently, Ottis places 162 orders of 4,050 plastic housing units per year. Required: 1. Compute the economic order quantity. X units 2. Compute the ordering, carrying, and total costs for the EOQ. Ordering cost $ X Carrying cost Total cost 3....

  • A company is about to begin production of a new product. The manager of the department...

    A company is about to begin production of a new product. The manager of the department that will produce one of the components for the product wants to know how often the machine used to produce the item will be available for other work. The machine will produce the item at a rate of 200 units a day. Eighty units will be used daily in assembling the final product. Assembly will take place five days a week, 50 weeks a...

  • Joe Birra needs to purchase malt for his microbrewery production. His supplier charges $35 per delivery...

    Joe Birra needs to purchase malt for his microbrewery production. His supplier charges $35 per delivery (no matter how much is delivered) and $1.20 per gallon. Joe’s annual holding cost per unit is 35 percent of the price per gallon. Joe uses 250 gallons of malt per week. Suppose Joe orders 1000 gallons each time. What is his average inventory (in gal)? Suppose Joe orders 1500 gallons each time. How many orders does he place with his supplier each year?...

  • Need help on E, F, and G. PA 12-3 Joe Birra needs to purchase malt for...

    Need help on E, F, and G. PA 12-3 Joe Birra needs to purchase malt for his... Joe Birra needs to purchase malt for his micro-brew production. His supplier charges $40 per delivery (no matter how much is delivered) and $1.25 per gallon. Joe's annual holding cost is 30% of the price per gallon. Joe uses 200 gallons of malt per week. a. Suppose Joe orders 125 gallons each time. What is his average inventory? gallons (Round your answer to...

  • Bruno Fruscalzo decided to start a small production facility in Sydney to sell gelato to the...

    Bruno Fruscalzo decided to start a small production facility in Sydney to sell gelato to the local restaurants. His local milk supplier charges $0.5 per kg of milk plus a $25 delivery fee (that is independent of the amount ordered). Bruno’s holding cost is $0.03 per kg per month. He needs 9750 kgs of milk per month. a. Suppose Bruno orders 9750 kgs each time. What is his average inventory (kgs)? kgs (Round your answer to 1 decimal place.) b....

  • Bruno Fruscalzo decided to start a small production facility in Sydney to sell gelato to the...

    Bruno Fruscalzo decided to start a small production facility in Sydney to sell gelato to the local restaurants local milk supplier charges $0.5 per kg of milk plus a $25 delivery fee (that is independent of the amount ordered). Bruno's holding cost is $0.03 per kg pe . His r month. He needs 9750 kgs of milk per month. Suppose Bruno orders 9750 kgs each time. What is his average inventory a. (kgs)? 4,875kgs (Round your answer to 1 decimal...

  • Part 1 Banana Inc. currently needs exactly 600 LCD screens per month for their smartphones. They...

    Part 1 Banana Inc. currently needs exactly 600 LCD screens per month for their smartphones. They currently order 450 screens in every order. The contracted price for screens is $20 per unit and they have calculated the storage and other inventory holding costs to be 30% of the price per year per item. Other costs associated with ordering (per order) are: - Order placement fees (documentation, network support): $100 - Delivery costs (Fuel, Driver, Truck, etc.): $150 - Cost of...

  • QUESTION 2 A company is about to begin production of a new product. The manager of the department wants to know how often the machine used to produce the current item will be available for the produc...

    QUESTION 2 A company is about to begin production of a new product. The manager of the department wants to know how often the machine used to produce the current item will be available for the production of the new product. The machine produces the current item at a rate of 220 units a day. 70 units will be used daily in assembling the final product. Assembly takes place five days a week, 50 weeks a year. The manager estimates...

  • I Think I have the first part down. I just need help on the last four questions with the 12 day cycle. Thank you! A company is about to begin production of a new product. The manager of the departmen...

    I Think I have the first part down. I just need help on the last four questions with the 12 day cycle. Thank you! A company is about to begin production of a new product. The manager of the department wants to know how often the machine used to produce the current item will be available for the production of the new product. The machine produces the current item at a rate of 170 units a day. 80 units will...

  • Inventory Management

    The H.A.L. Computer Store sells a printer for $230. Demand for this is constant during the year, and monthly demand is forecasted to be 52 units. The holding cost is $22 per unit per year, while the cost of ordering is $45 per order. Currently, the company is ordering 12 times per year (60 units each time). There are 260 working days per year and the lead-time is 7 days.REMEMBER TO EXPLICITLY WRITE THE FORMULAS USED.a.)  Given the current policy of ordering 60 units at a time, what is the total of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT