V Company use multiple department rates to apply manufacturing overhead. The shoe department applies overhead using predetermined overhead rate based on direct labor hours of 4.25. The boot department applies overhead using a predetermined overhead rate based on machine hours of 5.75. For job 990 the shoe department had 500 direct labor hours and 200 machine hours. Also for job 990, the boot department had 100 direct labor hours and 400 machine hours. Total direct materials used for job 990 was 1500. How much total manufacturing overhead was applied to job 990? And what were the total manufacturing costs for job 990

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:

Manufacturing Overhead applied to Shoe Department = $4.25 * 500
Manufacturing Overhead applied to Shoe Department = $2,125

Manufacturing Overhead applied to Boot Department = $5.75 * 400
Manufacturing Overhead applied to Boot Department = $2,300

Total Manufacturing Overhead applied to Job 990 = $2,125 + $2,300
Total Manufacturing Overhead applied to Job 990 = $4,425

Total Manufacturing Cost = Direct Materials + Direct Labor + Manufacturing Overhead
Total Manufacturing Cost for Job 990 = $1,500 + $0 + $4,425
Total Manufacturing Cost for Job 990 = $5,925

Add a comment
Know the answer?
Add Answer to:
V Company use multiple department rates to apply manufacturing overhead. The shoe department applies overhead using...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Muldorf, Inc. has two manufacturing departments, Forming and Assembly. The company applies manufacturing overhead to jobs...

    Muldorf, Inc. has two manufacturing departments, Forming and Assembly. The company applies manufacturing overhead to jobs using a predetermined rate based on machine hours in the Forming Department and on direct labor hours in the Assembly Department. Information used to compute predetermined rates is given below: Forming Assembly Estimated total manufacturing overhead cost $325,000 $200,000 Estimated machine hours 100,000 50,000 Estimated direct labor hours 25,000 80,000 Job 99 required 400 machine hours in the Forming Department and 200 direct labor...

  • Problem 3-21 (Algo) Plantwide Versus Multiple Predetermined Overhead Rates (LO3-1, LO3-2] Mason Company has two manufacturing...

    Problem 3-21 (Algo) Plantwide Versus Multiple Predetermined Overhead Rates (LO3-1, LO3-2] Mason Company has two manufacturing departments-Machining and Assembly. The company considers all of its manufacturing overhead costs to be fixed costs. It provided the following estimates at the beginning of the year as well as the following Information with respect to Jobs A and B: $ Estimated Data Manufacturing overhead Direct labor hours Machine hours Machining $ 1,008,000 12,000 84,000 Assembly 144,000 84,000 7,000 Total $1,152,000 96,000 91,000 Machining...

  • Question 9 8 pts 1. The Collins Company uses predetermined overhead rates to apply manufacturing overhead...

    Question 9 8 pts 1. The Collins Company uses predetermined overhead rates to apply manufacturing overhead to jobs. The predetermined overhead rate is based on labor costs in Dept. A and machinebours in Dept. B. at the beginning of the year, the company made the following estimates: Dept.A Dept. B Direct Labor cost........................ $65,000 $42.000 Manufacturing overhead..................$91,000 $48,000 Direct Labor-hours.......................8,000 hours 10,000 hours Machine hours........................... 3,000 hours 12.000 hours a. What is the predetermined overhead rate for department A? b....

  • High Desert Potteryworks.... show steps if possible Problem 2-19 Multiple Predetermined Overhead Rates; Applying Overhead LO21,...

    High Desert Potteryworks.... show steps if possible Problem 2-19 Multiple Predetermined Overhead Rates; Applying Overhead LO21, LO2-2, Lo24) High Desert Potteryworks makes a variety of pottery products that it sells to retailers. The company uses a job-order costing system in which departmental predetermined overhead rates are used to apply manufacturing overhead cost to jobs. The predetermined overhead rate in the Molding Department is based on machine-hours, and the rate in the Painting Department is based on direct labor- hours. At...

  • Hill Manufacturing uses departmental cost driver rates to apply manufacturing overhead costs to products. Manufacturing overhead...

    Hill Manufacturing uses departmental cost driver rates to apply manufacturing overhead costs to products. Manufacturing overhead costs are applied on the basis of machine-hours in the Machining Department and on the basis of direct labor-hours in the Assembly Department. At the beginning of 20X5, the following estimates were provided for the coming year: Machining Assembly Direct labor-hours 10,000 dlh 90,000 dlh Machine-hours 100,000 mh 5,000 mh Direct labor cost $ 80,000 $720,000 Manufacturing overhead costs $250,000 $360,000 The accounting records...

  • problem 2-19 Multiple Predetermined Overhead Rates; Applying Overhead (LO2-4, LO2-2, L02-4) High Desert Potteryworks makes a...

    problem 2-19 Multiple Predetermined Overhead Rates; Applying Overhead (LO2-4, LO2-2, L02-4) High Desert Potteryworks makes a variety of pottery products that it sells to retailers. The company uses a job-order costing system in which departmental predetermined overhead rates are used to apply manufacturing overhead cost to jobs. The predetermined overhead rate in the Molding Department is based on machine hours, and the rate in the Painting Department is based on direct labor hours. At the beginning of the year, the...

  • Problem 2-21 Plantwide Versus Multiple Predetermined Overhead Rates (L02-1, LO2-2) Mason Company has two manufacturing departments-Machining...

    Problem 2-21 Plantwide Versus Multiple Predetermined Overhead Rates (L02-1, LO2-2) Mason Company has two manufacturing departments-Machining and Assembly. The company considers all of its manufacturing overhead costs to be fixed costs. It provided the following estimates at the beginning of the year as well as the following information with respect to Jobs A and B: Estimated Data Manufacturing overhead Direct Labor hours Machine hours Machining Assembly $2,816,800 $ 256,000 16,000 176,000 176,000 11,000 Total $3,072,000 192,000 187,000 Job Direct labor...

  • Please answer all parts! Thank you! Problem 2-19 Multiple Predetermined Overhead Rates; Applying Overhead (LO2-1, LO2-2,...

    Please answer all parts! Thank you! Problem 2-19 Multiple Predetermined Overhead Rates; Applying Overhead (LO2-1, LO2-2, LO2-4) High Desert Potteryworks makes a variety of pottery products that it sells to retailers. The company uses a job-order costing system in which departmental predetermined overhead rates are used to apply manufacturing overhead cost to jobs. The predetermined overhead rate in the Molding Department is based on machine-hours, and the rate in the Painting Department is based on direct labor- hours. At the...

  • The Silver Corporation uses a predetermined overhead rate to apply manufacturing overhead to jobs. The predetermined...

    The Silver Corporation uses a predetermined overhead rate to apply manufacturing overhead to jobs. The predetermined overhead rate is based on labor cost in Dept. A and on machine-hours in Dept. B. At the beginning of the year, the Corporation made the following estimates: Direct labor cost Manufacturing overhead Direct labor-hours Machine-hours Dept. A Dept. B $60,000 $40,000 $90,000 $45,000 6,000 9,000 2,000 15,000 What predetermined overhead rates would be used in Dept. A and Dept. B, respectively? Multiple Choice...

  • Problem 2-19 Multiple Predetermined Overhead Rates; Applying Overhead (LO2-1, LO2-2, LO2-4) High Desert Potteryworks makes a...

    Problem 2-19 Multiple Predetermined Overhead Rates; Applying Overhead (LO2-1, LO2-2, LO2-4) High Desert Potteryworks makes a variety of pottery products that it sells to retailers. The company uses a job-order costing system in which departmental predetermined overhead rates are used to apply manufacturing overhead cost to jobs. The predetermined overhead rate in the Molding Department is based on machine-hours, and the rate in the Painting Department is based on direct labor- hours. At the beginning of the year, the company...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT