Question

For traveling to college 2. Create a work breakdown structure with at least 10 tasks in the below format Duration (Minutes) (

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The solution for the problem is provided below, please comment if any doubts:

1. The work break down can be done as given below

Task No

Description

Duration(Minutes)

Predecessor Tasks

1

Setting up alarm

2

*

2

Perform Ablutions

30

1

3

Prepare Breakfast

15

1

4

Eat breakfast

10

1, 2, 3

5

Pack Tiffin

5

3

6

Dress up

10

1, 2, 3, 4, 5

7

Pack the college bag

5

1, 3, 5

8

Collect the necessary items

5

1, 2, 3, 4, 5, 6, 7

9

Wear the shoes

2

1, 2, 3, 4, 5, 6, 7, 8

10

Travel to college

10

1,2,3,4,5,6,7,8,9,10

2. PERT chart of the task list:

10

3. The critical path analysis for the task is provided below:

Milestone

Earliest

start

Latest

start

Earliest

Finish

Latest

Finish

1

0

0

2

2

2

2

2

32

32

3

2

2

17

17

4

17

32

27

42

5

17

17

22

22

6

42

42

52

52

7

22

22

27

27

8

52

52

57

57

9

57

57

59

59

10

59

5

69

69

Thus the critical path length is= 69

Add a comment
Know the answer?
Add Answer to:
For traveling to college 2. Create a work breakdown structure with at least 10 tasks in...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Given the following construction project tasks and estimated durations: • Prepare foundation (3 d...

    Given the following construction project tasks and estimated durations: • Prepare foundation (3 days). • Assemble building (5 days). • Once the building is assembled, start the next two tasks at once: interior work (5 days) and landscaping (5 days). • Once the interior work is done, do the painting (2 days). • Once the landscaping is done, pave the driveway (1 day) • Once all tasks are completed, conduct the final inspection (1 day). Prepare a PERT/CPM chart for...

  • This project aims to develop an online bookstore system that acts as a central database containing...

    This project aims to develop an online bookstore system that acts as a central database containing various books in stock along with their title, author’s name, published date, and cost. This project, basically a website, will get a large amount of online visitors. The system should be hosted on a cloud platform in order to avoid site crash. The project can be developed using Java (front end support) and SQL (back end support). The online bookstore stores various book related...

  • The software developing firm, Flow Associates, is rolling out the new software. They are calling a...

    The software developing firm, Flow Associates, is rolling out the new software. They are calling a meeting of the potential customers to demonstrate the new software. To setup the meeting requires several tasks to be performed in a designated time period. Based on the management briefing, the system analyst came up with the following paragraph. First reserve the meeting room. Then order the marketing material and brief the managers. After the briefing send put the customer emails and burn sample...

  • 2. Using the information in Table 1, assuming that the project team will work a standard...

    2. Using the information in Table 1, assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible: Table 1: Project description Task Description Predecessor/s Duration (working days) 5 15 25 15 A B A B с D E F G H Requirement Analysis Systems Design Programming Telecoms Hardware Installation Integration System Testing Training/Support Handover and Go-Live B B 30 CD E, F 10...

  • Q1.      (10 marks) Construct an activity on arrow network based on the activity descriptions below. Show...

    Q1.      (10 marks) Construct an activity on arrow network based on the activity descriptions below. Show all your work. Label activities in the network by their activity letters and node numbers. Remove any redundant dependencies and label dummy activities DUMMY1, DUMMY2, etc. • Activities H, R2, T1 start the project. • Activity T2 can start when Activities H, E1 and S are completed. • Activity E1 also depends on Activity R2. • Activity X follows Activity H and precedes Activity...

  • al Industries are likely to use 4 At Webster University, where you work as a project...

    al Industries are likely to use 4 At Webster University, where you work as a project manager, you have been asked to conduct user training sessions for a new information system. You must develop a specific schedule for the tasks (the estimated task duration for each is shown in parentheses): . First, confirm arrangements for the training facility you plan to use (2 days). • After you have confirmed the training facility, two tasks can begin at the same time:...

  • Assignment 2 Question 1 Your company was awarded a culvert contract. The contract manager has appointed...

    Assignment 2 Question 1 Your company was awarded a culvert contract. The contract manager has appointed you to manage the project and has requested you to provide a schedule for the client. The contract manager handed you the table below, showing a breakdown of activities involved, together with their duration. The Start date is the 01/02/2021 (1st February 2021) Working week of 5 days, 40 hours must be use. Task Name 1 Setting out Excavation 2 Earthworks/Site Clearing 3 Bulk...

  • Microsoft Project Assignment Description A system development project has been defined to contain the following list of...

    Microsoft Project Assignment Description A system development project has been defined to contain the following list of activities along with their estimated times for completion. The project will start on 5/1/2019. Project Data Provided: Activity ID Activity Name Days Predecessors Optimistic(O) Realistic(R) Pessimistic(P) 1 Gather Requirement 1 2 3 2 Analyze processes 1 2 6 1 3 Define DFDs 0.5 1 1.5 2 4 Design Processes 2 7 12 2 5 Design database 4 7 22 3 6 Design UI...

  • Question 2 XYZ Industrial Machines has initiated a large client project to design, manufacture and instal a spoke plastics forming machine at a local manufacturing site. At this pre-project ph...

    Question 2 XYZ Industrial Machines has initiated a large client project to design, manufacture and instal a spoke plastics forming machine at a local manufacturing site. At this pre-project phase, it has sembled a project planning team and is undertaking discussions with the client to produce a mgheve pct plan. A range of key tasks have been identified and a logical network diagram for high-level the project has been developed. Project task information is provided in the following table (Table...

  • Develop a work breakdown structure (WBS) based on the following narrative. It should cover all aspects...

    Develop a work breakdown structure (WBS) based on the following narrative. It should cover all aspects of the move—from the beginning of the project (now) to the end, when all employees are moved into their new offices. Format your solution in tabular form with the following column headings: Task ID No, Task Description, Estimated Effort, Predecessor Task ID. For your solution, follow these guidelines: ■ Include dependencies. ■ Include effort (work) estimates. ■ Have 30 to 40 detailed tasks. ■...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT