Create a Work Breakdown Structure ( WBS) for a design & build project of your choosing (phone app)
10 – 15 tasks
Establish precedents
Determine critical path
Determine finish date (or time)
WBS for a Design and Build Project
Task | Precedent | Time (days) |
A | None | 4 |
B | A | 6 |
C | A | 3 |
D | B | 6 |
E | D | 14 |
F | C | 5 |
G | E,F | 2 |
H | G | 2 |
I | G | 3 |
J | H,I | 4 |
K | J | 2 |
STEP 1: Initial Network diagram
STEP 2: Deterministic time network graph
Step 4: Identifying the connected paths
A,B,D,E,G,H,J,K
A,B,D,E,G,I,J,K
A,C,F,G,H,J,K
A,C,F,G,I,J,K
STEP 5: Identifying time for each path
Path | Finish Time (days) |
A,B,D,E,G,H,J,K | 40 |
A,B,D,E,G,I,J,K | 41 |
A,C,F,G,H,J,K | 22 |
A,C,F,G,I,J,K | 23 |
STEP 6: identifying the critical path and finish time
The critical path is A,B,D,E,G,I,J,K since this is the longest connected path with a finish time of 41 days.
Create a Work Breakdown Structure ( WBS) for a design & build project of your choosing...
Project Management - Creating a Work-Breakdown Structure (WBS) Produce a WBS of at least 3 levels (1.1.1) for a "Fun Walk-or-Run" event, intended to raise money for the local community. A minimum of 6 tasks of at least 3 levels (1.1.1) need to be identified. Thank you.
Create a work breakdown for the project, the WBS should include up to the third level and must demonstrate dividing work up to multiple work items. A graphic chart must be used. Information :You have decided to enter a South African innovative App competition. The competition requires you (and your team) to think of an innovative idea that could lead to the development of an App aimed at assisting and benefiting south African citizens in the following category: (Government services)Some fundamental...
Work Breakdown Structure (WBS) Based on your understanding of project planning and budgeting, express your views on the following: What is scope planning and scope creeping? What are some of the ways to avoid problems and manage scope correctly? You've been assigned the project of setting up a LAN with a broadband connection in your office. You need to provide internet connectivity for web browsing to all users. All the computers have Microsoft Windows 7 software installed. Based on your...
Application Work Breakdown Structure In a single-person endeavor, it is relatively easy to understand the duties and responsibilities of the person. However, when you work in groups, the work should be distributed as appropriately as possible among the team members. As a PM, you can create a diagram called the work breakdown structure (WBS), which specifies the activities that need to be carried out and the responsibilities of the individuals. Complete the following tasks: 1. Write a set of tasks...
What differentiates a list of project requirements from a work breakdown structure (WBS)? What is the importance of developing a WBS to manage a project? How does the WBS contribute to the success of a project? Once the project schedule is finalized, what are the tools you can use to monitor the schedule? How do you handle resource over allocation? What are the advantages and disadvantages of fast-tracking a project?
Create a Work break down structure (WBS) for the following project case. The WBS should be organized by either “phase” or “project management process groups.” Break down the work to Level 3. The case description is simple. Thus, go beyond the case description and be creative to include additional detailed tasks. ---------------[Case] ----------------------- Project for building a new, state-of-the-art multimedia classroom for your organization within the next five months and the budget is $200,000. The classroom should include 40 high-end...
For traveling to college 2. Create a work breakdown structure with at least 10 tasks in the below format Duration (Minutes) (2 marks) I. Predecessor Tasks Task No Description Setting up alarm 2 1 1 30 Perform Ablutions 1 Prepare Breakfast 15 4 (5 marks) (3 marks) Transform this task list into a PERT/CPM chart A. Calculate Critical Path to reach college B.
QUESTION 22 Is the conversion of a project work breakdown structure (WBS) into an operating timetable. O Project budget O Project schedule O Project scope O Project resources QUESTION 23 People are the most valuable resource in your project O True False QUESTION 24 A common mistake in project management is to appoint as project manager an individual with excellent skills but weak skills. O Technical; Managerial O Managerial: Technical O Technical: Social O Social: Managerial
Please help!! 2.) Why do you think a Work Breakdown Structure (WBS) could be critical for developing an effective time management schedule?
What are the key elements and their associated risks of a work breakdown structure (WBS) in project development of COVID-19 emergency response plan for a community of 5600 members and a project budget of $250,000?