Question

Question 2 XYZ Industrial Machines has initiated a large client project to design, manufacture and instal a spoke plastics fo

Using the initial logical network structure within Figure 1 as a foundation di , complete the a) agram using suitable Activit

Question 2 XYZ Industrial Machines has initiated a large client project to design, manufacture and instal a spoke plastics forming machine at a local manufacturing site. At this pre-project phase, it has sembled a project planning team and is undertaking discussions with the client to produce a mgheve pct plan. A range of key tasks have been identified and a logical network diagram for high-level the project has been developed. Project task information is provided in the following table (Table as ) and the initial logical network diagram (Figure 1) has been additionally outlined Notes pecal Compary rangre ans Resource OrZ) Activity DurationResource (Days) Requirement 30 10 10 40 10 20 30 10 20 40 10 20 15 10 15 10 50 10 15
Using the initial logical network structure within Figure 1 as a foundation di , complete the a) agram using suitable Activity project duration proluitable Activity on Node (AoN) or PERT notation to calculate the minimum [6 marks) b) Provide a time-based schedule (Gantt chart) diagram and resource histogram for the project, based upon an early start assumption. Clearly indicate the critical path for the project within your work [14 marks] c) Discuss how the concept of activity float' and improved resource planning may be used to adjust the schedule to provide a feasible and effective implementation for the XYZ Industrial Machines project. [5 marks]
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Critical path is GHJ with duration 75.

Resource allocation schedule.

Days 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
Activity A B B C C C C I I
Activity G G H H H H H H H H J J J
Activity D D D E E F F F
Resources 60 40 60 60 60 30 30 30 30 30 20 20 40 40 40

Gantt chart

Days 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
J
I
H
G
F
E
D
C
B
A

(c) This project has a constraint, which is the availability of resource XYZ which is limited to 60. This constraint makes it possible to schedule only those activities in each period which have a total resource requirement less than or equal to 60. The float in each activity, which is not on critical path is used to delay it by some duration to satisfy the constraint of availability of XYZ and still complete the project within stipulated 75 days, as shown in the resource chart.

Add a comment
Know the answer?
Add Answer to:
Question 2 XYZ Industrial Machines has initiated a large client project to design, manufacture and instal a spoke plastics forming machine at a local manufacturing site. At this pre-project ph...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 2 XYZ Industrial Machines has initiated a large client project to design, manufacture and instal...

    Question 2 XYZ Industrial Machines has initiated a large client project to design, manufacture and instal a spoke plastics forming machine at a local manufacturing site. At this pre-project phase, it has sembled a project planning team and is undertaking discussions with the client to produce a mgheve pct plan. A range of key tasks have been identified and a logical network diagram for high-level the project has been developed. Project task information is provided in the following table (Table...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT