Question

Given the following construction project tasks and estimated durations: • Prepare foundation (3 d...

Given the following construction project tasks and estimated durations: • Prepare foundation (3 days). • Assemble building (5 days). • Once the building is assembled, start the next two tasks at once: interior work (5 days) and landscaping (5 days). • Once the interior work is done, do the painting (2 days). • Once the landscaping is done, pave the driveway (1 day) • Once all tasks are completed, conduct the final inspection (1 day).

Prepare a PERT/CPM chart for this project and identify the overall project duration and critical path. Please charts are must a CPM and the PERT

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Hey, here's the solution

Activity Symbol Activities Days
A Foundation              3
B Assembly Building              5
C Interior Work              5
D Landscaping              5
E Paiting              2
F Driveway              1
G Final Inspection              1

E-13 L=8 1-13 5DAYS 5DAYS E-15 E-16 L-16 YS L-15 1 DAY 8 3DAYS E=3 E=0 L=0 L=3 4 6 5DAYS 5 DAYS 1 DAY E-13 L-14 L=9 OVERALL P

Add a comment
Know the answer?
Add Answer to:
Given the following construction project tasks and estimated durations: • Prepare foundation (3 d...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • al Industries are likely to use 4 At Webster University, where you work as a project...

    al Industries are likely to use 4 At Webster University, where you work as a project manager, you have been asked to conduct user training sessions for a new information system. You must develop a specific schedule for the tasks (the estimated task duration for each is shown in parentheses): . First, confirm arrangements for the training facility you plan to use (2 days). • After you have confirmed the training facility, two tasks can begin at the same time:...

  • Scenario: Your organisation, ABC construction group has made a winning bid to construct a new manufacturing...

    Scenario: Your organisation, ABC construction group has made a winning bid to construct a new manufacturing plant. The client expects the plant to be functional within a year. You are assigned as the Project Manager to ensure that the whole project stays on schedule. The two important conditions as per the client contract are:- ABC construction group will incur a penalty if the work is not completed by the deadline of 47 weeks from now. ABC construction group will be...

  • Question #1: Some of the tasks in this project can be done in parallel. Prepare a...

    Question #1: Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required network of tasks and define the critical path. What is the length of the project without crashing? Do not just answer, but show the whole process. Question #2: If the critical path is longer than 29 days, what is the least additional amounting that Dr. Watage can spend and still achieve this schedule objective (29 days)? Do not just answer,...

  • Hello, I need help in the following exercises from book: Project Management: Achieving competitive advantage (4th...

    Hello, I need help in the following exercises from book: Project Management: Achieving competitive advantage (4th ed.).Jeffery Pinto Exercise 9.1 Consider the following information that you have compiled re- garding the steps needed to complete a project. You have identi- fied all relevant steps and have made some determinations re- garding predecessor/successor relationships. Using MS Project, develop a simple network diagram for this project, showing the links among the project activities. Activity Predecessors A – Survey site — B –...

  • Microsoft Project Assignment Description A system development project has been defined to contain the following list of...

    Microsoft Project Assignment Description A system development project has been defined to contain the following list of activities along with their estimated times for completion. The project will start on 5/1/2019. Project Data Provided: Activity ID Activity Name Days Predecessors Optimistic(O) Realistic(R) Pessimistic(P) 1 Gather Requirement 1 2 3 2 Analyze processes 1 2 6 1 3 Define DFDs 0.5 1 1.5 2 4 Design Processes 2 7 12 2 5 Design database 4 7 22 3 6 Design UI...

  • Problem 15-7 Consider the following table of precedence relationships for a portion of a house building...

    Problem 15-7 Consider the following table of precedence relationships for a portion of a house building project: Task Duration Estimates Immediate Predecessor(s) A Prepare Site 3 days None B Install Rough Plumbing 2 days Prepare Site C Pour Concrete Foundation 3 days Install Rough Plumbing D Concrete Curing Time 4 days Pour Concrete Foundation E Preassemble Wall Frames 6 days None F Erect Wall Frames 2 days Preassemble WF, Cure Concrete G Install Roof 1 day Erect Wall Frames H...

  • 1. Develop a network drawing for Hill Construction and determine the critical path. How long is...

    1. Develop a network drawing for Hill Construction and determine the critical path. How long is the project expected to take? 2. What is the probability of finishing in 270 days? 3. If it is necessary to crash to 250 or 240 days, how would Hill do so, and at what costs? As noted in the case, assume that optimistic time estimates can be used as crash times. Southwestern University: (A)* Southwestern University (SWU), a large state college in Stephenville,...

  • Case #2 Table 2 Family Planning Research Center Costs Activity A В. Crash Time (days) 3...

    Case #2 Table 2 Family Planning Research Center Costs Activity A В. Crash Time (days) 3 4 2 1 3 Normal Time (days) 6 8 4 3 7 5 3 6 7 10 10 Dr. John Watage, deputy director of the family planning Research Center in Nigeria's Over-The-River Providence, was assigned the task of organizing and training five teams of field workers to perform educational and outreach activities as part of a large project to demonstrate acceptance of a new...

  • only number 3 3 Southwestern University South Day Sweate AL One of m' demanding Wha wad....

    only number 3 3 Southwestern University South Day Sweate AL One of m' demanding Wha wad. With dance. WU to face the head on. Althoch alarm wing and some seriously Wisner, president of Southwester Unity deci to Adding thods of all, including of boxes, would not please everyone. The went argued the foreftad tory for his players and a place App the couch of a fare NCAA champion Bondag pobability of 1 The bow to get to de 2015 eded....

  • just need 2 and 3 Southwestern University (A) Southwester Unity Swage wat AL dom ACTIVE Bonde...

    just need 2 and 3 Southwestern University (A) Southwester Unity Swage wat AL dom ACTIVE Bonde . One of a demandej ad With dance w to face the head on Auch cal armwrestling and some seriously Wisme president of Southwestern University, decision to expand the capacity at Adding thods of all, including of boxes, would not please everyone. The argued them for a festa di un tory for his players and a paleta office app the couch of a future...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT